# Airbus Service Bulletin A350-57-P036

## Copies (2)

Copies the FAA filed in AD dockets on regulations.gov, newest revision first. A newer revision may exist.

- Revision 3 ("A350-57-P036 rev 3"), 487 pages: PDF https://openairdocs.org/files/sha256/fd/0e/fd0e582aadae3f51f2f765cb818b957938676e86b0d7b9f08ae6eb8327abe7c1; text https://openairdocs.org/service-documents/airbus/a350-57-p036/file/fd0e582aadae.md. Rights: © Airbus S.A.S. Filed by the FAA in regulations.gov docket FAA-2023-1887, the docket of AD 2023-25-15. Not covered by OpenAirDocs’ CC0 dedication.
- No revision named ("SB A350-57-P036"), 451 pages: PDF https://openairdocs.org/files/sha256/aa/3c/aa3c4b0301a1eefdde9b44f9d3bea8c428bdc9082c26fa3ef4ac2f695900af54; text https://openairdocs.org/service-documents/airbus/a350-57-p036/file/aa3c4b0301a1.md. Rights: © Airbus S.A.S. Filed by the FAA in regulations.gov docket FAA-2020-0780, the docket of AD 2020-24-12. Not covered by OpenAirDocs’ CC0 dedication.

## Details

- Manufacturer: [Airbus](https://openairdocs.org/service-documents/airbus.md)
- Type: Service bulletin (Service Bulletin)
- Number: A350-57-P036
- Latest revision known: A350-57-P036, Revision 3 (OpenAirDocs)
- Page: https://openairdocs.org/service-documents/airbus/a350-57-p036

## Text (487 pages)

Revision 3, the newest copy. Rights: © Airbus S.A.S. Filed by the FAA in regulations.gov docket FAA-2023-1887, the docket of AD 2023-25-15. Not covered by OpenAirDocs’ CC0 dedication. Each page's text from the PDF; open the PDF at a page with #page=N.

### Page 1

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 1
CONF ALL
AIRBUS
2, ROND POINT EMILE DEWOITINE
31700 BLAGNAC
FRANCE
 
The content of this document is the property of Airbus. All rights including copyrights are reserved.
It is supplied in confidence and commercial security on its contents must be maintained.
It must not be used for any purpose other than that for which it is supplied, nor may information
contained in it be disclosed to unauthorized persons.
It must not be reproduced in whole or in part without permission in writing from the owners of the
copyright. Requests for reproduction of any data in this document and the media authorized for it must
be addressed to Airbus.
MANDATORY MANDATORY MANDATORY
ATA SYSTEM: 57
TITLE: WINGS - CENTER WING - CHANGE CWB FASTENERS FOR FUEL
TIGHTNESS REQUIREMENT ADHERENCE
MODIFICATION No.:
111826L26476

