# Airbus Service Bulletin A310-71-2038

Copy: No revision named ("U.S. DOT/FAA - SB A310-71 2038-00"), 34 pages: PDF https://openairdocs.org/files/sha256/43/5b/435b57680a86a5603000b730a867d7dae62c4c9a0a6cb163b2fd1b9fbe925755; text https://openairdocs.org/service-documents/airbus/a310-71-2038/file/435b57680a86.md. Rights: © Airbus S.A.S. Filed by the FAA in regulations.gov docket FAA-2015-0086; AD 2015-14-08 incorporates this document by reference. Not covered by OpenAirDocs’ CC0 dedication.

## Details

- Manufacturer: [Airbus](https://openairdocs.org/service-documents/airbus.md)
- Type: Service bulletin (Service Bulletin)
- Number: A310-71-2038
- Page: https://openairdocs.org/service-documents/airbus/a310-71-2038

## ADs that cite it (1) (OpenAirDocs)

Newest first, with the revision each names, as OpenAirDocs read it from the AD's text.

- [AD 2015-14-08](https://openairdocs.org/ad/2015-14-08.md), effective Aug 20, 2015: No revision named

Also cited in [1 proposed AD](https://openairdocs.org/service-documents/airbus/a310-71-2038/proposed.md).

## Text (34 pages)

Rights: © Airbus S.A.S. Filed by the FAA in regulations.gov docket FAA-2015-0086; AD 2015-14-08 incorporates this document by reference. Not covered by OpenAirDocs’ CC0 dedication. Some pages are OCR from a scan. OCR can misread letters and numbers. Each page's text from the PDF; open the PDF at a page with #page=N.

### Page 1

@A310
SERVICE BULLETIN
SUMMARY
AIRBUS
CUSTOMER SERVICES DIRECTORATE
1 Rond Point Maurice Bellonte
31707 BLAGNAC CEDEX
FRANCE
T e l:( 3 3 )56 19 33 33 3
Telex : AIRBU 530526F
F a x:( 3 3 )56 19 34 25 1
This summary is for information only and is not approved for modification of the aircraft.
MANDATORY
 MANDATORY
 MANDATORY
ATA SYSTEM: 71
TITLE: POWER PLANT - GENERAL - REPLACEMENT OF CF6-80A3 SIDE LINK
CLEVIS ENGINE MOUNT BOLTS
**CONF ALL
MODIFICATIONS
None
REASON/DESCRIPTION/OPERATIONAL CONSEQUENCES
The side link clevis bolts of the CF6-80A3 front engine mount have a time limitation from their
installation, calculated with the fatigue lives of the bolts and the yearly fleet leader data. They must be
replaced by new ones at the next engine removal without exceeding 18 months from Service Bulletin
issue date. Replacement by brand new bolts is then to be repeated at an interval of 29 years.
This Service Bulletin details the replacement plan for all side link clevis bolts of the CF6-80A3 front
engine mount before they achieve their fatigue life limitation. New bolts will have to be marked by one
or several cross(es) depending on the number of replacements already done, to differentiate them from
the old ones.
Accomplishment of this Service Bulletin will replace the FWD engine mounts bolts (side link clevis bolts)
before they reach their life limit.
GENERAL EVALUATION
EVALUATION TABLE
COMPLIANCE
 MANDATORY (1)
 CANCELS INSPECTION SB
 NO
POTENTIAL AD
 YES
 A/C OPERATION AFFECTED
 NO
RELIABILITY AFFECTED
 NO
 PAX COMFORT AFFECTED
 NO
COST SAVING
 NO
 ETOPS AFFECTED
 NO
STRUCTURAL LIFE EXTN
 NO
 VENDOR SB INVOLVED
 NO
NOTE
 (1)
: Service Bulletin must be accomplished.
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 1
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 2

@A310
SERVICE BULLETIN
SUMMARY
MATERIAL PRICE INFORMATION
MATERIAL PRICE INFORMATION TABLE
MATERIAL SET
 QTY PER
A/C
PRICE PER
A/C (USD)
MAIN PARTS
Equipment BFEA01
 1
 See SB
 Bolt, Nut, Bushing.
EFFECTIVITY
This Service Bulletin is applicable to this (these) operator(s) :
FDX
CONCURRENT REQUIREMENTS
None
REFERENCES / REPERCUSSIONS
TFU
 None
OEB
 None
AOT
 None
SIL
 None
LINE MAINTENANCE AFFECTED
 No
LIFE LIMIT
 None
NATURE OF THE WORK
AIRCRAFT
 NO
EQUIPMENT
 YES
HARD
 NO
SOFT
 NO
OBRM
 NO
MANPOWER
Task 712038-832-801-001: Replace the Forward Engine Mount Side Link Clevis Bolts
TOTAL MANHOURS
 142.00
ELAPSED TIME (HOURS)
 23.00
APPENDICES
Appendix 01 - Elapsed Time Assumption
Appendix 02 - GE SPM Dot Peen Marking
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 2
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 3

@A310
SERVICE BULLETIN
SUMMARY
**CONF ALL
Z464
Z454
A
A
B
A
B
LH SHOWN
RH SYMMETRICAL
TO BE REPLACED BY NEW
AND CROSS MARKED
B_SB_712038_5_SAAA_01_00
Figure A-FSAAA - Sheet 01
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 3
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 4

@A310
SERVICE BULLETIN
SUMMARY
This Page Intentionally Left Blank
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 4
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 5

