- Type: Service difficulty report (as reported; unverified)
- Difficulty date: January 3, 1995
- Submitted: March 26, 2000
- Operation: Air carrier
- Aircraft: [N401EA](https://openairdocs.org/aircraft/N401EA), registered now
- Make and model: Doug DC-9-51
- Registry model: [Doug DC-9-51](https://openairdocs.org/model/mcdonnell-douglas-dc-9-51) (OpenAirDocs)
- Aircraft serial: 47682
- Engine: Pwa JT8D17
- System (JASC): [7320 · Fuel Controlling System](https://openairdocs.org/jasc/7320)
- Part: Pt2 Probe
- Condition: Iced Up
- Location: Nr 1 Engine
- Stage of operation: TO
- Nature of condition: R
- Precautionary procedure: C, D
- FAA source: FAA Service Difficulty Reporting System (https://sdrs.faa.gov/)
- Page: https://openairdocs.org/sdr/9600559885

## Discrepancy

NR 1 ENGINE EPR DID NOT REACH TARGET ON TAKEOFF ROLL.  THE TAKEOFF WAS ABORTED AND THE FLIGHT RETURNED TO THE GATE.  MAINTENANCE INSPECTED THE ENGINE AND REMOVED ICE OBSTRUCTING THE PT2 PROBE.  ENGINE CHECKED OK ON RUNUP.

---