### Page 2

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 2
ATA SYSTEM: 57
TITLE: WINGS - CENTER WING - CHANGE CWB FASTENERS FOR FUEL
TIGHTNESS REQUIREMENT ADHERENCE
REVISION TRANSMITTAL SHEET
This page transmits Revision No. 03 of Service Bulletin No. A350-57-P036.
A. ADDITIONAL WORK
Additional work is required by this revision for aircraft modified by any previous issue to
ensure the correct application of the fuel vapour barrier structure paint from outside the
CWB with the next 6 yearly check.
No additional work is required for aircrafts on which the fuel vapour barrier structure paint
has been already correctly applied only from the outside of the CWB covered by RDAF
81075036/007/2022 and RDAF 81079963/004/2022.
B. REASON
Revision No. 03 issued to correct the application of protective CML 04PAG2 for the outside
CWB, correct the CML code for wet install the fasteners from 06AAC1 to 06ABA1 and to add
the electrical bonding code in illustrations.
NOTE: This revision satisfies the requirements of the subsequent Repair and Design
Approval Form (RDAF) and/or T echnical Adaptation (TA) issued for the related
Manufacturer Serial Number (MSN)s.
RDAF/TA MSN
81073425/013/2022
81073425/023/2022
81073946/006/2022
0029
81075036/007/2022 0037
81079963/004/2022
81090479/028/2022
0006, 0007, 0008 ,0009, 0010, 0011, 0012,
0013, 0014, 0015, 0016, 0017, 0018, 0019,
0020, 0021, 0022, 0023, 0024, 0025, 0026,
0027, 0028, 0029, 0030, 0031, 0032, 0033,
0034, 0035, 0036, 0037, 0038, 0039, 0040,
0041, 0042, 0043, 0044, 0045, 0046, 0047,
0048, 0049, 0050, 0051, 0052, 0053, 0054,
0055, 0056, 0057, 0058, 0060, 0061, 0062,
0063, 0064, 0066, 0067, 0068, 0069, 0070,
0072, 0073, 0074, 0075, 0076, 0077, 0078,
0079, 0080, 0081, 0082, 0083, 0084, 0085,
0086, 0087, 0089, 0090, 0091, 0092, 0093,
0094, 0095, 0096, 0097
81110072/006/2022 0038
81123463/006/2022
81123463/016/2022
0056
81123824/012/2022 0044, 0050, 0095
81110072/013/2022 0038
81133471/004/2022 0058
C. CHANGES

### Page 3

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 3
CONF 001
PLANNING INFORMATION
INDUSTRY SUPPORT INFORMATION Sentence added for additional work.
ACCOMPLISHMENT INSTRUCTIONS
T ask set A350-A-57-XX-P036-01000-
93AA-A Replacement of Fasteners
on the CWB
Caution updated.
PROCEDURE
A350-A-57-XX-P036-
01001-920A-A Replace
the Fasteners at FR47 and
FR49 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BA Sol.AA Replace the
Fasteners at FR47 and
FR49 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
02001-920A-A Replace
the Fasteners at FR47 and
FR49 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BB Sol.AA Replace the
Fasteners at FR47 and
FR49 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
03001-920A-A Replace
the Fasteners on the CWB
Front Panel at FR46 on the
LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.

### Page 4

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 4
Fig.BD Sol.AA Replace the
Fasteners on the CWB
Front Panel at FR46 on the
LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
04001-920A-A Replace
the Fasteners on the CWB
Front Panel at FR46 on the
RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BC Sol.AA Replace the
Fasteners on the CWB
Front Panel at FR 46 on the
RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
05001-920A-A Replace
the Fasteners on the CWB
Front Panel at STGR27,
FR46 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BE Sol.AA Replace the
Fasteners on the CWB
Front Panel at STGR27,
FR46 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
06001-920A-A Replace
the Fasteners on the CWB
Front Panel at STGR27,
FR46 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BF Sol.AA Replace the
Fasteners on the CWB
Front Panel at STGR27,
FR46 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.

### Page 5

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 5
A350-A-57-XX-P036-
07001-920A-A Replace the
Fasteners on the CWB at
FR54 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BG Sol.AA Replace the
Fasteners on the CWB at
FR54 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
08001-920A-A Replace the
Fasteners on the CWB at
FR54 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BH Sol.AA Replace the
Fasteners on the CWB at
FR54 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
09001-920A-A Replace
the Fasteners at STGR29,
FR46 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BI Sol.AA Replace the
Fasteners at STGR29,
FR46 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.

### Page 6

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 6
A350-A-57-XX-P036-
10001-920A-A Replace
the Fasteners at STGR29,
FR46 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BJ Sol.AA Replace the
Fasteners at STGR29,
FR46 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the note for application of
protection CML 06AAC1, CML 04QAC5, CML 04PAG2
and CML 12AEB1 from outside the CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
11001-920A-A Replace the
Fasteners between FR53
and FR54 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BK Sol.AA Replace the
Fasteners between FR53
and FR54 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the overlapping in wording.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
12001-920A-A Replace the
Fasteners between FR53
and FR54 on the RH side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BL Sol.AA Replace the
Fasteners between FR53
and FR54 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
T ask set A350-A-57-XX-P036-01000-
93BA-A Additional Work for Aircraft
Modified by any Previous Issue
Additional work and all associated data added.
APPENDIX
SURFACE PROTECTION TREATMENT
SURFACE PROTECTION
TREATMENT
Appendix surface protection treatment updated to
correct the note for application of protective CML
04PAG2 from the inside CWB to the outside CWB.