@A310
SERVICE BULLETIN
AIRBUS
CUSTOMER SERVICES DIRECTORATE
1 Rond Point Maurice Bellonte
31707 BLAGNAC CEDEX
FRANCE
T e l:( 3 3 )56 19 33 33 3
Telex : AIRBU 530526F
F a x:( 3 3 )56 19 34 25 1
MANDATORY
 MANDATORY
 MANDATORY
ATA SYSTEM: 71
TITLE: POWER PLANT - GENERAL - REPLACEMENT OF CF6-80A3 SIDE LINK
CLEVIS ENGINE MOUNT BOLTS
MODIFICATION No.: None
This document contains AIRBUS PROPRIETARY INFORMATION and shall at all times remain the
property of AIRBUS; no intellectual property right or licence is granted by AIRBUS in connection with
any information contained in it. It is delivered on the express condition that said document and the
information contained in it shall be treated as confidential, shall not be used for any purpose other than
that for which it is hereby delivered. It shall not be disclosed in whole or in part to third parties and shall
not be duplicated in any manner (except for the purposes of performing the tasks described hereunder
and provided that any recipient of such document shall comply with the conditions herein), without
AIRBUS prior written consent.
1. PLANNING INFORMATION
**CONF ALL
A. EFFECTIVITY
NOTE
: This Service Bulletin is applicable only to aircraft equipped with GE CF6-80A3
engines.
(1) Models
310-203
(2) Effectivity by MSN
0230 0237 0245 0248 0281 0283 0316 0356 0362 0364 0369 0394 0454
(3) Effectivity by Operator
The Operator/MSN relationship is provided for information only and is correct at the time
of issue in accordance with the information available to AIRBUS. Any future changes
resulting from transfer of an aircraft from one operator to another will not be reflected in
this list unless the Service Bulletin is revised for another reason.
OPERATOR
 MSN
FDX
 0230 0237 0245 0248 0281 0283 0316 0356 0362 0364 0369 0394
0454
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 1
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 6

@A310
SERVICE BULLETIN
(4) Configuration by MSN
MSN
 CONFIGURATION
0230 0237 0245 0248 0281 0283 0316 0356 0362 0364 0369
0394 0454
001
(5) Configuration definition
**CONF 001
Config. 001 is valid for all the aircraft given in the effectivity of this Service Bulletin as a
standard configuration.
(6) Material Effectivity
MATERIAL
 QTY PER A/C
 SEE NOTES
Equipment BFEA01
 1
B. CONCURRENT REQUIREMENTS
None
C. REASON
(1) History
The side link clevis bolts of the CF6-80A3 front engine mount have a time limitation from
their installation, calculated with the fatigue lives of the bolts and the yearly fleet leader
data. They must be replaced by new ones at the next engine removal without exceeding
18 months from Service Bulletin issue date. Replacement by brand new bolts is then to
be repeated at an interval of 29 years.
(2) Objective/Action
This Service Bulletin details the replacement plan for all side link clevis bolts of the
CF6-80A3 front engine mount before they achieve their fatigue life limitation. New bolts
will have to be marked by one or several cross(es) depending on the number of
replacements already done, to differentiate them from the old ones.
(3) Advantages
Accomplishment of this Service Bulletin will replace the FWD engine mounts bolts (side
link clevis bolts) before they reach their life limit.
(4) Operational/Maintenance Consequences
None
D. DESCRIPTION
To accomplish this Service Bulletin it is necessary to :
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 2
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 7

@A310
SERVICE BULLETIN
Task 712038-832-801-001: Replace the Forward Engine Mount Side Link Clevis Bolts
(1) On Bench, Replace the LH Forward Engine Mount Side Link Clevis Bolts
(2) On Bench, Replace the RH Forward Engine Mount Side Link Clevis Bolts
E. COMPLIANCE
(1) Classification
MANDATORY: Service Bulletin must be accomplished.
(2) Accomplishment Timescale
This Service Bulletin has been classified Mandatory. It is expected that an Airworthiness
Directive (AD) published by the European Av iation Safety Agenc y (EASA) will be issued
to confirm this classification. It is anticipated that the AD will confirm the thresholds and
intervals given below but reference should be made to the AD for confirmation of the
mandated accomplishment timescale.
Table 1, Config.001: Replace the Forward Engine Mount Side Link Clevis Bolts
Condition
 Action
 Compliance Time
 Repetitive interval
All Aircraft
 Do TASK 712038-832-801
001 Replace the Forward
Engine Mount Side Link
Clevis Bolts
No later than 18
months from SB issue
date
None
Do one cross mark on the
head of the new bolt, refer
to SUBTASK
712038-832-001 002 On
Bench, Replace the LH
Forward Engine Mount Side
Link Clevis Bolts and/or
SUBTASK 712038-832-002
002 On Bench, Replace the
RH Forward Engine Mount
Side Link Clevis Bolts
and
Before Next Flight
 None
First replacement of bolt
Repeat TASK
712038-832-801 001
Replace the Forward
Engine Mount Side Link
Clevis Bolts
None
 29 Years
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 3
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 8

