# SDR ASMF200501009

- Type: Service difficulty report (as reported; unverified)
- Difficulty date: January 16, 2005
- Submitted: January 18, 2005
- Operation: Air carrier
- Aircraft: N751RA
- Make and model: Doug DC-9-87
- Registry model: [Doug DC-9-87](https://openairdocs.org/model/mcdonnell-douglas-dc-9-87) (OpenAirDocs)
- Aircraft serial: 49779
- Aircraft time: 39,233 hours, 26,825 cycles
- Engine: Pwa JT8D219
- System (JASC): [2910 · Hydraulic System, Main](https://openairdocs.org/jasc/2910)
- Part: Selector Valve
- Part number: 1474253
- Part serial: 5013
- Condition: Leaking
- Location: Hyd System
- Part time: 15,947 hours, 10,900 cycles
- Stage of operation: IN
- How discovered: 9
- Nature of condition: K
- Precautionary procedure: K
- FAA source: FAA Service Difficulty Reporting System (https://sdrs.faa.gov/)
- Page: https://openairdocs.org/sdr/ASMF200501009

## Discrepancy

DURING TRANSIT CHECK WAS DETECTED AN HYDRAULIC LEAK ON RT MAIN LANDING GEAR WELL.  WELL WAS CLEANED AND SYSTEM WAS PRESSURIZED AND NO LEAK WAS DETECTED, HYDRAULIC SYSTEM WAS RECHARGED WITH 4 QUARTERS, ALL CORRECT. AT AGU, HYDRAULIC LEAK WAS DETECTED ON RIGHT SPOILER SELECTOR VALVE. SELECTOR VALVE LINES WERE TIGHTENED AND SYSTEM WAS CHECKED BY LEAKS IAW MM  29-10-26, ALL CORRECT. AT MEX VALVE WAS REPLACED AND TESTED IAW MM 29-10-06, HYDRAULIC SYSTEM WAS RECHARGED AT CORRECT LEVEL, ALL CORRECT.

---