### Page 7

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 7
Fig.AD Sol.AA Surface
Protection Treatment
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
REPORTING SHEET
REPORTING SHEET Appendix reporting sheet updated to change the word
from SEES1 to 1SAEB.
Appendix reporting sheet updated to update the
instruction.
CONF 002
PLANNING INFORMATION
INDUSTRY SUPPORT INFORMATION Sentence added for additional work.
MATERIAL INFORMATION
LIST OF NEW PARTS
Part kit 57P036A04R04 Quantity for PN EN6115V8-15 and PN EN6115V8-14
updated.
ACCOMPLISHMENT INSTRUCTIONS
T ask set A350-A-57-XX-P036-01000-
93AA-A Replacement of Fasteners
on the CWB
Caution updated.
PROCEDURE
A350-A-57-XX-P036-
01002-920A-A Replace
the Fasteners at FR47 and
FR49 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BA Sol.AA Replace the
Fasteners at FR47 and
FR49 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
02002-920A-A Replace
the Fasteners at FR47 and
FR49 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.

### Page 8

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 8
Fig.BB Sol.AA Replace the
Fasteners at FR47 and
FR49 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
03002-920A-A Replace
the Fasteners on the CWB
Front Panel at FR46 on the
LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BD Sol.AA Replace the
Fasteners on the CWB
Front Panel at FR46 on the
LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
04002-920A-A Replace
the Fasteners on the CWB
Front Panel at FR46 on the
RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BC Sol.AA Replace the
Fasteners on the CWB
Front Panel at FR 46 on the
RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
05002-920A-A Replace
the Fasteners on the CWB
Front Panel at STGR27,
FR46 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BE Sol.AA Replace the
Fasteners on the CWB
Front Panel at STGR27,
FR46 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.

### Page 9

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 9
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
06002-920A-A Replace
the Fasteners on the CWB
Front Panel at STGR27,
FR46 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BF Sol.AA Replace the
Fasteners on the CWB
Front Panel at STGR27,
FR46 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
07002-920A-A Replace the
Fasteners on the CWB at
FR54 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BG Sol.AA Replace the
Fasteners on the CWB at
FR54 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
08002-920A-A Replace the
Fasteners on the CWB at
FR54 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BH Sol.AA Replace the
Fasteners on the CWB at
FR54 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.

### Page 10

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 10
A350-A-57-XX-P036-
09004-920A-A Replace
the Fasteners at STGR29,
FR46 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BI Sol.AA Replace the
Fasteners at STGR29,
FR46 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
10004-920A-A Replace
the Fasteners at STGR29,
FR46 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BJ Sol.AA Replace the
Fasteners at STGR29,
FR46 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the note for application of
protection CML 06AAC1, CML 04QAC5, CML 04PAG2
and CML 12AEB1 from outside the CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
11002-920A-A Replace the
Fasteners between FR53
and FR54 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to correct the quantity of item 52 and
item 62.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BK Sol.AB Replace the
Fasteners between FR53
and FR54 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the overlapping in wording.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.