@A310
SERVICE BULLETIN
Table 1, Config.001: Replace the Forward Engine Mount Side Link Clevis Bolts
Condition
 Action
 Compliance Time
 Repetitive interval
Do two cross marks on the
head of the new bolt, refer
to SUBTASK
712038-832-001 002 On
Bench, Replace the LH
Forward Engine Mount Side
Link Clevis Bolts and/or
SUBTASK 712038-832-002
002 On Bench, Replace the
RH Forward Engine Mount
Side Link Clevis Bolts
and
Before Next Flight
 None
Second replacement of
bolt
Repeat TASK
712038-832-801 001
Replace the Forward
Engine Mount Side Link
Clevis Bolts
None
 29 Years
F. APPROVAL
The technical content of this document is approved under the authority of Design
Organization Approval No. EASA.21J.031.
If an aircraft listed in the effectivity has a modification or repair embodied that is not of
AIRBUS origin, and which affects the content of this Service Bulletin, the operator is
responsible for obtaining approval by its airworthiness authority for any adaptation necessary
before incorporation of the Service Bulletin.
G. MANPOWER
The manpower estimates given in this Service Bulletin are based on the direct labor cost to
do the work. These estimates assume that the work will be done by experienced personnel,
and may need to be revised upwards to suit operator’s circumstances. The estimates do not
include the time to prepare, plan or inspect the work. Manufacture and procurement of parts
and tools, drying times for paints, sealants, etc., and general administration work are also not
included.
For an explanation of the manhours and elapsed time, refer to the Gantt Chart given in
Appendix 01 - Elapsed Time Assumption .
Task 712038-832-801-001: Replace the Forward Engine Mount Side Link Clevis Bolts
Get Access
 66.00
On Bench
On Bench, Replace the LH Forward Engine Mount
Side Link Clevis Bolts
2.00
On Bench, Replace the RH Forward Engine Mount
Side Link Clevis Bolts
2.00
Close-Up
 72.00
TOTAL MANHOURS
 142.00
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 4
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 9

@A310
SERVICE BULLETIN
Task 712038-832-801-001: Replace the Forward Engine Mount Side Link Clevis Bolts
ELAPSED TIME (HOURS)
 23.00
H. WEIGHT AND BALANCE
Not Changed
I. ELECTRICAL LOAD DATA
Not Changed
J. REFERENCES
Aircraft Maintenance Manual (AMM)
 06-21-00 24-00-00 71-00-00
Elec. Std. Practices Manual (ESPM)
 20-55-00
Standards Manual (SM)
Structural Repair Manual (SRM)
 51-40-00 51-40-20 51-40-30
K. PUBLICATION AFFECTED
Aircraft Maintenance Manual (AMM)
 71-21-00
L. INTERCHANGEABILITY/MIXABILITY
Not Applicable
M. SPARES
None
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 5
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 10

@A310
SERVICE BULLETIN
This Page Intentionally Left Blank
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 6
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 11

@A310
SERVICE BULLETIN
2. MATERIAL INFORMATION
**CONF ALL
A. MATERIAL - PRICE AND AVAILABILITY
(1) Procurement Addresses
Vendor parts are to be procured from GENERAL ELECTRIC:
Equipment BFEA01
 GENERAL ELECTRIC CO ENGINE
BUSINESS GROUP
1 NEWMANN WAY PO BOX 156301
OH 45215-1915 CINCINNATI USA
(2) Price and Availability
No AIRBUS kit will be provided.
Procurement terms for the equipment must be negotiated with the equipment supplier.
B. INDUSTRY SUPPORT INFORMATION
Industry Support terms for the equipment must be negotiated with the equipment supplier.
C. LIST OF COMPONENTS
No Kit
D. LIST OF MATERIALS - OPERATOR SUPPLIED
(1) Consumable Materials
None
(2) Components
NOTE
: To accomplish this Service Bulletin it is necessary to use the expendable
parts listed in the subsequent referenced AMM task:
- AMM 71-00-00, Page Block 401
(3) Equipment
Equipment BFEA01
ITEM
 NEW PART N˚
 QTY (UM)
 KEYWORD
 ITEM
 OLD PART N˚
 INT
 SEE
NOTES
1
 9205M84P04
 4
 BOLT
 (1)
2
 9204M95P01
 8
 BUSHING
3
 9629M48P18
 4
 NUT
8
 J626P04
 4
 NUT
9
 9205M84P05
 4
 BOLT
 (1)
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 7
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 12

@A310
SERVICE BULLETIN
NOTE
: If you find part numbers of hardware components in the related kit(s)
which you cannot identify in the LIST OF COMPONENTS of this Service
Bulletin, refer to Standards Manual (SM). The SM will give you the
correct part number to part number relationship.
NOTE
: The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.
NOTE
 (1)
: Order either the one or the other Part Number:
- item 1 or item 9.
E. PARTS TO BE RE-IDENTIFIED BY OPERATOR
None
F. TOOLING
(1) Tooling - Price and Availability
None
(2) Tools
NOTE
: To accomplish this Service Bulletin it is necessary to use the tools listed
in the subsequent referenced AMM task:
- AMM 71-00-00, Page Block 401
(3) Special Tools
None
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 8
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 13