### Page 11

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 11
A350-A-57-XX-P036-
12002-920A-A Replace the
Fasteners between FR53
and FR54 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to correct the quantity of item 52 and
item 62.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BL Sol.AB Replace the
Fasteners between FR53
and FR54 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
T ask set A350-A-57-XX-P036-01000-
93BA-A Additional Work for Aircraft
Modified by any Previous Issue
Additional work and all associated data added.
APPENDIX
SURFACE PROTECTION TREATMENT
SURFACE PROTECTION
TREATMENT
Appendix surface protection treatment updated to
correct the note for application of protective CML
04PAG2 from the inside CWB to the outside CWB.
Fig.AD Sol.AA Surface
Protection Treatment
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
REPORTING SHEET
REPORTING SHEET Appendix reporting sheet updated to change the word
from SEES1 to 1SAEB.
Appendix reporting sheet updated to update the
instruction.
CONF 003
PLANNING INFORMATION
INDUSTRY SUPPORT INFORMATION Sentence added for additional work.
MATERIAL INFORMATION
LIST OF NEW PARTS
Part kit 57P036A04R04 Quantity for PN EN6115V8-15 and PN EN6115V8-14
updated.
ACCOMPLISHMENT INSTRUCTIONS
T ask set A350-A-57-XX-P036-01000-
93AA-A Replacement of Fasteners
on the CWB
Caution updated.
PROCEDURE
A350-A-57-XX-P036-
01002-920A-A Replace
the Fasteners at FR47 and
FR49 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.

### Page 12

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 12
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BA Sol.AA Replace the
Fasteners at FR47 and
FR49 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
02002-920A-A Replace
the Fasteners at FR47 and
FR49 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BB Sol.AA Replace the
Fasteners at FR47 and
FR49 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
03002-920A-A Replace
the Fasteners on the CWB
Front Panel at FR46 on the
LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BD Sol.AA Replace the
Fasteners on the CWB
Front Panel at FR46 on the
LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
04002-920A-A Replace
the Fasteners on the CWB
Front Panel at FR46 on the
RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.

### Page 13

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 13
Fig.BC Sol.AA Replace the
Fasteners on the CWB
Front Panel at FR 46 on the
RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
05002-920A-A Replace
the Fasteners on the CWB
Front Panel at STGR27,
FR46 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BE Sol.AA Replace the
Fasteners on the CWB
Front Panel at STGR27,
FR46 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
06002-920A-A Replace
the Fasteners on the CWB
Front Panel at STGR27,
FR46 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BF Sol.AA Replace the
Fasteners on the CWB
Front Panel at STGR27,
FR46 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
07002-920A-A Replace the
Fasteners on the CWB at
FR54 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BG Sol.AA Replace the
Fasteners on the CWB at
FR54 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.

### Page 14

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 14
A350-A-57-XX-P036-
08002-920A-A Replace the
Fasteners on the CWB at
FR54 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BH Sol.AA Replace the
Fasteners on the CWB at
FR54 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
09003-920A-A Replace
the Fasteners at STGR29,
FR46 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BI Sol.AB Replace the
Fasteners at STGR29,
FR46 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
10003-920A-A Replace
the Fasteners at STGR29,
FR46 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BJ Sol.AB Replace the
Fasteners at STGR29,
FR46 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the note for application of
protection CML 06AAC1, CML 04QAC5, CML 04PAG2
and CML 12AEB1 from outside the CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
11002-920A-A Replace the
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.

### Page 15

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 15
Fasteners between FR53
and FR54 on the LH Side T ask updated to correct the quantity of item 52 and
item 62.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BK Sol.AB Replace the
Fasteners between FR53
and FR54 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the overlapping in wording.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
12002-920A-A Replace the
Fasteners between FR53
and FR54 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to correct the quantity of item 52 and
item 62.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BL Sol.AB Replace the
Fasteners between FR53
and FR54 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
T ask set A350-A-57-XX-P036-01000-
93BA-A Additional Work for Aircraft
Modified by any Previous Issue
Additional work and all associated data added.
APPENDIX
SURFACE PROTECTION TREATMENT
SURFACE PROTECTION
TREATMENT
Appendix surface protection treatment updated to
correct the note for application of protective CML
04PAG2 from the inside CWB to the outside CWB.
Fig.AD Sol.AA Surface
Protection Treatment
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
REPORTING SHEET
REPORTING SHEET Appendix reporting sheet updated to change the word
from SEES1 to 1SAEB.
Appendix reporting sheet updated to update the
instruction.
CONF 004
PLANNING INFORMATION
INDUSTRY SUPPORT INFORMATION Sentence added for additional work.
MATERIAL INFORMATION
LIST OF NEW PARTS

### Page 16

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 16
Part kit 57P036A04R04 Quantity for PN EN6115V8-15 and PN EN6115V8-14
updated.
ACCOMPLISHMENT INSTRUCTIONS
T ask set A350-A-57-XX-P036-01000-
93AA-A Replacement of Fasteners
on the CWB
Caution updated.
PROCEDURE
A350-A-57-XX-P036-
01002-920A-A Replace
the Fasteners at FR47 and
FR49 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BA Sol.AA Replace the
Fasteners at FR47 and
FR49 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
02002-920A-A Replace
the Fasteners at FR47 and
FR49 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BB Sol.AA Replace the
Fasteners at FR47 and
FR49 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
03002-920A-A Replace
the Fasteners on the CWB
Front Panel at FR46 on the
LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.

### Page 17

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 17
Fig.BD Sol.AA Replace the
Fasteners on the CWB
Front Panel at FR46 on the
LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
04002-920A-A Replace
the Fasteners on the CWB
Front Panel at FR46 on the
RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BC Sol.AA Replace the
Fasteners on the CWB
Front Panel at FR 46 on the
RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
05002-920A-A Replace
the Fasteners on the CWB
Front Panel at STGR27,
FR46 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BE Sol.AA Replace the
Fasteners on the CWB
Front Panel at STGR27,
FR46 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
06002-920A-A Replace
the Fasteners on the CWB
Front Panel at STGR27,
FR46 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BF Sol.AA Replace the
Fasteners on the CWB
Front Panel at STGR27,
FR46 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.

### Page 18

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 18
A350-A-57-XX-P036-
07002-920A-A Replace the
Fasteners on the CWB at
FR54 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BG Sol.AA Replace the
Fasteners on the CWB at
FR54 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
08002-920A-A Replace the
Fasteners on the CWB at
FR54 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BH Sol.AA Replace the
Fasteners on the CWB at
FR54 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
09003-920A-A Replace
the Fasteners at STGR29,
FR46 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to add the cleaning work steps from
outside the CWB with CML 14SBA1 and CML 08BAA9.
T ask updated to add the cleaning area location from
inside the CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BI Sol.AB Replace the
Fasteners at STGR29,
FR46 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.

### Page 19

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 19
A350-A-57-XX-P036-
10003-920A-A Replace
the Fasteners at STGR29,
FR46 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to correct the CML code from 06AAC1 to
06ABA1 for wet installation.
Fig.BJ Sol.AB Replace the
Fasteners at STGR29,
FR46 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to add the note for application of
protection CML 06AAC1, CML 04QAC5, CML 04PAG2
and CML 12AEB1 from outside the CWB.
Figure updated to add the bonding code and correct
the CML code from 06AAC1 to 06ABA1 for wet
installation.
A350-A-57-XX-P036-
11002-920A-A Replace the
Fasteners between FR53
and FR54 on the LH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to correct the quantity of item 52 and
item 62.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BK Sol.AB Replace the
Fasteners between FR53
and FR54 on the LH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the overlapping in wording.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
A350-A-57-XX-P036-
12002-920A-A Replace the
Fasteners between FR53
and FR54 on the RH Side
T ask updated to correct the application of protective
CML 04PAG2 from the inside CWB to the outside CWB.
T ask updated to correct the quantity of item 52 and
item 62.
T ask updated to add the standard practice and
correct the CML code from 06AAC1 to 06ABA1 for wet
installation.
Fig.BL Sol.AB Replace the
Fasteners between FR53
and FR54 on the RH Side
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
Figure updated to correct the CML code from 06AAC1
to 06ABA1 for wet installation.
T ask set A350-A-57-XX-P036-01000-
93BA-A Additional Work for Aircraft
Modified by any Previous Issue
Additional work and all associated data added.
APPENDIX
SURFACE PROTECTION TREATMENT