@A310
SERVICE BULLETIN
3. ACCOMPLISHMENT INSTRUCTIONS
Task 712038-832-801-001 - Replace the Forward Engine Mount Side Link Clevis Bolts
WARNING
: MAKE SURE THAT YOU OBEY ALL THE WARNINGS AND ALL THE CAUTIONS
INCLUDED IN THE REFERENCED PROCEDURES.
CAUTION
: ALWAYS OBEY THE PRECAUTIONS THAT FOLLOW TO KEEP
ELECTRICAL WIRING IN A SATISFACTORY CONDITION (ELECTRICALLY
AND MECHANICALLY SERVICEABLE) . WHEN YOU DO MAINTENANCE
WORK, REPAIRS OR MODIFICATIONS, ALWAYS KEEP ELECTRICAL WIRING,
COMPONENTS AND THE WORK AREA AS CLEAN AS POSSIBLE. TO DO
THIS:
- PUT PROTECTION, SUCH AS PLASTIC SHEETING, CLOTHS, ETC; AS
NECESSARY ON WIRING AND COMPONENTS.
- REGULARLY REMOVE ALL SHAVINGS, UNWANTED MATERIAL AND
OTHER CONTAMINATION.
THESE PRECAUTIONS WILL DECREASE THE RISK OF CONTAMINATION
AND DAMAGE TO THE ELECTRICAL WIRING INSTALLATION.
IF THERE IS CONTAMINATION, REFER TO ESPM 20-55-00.
NOTE
: The accomplishment instructions of this Service Bulletin refer to procedures
included in other AIRBUS documents. When the words ’refer to’ are used and the
operator has an accepted alternative procedure, the accepted alternative procedure
can be used. When the words ’in accordance with’ are included in the instruction,
the procedure in the AIRBUS document must be used.
NOTE
: The access and close-up instructions, not comprising return to service tests, in this
Service Bulletin do not constitute or affect the technical intent of the Service
Bulletin. Operators can therefore, as deemed necessary, omit or add access and/or
close-up steps to add flexibility to their maintenance operations as long as the
technical intent of the Service Bulletin is met within the set parameters.
NOTE
: Manual titles given in the accomplishment instructions are referred to by acronyms.
Refer to paragraph 1.J., References, for the definition of acronyms.
NOTE
: The purpose of flow charts is to supplement the information given in the Procedure
and Compliance paragraphs and not to serve as the primary source for tasks or
compliance times given in this Service Bulletin.
NOTE
: This Service Bulletin is mandated or expected to be mandated by an Airworthiness
Directive (AD). The paragraphs 3.C. and 3.D. in these accomplishment instructions
are Required for Compliance (RC) and must be done to comply with the AD. Other
paragraphs are recommended and may be deviated from, done as part of other
actions or done with accepted methods different from those given in the Service
Bulletin, as long as the RC paragraphs can be done and the aircraft can be put
back into a serviceable condition.
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 9
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 14

@A310
SERVICE BULLETIN
Task Associated Data
Zone
454 464
Manpower
TOTAL MANHOURS
 142.00
ELAPSED TIME (HOURS)
 23.00
A. GENERAL
(1) Subtask 712038-910-001-001 - Standard Practices
Manpower Resources
Skills
 NON SPECIFIC
References
Aircraft Maintenance Manual (AMM)
 06-21-00, Page Block 001
Structural Repair Manual (SRM)
 51-40-00
51-40-20
51-40-30
(a) For the identification of Zones, refer to AMM 06-21-00, Page Block 001.
(b) Remove and install fasteners in accordance with SRM 51-40-20.
(c) Obtain alternative and substitute fastener data, in accordance with SRM 51-40-30.
(d) If alternative and substitute fasteners have to be used, you must make sure that the
associated nut/collar are compatible in accordance with SRM 51-40-00 "Mating
Part" column.
(2) Subtask 712038-839-001-001 - Administrative
Manpower Resources
Skills
 NON SPECIFIC
Write in the applicable aircraft records that you have done all the work given in this
Service Bulletin.
B. PREPARATION
(1) Subtask 712038-941-001-001 - Job Set-up on the LH and RH Engines
Work Zones and Access Panels
Zone
 Access/Work location
454
464
Manpower Resources
Skills
 ENGINE
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 10
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 15

@A310
SERVICE BULLETIN
References
Aircraft Maintenance Manual (AMM)
 24-00-00, Page Block 301
71-00-00, Page Block 401
(a) The following items shall be considered as the basic Aircraft configuration before
you start a maintenance task:
- Aircraft on the ground resting on landing gear (the ground safety locks and the
wheel chocks are in position on the landing gear).
- Engine shut down, thrust reversers closed and locked.
- Aircraft in clean configuration.
- Parking brake applied.
- Aircraft electrical network de-energized.
- Hydraulic systems depressurized.
- Access to the cockpit and cabin is available.
- All circuit breakers are in closed position.
- All controls in NORM, AUTO or OFF position.
(b) Make sure that the aircraft is electrically grounded, refer to AMM 24-00-00, Page
Block 301.
(c) Put access platform(s) in position at zone 454 and 464.
(d) Put the warning notices in position to tell persons not to operate the flight controls.
(e) Do the Job Set-up procedure as specified in the removal of the power plant on LH
and RH sides, refer to AMM 71-00-00, Page Block 401.
(2) Subtask 712038-010-001-001 - Remove the LH Power Plant
Work Zones and Access Panels
Zone
 Access/Work location
454
Manpower Resources
Manhours
 32.00
Minimum number of person
 4
Subtask elapsed time
 8.00
Skills
 ENGINE
References
Aircraft Maintenance Manual (AMM)
 71-00-00, Page Block 401
(a) Remove the LH power plant, refer to AMM 71-00-00, Page Block 401.
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 11
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 16

@A310
SERVICE BULLETIN
(3) Subtask 712038-010-002-001 - Remove the RH Power Plant
Work Zones and Access Panels
Zone
 Access/Work location
464
Manpower Resources
Manhours
 32.00
Minimum number of person
 4
Subtask elapsed time
 8.00
Skills
 ENGINE
References
Aircraft Maintenance Manual (AMM)
 71-00-00, Page Block 401
(a) Remove the RH power plant, refer to AMM 71-00-00, Page Block 401.
C. PROCEDURE
(1) Subtask 712038-832-001- 002 - On Bench, Replace the LH Forward Engine Mount
Side Link Clevis Bolts
Manpower Resources
Manhours
 2.00
Minimum number of person
 1
Subtask elapsed time
 2.00
Skills
 ENGINE
Material necessary to do the job
Equipment BFEA01
ITEM
 NEW PART N˚
 QTY (UM)
 KEYWORD
 SEE
NOTES
1
 9205M84P04
 2
 BOLT
 (1)
2
 9204M95P01
 4
 BUSHING
3
 9629M48P18
 2
 NUT
8
 J626P04
 2
 NUT
9
 9205M84P05
 2
 BOLT
 (1)
NOTE
: The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.
NOTE
 (1)
: Order either the one or the other Part Number:
- item 1 or item 9.
References
Structural Repair Manual (SRM)
 51-40-20
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 12
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 17

@A310
SERVICE BULLETIN
References
Fig. A-FBAAA
Area where Bolts are to be replaced and
marked
Sheet 01
Fig. A-FBBAA
Replacement of Forward Engine Mount
Side Link Clevis Bolts
Sheet 01
Sheet 02
Fig. A-FFAAA
Flow Chart
Sheet 01
Fig. A-FRAAA
Inspection Report
Sheet 01
(a) Do the replacement of the LH Forward Engine Mount Side Link Clevis Bolts at the
threshold given in the Planning Information Paragraph E.(2) :
Refer to Fig. A-FBAAA
.
Refer to Fig. A-FFAAA
.
1
 Remove the fasteners from the Forward Engine Mount:
Refer to Fig. A-FBBAA
.
In accordance with SRM 51-40-20.
2 Side Link Clevis Bolt Item (1) Discard
4 Bushing Item (2) Discard
2 Nut Item (3) Discard
2 Nut Item (8) Discard
2 Bolt Item (4) Retain
2 Washer Item (5) Retain
2 Bracket Item (6) Retain
2 Bracket Item (7) Retain
NOTE
: PN of Side Link Clevis Bolt Item (1) include the associated
washer.
2
 Do a check of the removed side link clevis bolts:
Refer to Appendix 02 - GE SPM Dot Peen Marking .
- If there is no cross on the head of the removed bolts, then mark one
cross on the head of the new bolts.
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 13
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 18

@A310
SERVICE BULLETIN
- If there is one cross on the head of the removed bolts, then mark two
crosses on the head of the new bolts.
3
 Install the new marked fasteners on the Forward Engine Mount:
Refer to Fig. A-FBBAA
.
Refer to Appendix 02 - GE SPM Dot Peen Marking .
In accordance with SRM 51-40-20.
2 Side Link Clevis Bolts 9205M84P04 Item 1
or
2 Side Link Clevis Bolt 9205M84P05 Item 9
4 Bushing 9204M95P01 Item 2
2 Nut 9629M48P18 Item 3
2 Nut J626P04 Item 8
2 Bolt Item (4) Retained at
removal
2 Washer Item (5) Retained at
removal
2 Bracket Item (6) Retained at
removal
2 Bracket Item (7) Retained at
removal
NOTE
 (01)
: PN of Side Link Clevis Bolt Item 1 or 9 include the associated
washer.
NOTE
 (02)
: Tighten the nut Item 3 to a torque value comprised between
11.42 m.daN (1010.62 lbf.in) and 12.77 m.daN (1130.09 lbf.in).
NOTE
 (03)
: Tighten the nut item 8 to a torque value comprised between
0.62 m.daN (54.87 lbf.in) and 0.79 m.daN (69.91 lbf.in).
(b) Report accomplishment of this SB to AIRBUS, refer to Fig. A-FRAAA
.
(c) Repeat the replacement of the LH Forward Engine Mount Side Link Clevis Bolts at
the interval given in the Planning Information Paragraph E.(2).
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 14
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 19

@A310
SERVICE BULLETIN
(2) Subtask 712038-832-002- 002 - On Bench, Replace the RH Forward Engine Mount
Side Link Clevis Bolts
Manpower Resources
Manhours
 2.00
Minimum number of person
 1
Subtask elapsed time
 2.00
Skills
 ENGINE
Material necessary to do the job
Equipment BFEA01
ITEM
 NEW PART N˚
 QTY (UM)
 KEYWORD
 SEE
NOTES
1
 9205M84P04
 2
 BOLT
 (1)
2
 9204M95P01
 4
 BUSHING
3
 9629M48P18
 2
 NUT
8
 J626P04
 2
 NUT
9
 9205M84P05
 2
 BOLT
 (1)
NOTE
: The above list of components is not an AIRBUS Kit, the required parts
shall be ordered as necessary through the given channel.
NOTE
 (1)
: Order either the one or the other Part Number:
- item 1 or item 9.
References
Structural Repair Manual (SRM)
 51-40-20
Fig. A-FBAAA
Area where Bolts are to be replaced and
marked
Sheet 01
Fig. A-FBBAA
Replacement of Forward Engine Mount
Side Link Clevis Bolts
Sheet 01
Sheet 02
Fig. A-FFAAA
Flow Chart
Sheet 01
Fig. A-FRAAA
Inspection Report
Sheet 01
(a) Do the replacement of the RH Forward Engine Mount Side Link Clevis Bolts at the
threshold given in the Planning Information Paragraph E.(2) :
Refer to Fig. A-FBAAA
.
Refer to Fig. A-FFAAA
.
1
 Remove the fasteners from the Forward Engine Mount:
Refer to Fig. A-FBBAA
.
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 15
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 20

@A310
SERVICE BULLETIN
In accordance with SRM 51-40-20.
2 Bolt Item (1) Discard
4 Bushing Item (2) Discard
2 Nut Item (3) Discard
2 Nut Item (8) Discard
2 Bolt Item (4) Retain
2 Washer Item (5) Retain
2 Bracket Item (6) Retain
2 Bracket Item (7) Retain
NOTE
: PN of Side Link Clevis Bolt Item (1) include the associated
washer.
2
 Do a check of the removed side link clevis bolts:
Refer to Appendix 02 - GE SPM Dot Peen Marking .
- If there is no cross on the head of the removed bolts, then mark one
cross on the head of the new bolts.
- If there is one cross on the head of the removed bolts, then mark two
crosses on the head of the new bolts.
3
 Install the new marked fasteners on the Forward Engine Mount:
Refer to Fig. A-FBBAA
Refer to Appendix 02 - GE SPM Dot Peen Marking .
In accordance with SRM 51-40-20.
2 Side Link Clevis Bolts 9205M84P04 Item 1
or
2 Side Link Clevis Bolt 9205M84P05 Item 9
4 Bushing 9204M95P01 Item 2
2 Nut 9629M48P18 Item 3
2 Nut J626P04 Item 8
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 16
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 21

@A310
SERVICE BULLETIN
2 Bolt Item (4) Retained at
removal
2 Washer Item (5) Retained at
removal
2 Bracket Item (6) Retained at
removal
2 Bracket Item (7) Retained at
removal
NOTE
 (01)
: PN of Side Link Clevis Bolt Item 1 or 9 include the associated
washer.
NOTE
 (02)
: Tighten the nut Item 3 to a torque value comprised between
11.42 m.daN (1010.62 lbf.in) and 12.77 m.daN (1130.09 lbf.in).
NOTE
 (03)
: Tighten the nut item 8 to a torque value comprised between
0.62 m.daN (54.87 lbf.in) and 0.79 m.daN (69.91 lbf.in).
(b) Report accomplishment of this SB to AIRBUS, refer to Fig. A-FRAAA
.
(c) Repeat the replacement of the RH Forward Engine Mount Side Link Clevis Bolts at
the interval given in the Planning Information Paragraph E.(2).
D. TEST
(1) Subtask 712038-710-001-001 - Testing
Work Zones and Access Panels
Zone
 Access/Work location
454
464
Manpower Resources
Skills
 ENGINE
References
Aircraft Maintenance Manual (AMM)
 71-00-00, Page Block 401
NOTE
: This Service Bulletin requires the accomplishment of the following Tests
which are given in subtasks included in the topic Close-up. The
manhours for the tests are included in the referenced Service Bulletin
subtasks.
- Remove the safety clips and tags and close the circuit breakers
as specified after the installation of the power plant, refer to AMM
71-00-00, Page Block 401.
- Do the test procedure as specified after the installation of the power
plant, refer to AMM 71-00-00, Page Block 401.
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 17
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 22

@A310
SERVICE BULLETIN
E. CLOSE-UP
(1) Subtask 712038-400-001-001 - Install the LH Power Plant
Work Zones and Access Panels
Zone
 Access/Work location
454
Manpower Resources
Manhours
 32.00
Minimum number of person
 4
Subtask elapsed time
 8.00
Skills
 ENGINE
References
Aircraft Maintenance Manual (AMM)
 71-00-00, Page Block 401
(a) Install the LH power plant, refer to AMM 71-00-00, Page Block 401.
(2) Subtask 712038-400-002-001 - Install the RH Power Plant
Work Zones and Access Panels
Zone
 Access/Work location
464
Manpower Resources
Manhours
 32.00
Minimum number of person
 4
Subtask elapsed time
 8.00
Skills
 ENGINE
References
Aircraft Maintenance Manual (AMM)
 71-00-00, Page Block 401
(a) Install the RH power plant, refer to AMM 71-00-00, Page Block 401.
(3) Subtask 712038-942-002-001 - Close-up for the LH and RH Engines
Work Zones and Access Panels
Zone
 Access/Work location
454
464
Manpower Resources
Skills
 NON SPECIFIC
References
Aircraft Maintenance Manual (AMM)
 71-00-00, Page Block 401
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 18
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 23

@A310
SERVICE BULLETIN
(a) Do the Close-up procedure as specified after the installation of the Power Plant on
LH and RH sides, refer to AMM 71-00-00, Page Block 401.
(b) Make sure that the work areas are clean and clear of tools and other items of
equipment.
(c) Remove the WARNING NOTICES.
(d) Remove the access platforms.
(e) Restore the systems and the aircr aft to normal operating conditions.
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 19
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 24

@A310
SERVICE BULLETIN
**CONF ALL
Z464
Z454
A
A
B
A
B
LH SHOWN
RH SYMMETRICAL
TO BE REPLACED BY NEW
AND CROSS MARKED
B_SB_712038_5_BAAA_01_00
Figure A-FBAAA - Sheet 01
Area where Bolts are to be replaced and marked
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 20
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 25

@A310
SERVICE BULLETIN
**CONF ALL
Z464
Z454
A
A
B
B
AC
LH SHOWN
RH SYMMETRICAL
B_SB_712038_5_BBAA_01_00
Figure A-FBBAA - Sheet 01
Replacement of Forward Engine Mount Side Link Clevis Bolts
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 21
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 26

@A310
SERVICE BULLETIN
**CONF ALL
(4)
(5)
(6)
(7)
(8)
2
(2)
3
(3)
2
(2)
MARKING EXAMPLE
C
xx x
EXAMPLE FIRST REPLACEMENT EXAMPLE SECOND REPLACEMENT
NOTE:
TYPICAL INSTALLATION FOR LH AND RH SIDE OF THE MOUNT01
1 CROSS FOR THE FIRST REPLACEMENT, 2 CROSSES FOR THE SECOND AND SO ON
01
01
SIDE LINK
MOUNT
OR
9
1
(1)
8
TIGHTEN THE NUT ITEM 3 TO A TORQUE VALUE COMPRISED BETWEEN 11.42 m.daN (1010.62 lbf.in)02
AND 12.77 m.daN (1130.09 lbf.in)
TIGHTEN THE NUT ITEM 8 TO A TORQUE VALUE COMPRISED BETWEEN 0.62 m.daN (54.87 lbf.in)03
AND 0.79 m.daN (69.91 lbf.in)
WASHER ITEM 1 OR 9 IS A PART OF THE BOLT ASSY ITEM 1 OR 904
03
02
OR
9
1
(1) 04
B_SB_712038_5_BBAA_02_03
Figure A-FBBAA - Sheet 02
Replacement of Forward Engine Mount Side Link Clevis Bolts
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 22
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 27

@A310
SERVICE BULLETIN
**CONF ALL
NOTE:
−
DO THE REPLACEMENT OF THE FORWARD ENGINE
MOUNT SIDE LINK CLEVIS BOLTS AT THE
THRESHOLD GIVEN IN THE PLANNING
INFORMATION PARAGRAPH E.(2).
DO THE CROSS MARK ON THE HEAD OF THE NEW ENGINE MOUNT BOLTS:
1 CROSS (X) FOR THE FIRST REPLACEMENT
2 CROSSES (XX) FOR THE SECOND REPLACEMENT...
THEN REPLACE OLD FORWARD ENGINE MOUNT SIDE LINK CLEVIS BOLTS, 
BUSHING  AND NUT BY NEW ONES
(REFER TO SUBTASK 712038−832−001−002 AND SUBTASK 712038−832−002−002)
REPORT SB ACCOMPLISHMENT TO AIRBUS
REPEAT REPLACEMENT OF THE FORWARD ENGINE
MOUNT SIDE LINK CLEVIS BOLTS AT THE INTERVAL GIVEN IN
PLANNING INFORMATION PARAGRAPH E.(2).
QUESTION
ACTION
FINDING
THE PURPOSE OF FLOW CHARTS IS TO SUPPLEMENT THE  INFORMATION GIVEN IN THE
PROCEDURE AND COMPLIANCE PARAGRAPHS AND NOT TO SERVE AS THE PRIMARY
SOURCE FOR TASKS OR COMPLIANCE TIMES GIVEN IN THIS SERVICE BULLETIN.
REFER TO TASK 712038−832−801−001
REFER TO TASK 712038−832−801−001
−
B_SB_712038_5_FAAA_01_00
Figure A-FFAAA - Sheet 01
Flow Chart
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 23
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 28

@A310
SERVICE BULLETIN
**CONF ALL
INSPECTION REPORT
SERVICE BULLETIN No :
A/C MSN :
FLIGHT CYCLES :
FLIGHT HOURS :
A310−71−2038
DATE OF INSPECTION :
RETURN TO :
AIRBUS
CUSTOMER SERVICES ENGINEERING − SEEE6
NACELLE SYSTEMS
INSPECTION METHOD :
1 ROND POINT MAURICE BELLONTE
31707 BLAGNAC CEDEX
FRANCE
FAX +33 (0)5 61 93 36 14DETAILED
INSPECTION
FIRST REPLACEMENT OF BOLT ?
SECOND REPLACEMENT OF BOLT ?
YES
YES
NO
NO
B_SB_712038_5_RAAA_01_00
Figure A-FRAAA - Sheet 01
Inspection Report
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 24
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 29

@A310
SERVICE BULLETIN
Appendix 01 - Elapsed Time Assumption
**CONF ALL
(1) For an explanation of the manhours and elapsed time, refer to the following Gantt Chart.
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 1
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 30

@A310
SERVICE BULLETIN
Appendix 01 - Elapsed Time Assumption
**CONF ALL
ELAPSED TIME ASSUMPTION SERVICE BULLETIN No A310−71−2038 0102
SB ELAPSED TIME
(HOURS)
GET ACCESS 66.00 9.008
SIDE LINK CLEVIS BOLTS (LH)
REPLACEMENT OF THE FWD ENGINE MOUNT 2.00 2.001
SIDE LINK CLEVIS BOLTS (RH)
REPLACEMENT OF THE FWD ENGINE MOUNT 
CLOSE−UP 72.00 12.008
MH ET/S
TOTAL MANHOURS (MH)
ELAPSED TIME (ET)
142.00
23.00
STEPS
5 10 15 20 250
PER
2.00 2.001
MH
ET/S:
PER
MANHOURS
ELAPSED TIME PER STEP
NUMBER OF PERSONS
THIS CHART IS ONLY A PROPOSAL.
OPERATORS MAY DETERMINE THAT ANOTHER WAY
TO DO THE WORK IS MORE SUITABLE FOR THEM
01
02
NOTE:
MANHOUR GIVEN IN VENDOR SERVICE BULLETINS 
ARE NOT REFLECTED IN THIS GANTT CHART
:
:
B_SB_712038_5_AAAA_01_02
Figure A-FAAAA - Sheet 01
Elapsed Time Assumption
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 2
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 31

@A310
SERVICE BULLETIN
Appendix 02 - GE SPM Dot Peen Marking
**CONF ALL
(1) The following document is extracted from GENERAL ELECTRIC Standard Practices Manual and
explain how to cross mark the bolts in a compliant way.
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 1
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 32 (OCR)

©A310
SERVICE BULLETIN
Appendix 02 - GE SPM Dot Peen Marking
**CONF ALL
& COMMERCIAL ENGINE STANDARD PRACTICES MANUAL  Dated: 10/01/2006
SPM 70-16-08 DOT PEEN MARKING FOR OPTICAL CHARACTER RECOGNITION
Dot Peen Marking - Table 1
Method  Depth Limits  Dot Peen May Be Used as
Number/Description  Alternative Method for
Standard Practice
Requirements Below
2 Intermediate  0.001 - 0.004 in  70-16-03, 70-16-04, 70-16-
(0.03 - 0.10 mm)  06 Method 1C or 2B
NOTE: (a*) Depth sufficient to provide marking that it can be seen without magnification.
OCR-A Marking - Table 3
OCR Font Character  Character  Character  Max. Deviation  Min Line
Desig-nator Height (a*)  Width (a*)  Spacing (b*)  (c*)(d*)  Separation (c*)
A1  0.030=0.004  0.015 =0.004  0.025=0.004  0.005 in (0.13  0.015 in. (0.38
111.  111.  111.  mum)  mm)
(0.76 =0.09  (0.38 =0.09  (0.63 =0.09
mim)  mmm)  mm)
NOTE: (a*) Character height and width measurements are referenced from the center of the
character's scribe line.
NOTE: (b*) Character spacing is the horizontal distance between two adjacent character's
vertical center lines.
NOTE: (c*) Character skew must be less than 3.0 degrees. For terms and definitions of the
character's positional control requirements refer to ANSI X3.93M, except that skewness
shall be measured from the average baseline of a line of characters rather than from a
reference document edge.
NOTE: (d*) Maximum deviation is from the average baseline.
HEIGHT
Figure 2 Character Shapes - Standard 5x7 Dot Matrix Characteristics
B_SB_712038_5_ABAA_01_00
Figure A-FABAA - Sheet 01
GE SPM Dot Peen Marking
5  DATE: Apr 08/14  SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14  Page: 2
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 33

@A310
SERVICE BULLETIN
REPORTING SHEET
TITLE: POWER PLANT - GENERAL - REPLACEMENT OF CF6-80A3 SIDE LINK
CLEVIS ENGINE MOUNT BOLTS
MODIFICATION No.: None
Please complete the appropriate item (A or B):
A - SB WILL BE
 embodied YES/NO (if NO please comment)
If YES, aircraft concer ned (as per SB effectivity by default) and planned dates (month/year) of
embodiment:
B - SB HAS BEEN
 embodied on aircraft:
Operator comments:
From Airline:
Name/Title:
Signature: Date:
If operational documentation is affected (see Paragraph 1.K of this SB): If information is needed prior to
next normal revision or prior to SB embodiment, please indicate required service(s):
Either: Modification Operational Impact (MOI), if available YES/NO
Or : Intermediate revision YES/NO
Important Information:
 This SB will only be incorporated in your maintenance and operational
documentation if this sheet is returned to Airbus and signed by a duly authorised representative. With
the next feasible revision, this will result in
- Updating of maintenance documentation to show pre and post SB data.
- Updating of maintenance and operational documentation to show post SB data after embodiment.
If this SB requires previous or simultaneous accomplishment of other SBs, Airbus shall automatically
include them in the manual revisions. Refer to SIL 00-037 for detailed information.
Please return this completed sheet to:
AIRBUS
CUSTOMER SERVICES DIRECTORATE
1 Rond Point Maurice Bellonte
31707 BLAGNAC CEDEX FRANCE
Attn: SDC32 Technical Data and Documentation Services
F A X :( + 3 3 )56 19 32 80 6
e-mail: sb.reporting@airbus.com
or via your Resident Customer Support Office.
Alternatively, SB lists via letters or fax are also accepted.
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 1
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

### Page 34

@A310
SERVICE BULLETIN
QUALITY PERCEPTION FORM
Use this form to tell us what is your perception of the quality of this Service Bulletin. The reported data
that you provide us will be used to analyse areas of difficulties and to take corrective action to further
improve the quality of our Service Bulletins.
We thank you for the time you have taken in completing this form.
(Please rate on a scale of 1 to 4, with 4 being the highest score)
- Quality rating of this SB 4321
- Quality rating of the Accomplishment Instructions 4321
- Quality rating of the Illustrations 4321
- Is this SB easy to understand ? Y/N
If you have had difficulties in the accomplishment of this SB please quote below the area(s) and give a
short description of the issue.
Planning Material Instructions
X Effectivity X Kit content X Preparation
X Reason X List of Materials Operator Supplied X Mod/Inspection
X Manpower X Industry support X Test
X References X Re-identification X Close-Up
X Publication X Tooling X Illustrations
Comments:
Operator: Date:
Name/Title:
Please return this form to:
AIRBUS
CUSTOMER SERVICES DIRECTORATE
1 Rond Point Maurice Bellonte
31707 BLAGNAC CEDEX FRANCE
Attn : SEM4 Service Bulletins Management
F A X:( 3 3 )56 19 34 25 1
Or via your Resident Customer Support Office.
DATE: Apr 08/14 SERVICE BULLETIN No.: A310-71-2038
REVISION No.: 00 - Apr 08/14 Page: 1
5
Printed in FRANCE © AIRBUS S.A.S. 2007. All rights reserved.

---
OpenAirDocs.org is an independent research project of [Contrail Labs](https://contraillabs.com/). It is not affiliated with the FAA or the NTSB. Source documents are U.S. government works in the public domain, except the copies of manufacturers’ service documents, which belong to their rights holders.