### Page 20

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 20
SURFACE PROTECTION
TREATMENT
Appendix surface protection treatment updated to
correct the note for application of protective CML
04PAG2 from the inside CWB to the outside CWB.
Fig.AD Sol.AA Surface
Protection Treatment
Figure updated to correct the note for application of
protective CML 04PAG2 from the inside CWB to the
outside CWB.
REPORTING SHEET
REPORTING SHEET Appendix reporting sheet updated to change the word
from SEES1 to 1SAEB.
Appendix reporting sheet updated to update the
instruction.
CONF ALL
D. FILING INSTRUCTIONS
This Service Bulletin has been generated electronically and is reissued as a complete
document. Replace the complete document.
Put this Revision Transmittal Sheet in front of the Service Bulletin.
E. HISTORY OF PREVIOUS REVISIONS
Revision No. 01 issued to:
- Update the operator applicability of this Service Bulletin
- Update fastener quantity in Part Kit A01 and A04
- Replace references MP A350-A-20-51-20-04ZZZ-264Z-A and MP A350-A-20-51-20-
00ZZZ-25BZ-A updated instead of ASR A350-A-20-51-20-04ZZZ-264Z-A and ASR A350-
A- 20-51-20-00ZZZ-25BZ-A
- Wet install the electrical bonding fasteners with sealant material No. 06AAC1.
NOTE: This revision satisfies the requirements of the subsequent T echnical Adaptation(s)
(TA) issued for the related Manufacturer Serial Number (MSN)s.
TA MSN
80834782/018/2020 0006-0058 0060-0064 0066-0070 0072-0087
0089-0097
80844130/003/2020 0006-0058 0060-0064 0066-0070 0072-0087
0089-0097
Revision No. 02 issued to:
- Incorporate changes found necessary and carried out during the accomplishment of
this Service Bulletin on aircraft with Manufacturer Serial Number (MSN) 00014
- Remove waiting time to retorque the nuts
- Update procedure step for stripping
- Correct typographical errors at figure sheets in the procedure
- Correct view letters in figure in the procedure
- Add an alternative fuel leak test
- Update Appendix Figures Fastener Pattern.

### Page 21

A350
SERVICE BULLETIN
REVISION TRANSMITTAL SHEET
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 21
NOTE: This revision satisfies the requirements of the subsequent Repair and Design
Approval Form (RDAF) issued for the related Manufacturer Serial Number (MSN)s.
RDAF MSN
80926693/013/2021 0014 0015 0016 0017 0056 0067 0086
80960443/005/20201 0006 thru 0058 0060 thru 0064 0066 thru
0070 0072 thru 0087 0089 thru 0097
F. REVISION SEQUENCE
ORIGINAL: Jan 17/20
REVISION No. : 01 - Jan 19/21
REVISION No. : 02 - Mar 16/22
REVISION No. : 03 - Dec 12/22

### Page 22

A350
SERVICE BULLETIN
SUMMARY
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 22
ATA SYSTEM: 57
TITLE: WINGS - CENTER WING - CHANGE CWB FASTENERS FOR FUEL
TIGHTNESS REQUIREMENT ADHERENCE
SUMMARY
This summary is for information only and is not approved for modification of the aircraft.
A. MODIFICATIONS
CONF 001
MODIFICATION CLASSIFICATION
MAJOR None
MINOR 111826L26476
NOTE: As per EASA IR 21, a minor change is one that has no appreciable effect on the
mass, balance, structural strength, reliability, operational characteristics affecting
the airworthiness of the product. All other changes are major changes.
NOTE: This modification is related to an airworthiness issue and has been re-classified and
confirmed by EASA as minor in accordance with EU Part 21.A.91. As such, this is
handled by Airbus under the Design Organisation Approval ref. EASA.21J.031.
CONF 002
MODIFICATION CLASSIFICATION
MAJOR None
MINOR 111826L26476
NOTE: As per EASA IR 21, a minor change is one that has no appreciable effect on the
mass, balance, structural strength, reliability, operational characteristics affecting
the airworthiness of the product. All other changes are major changes.
NOTE: This modification is related to an airworthiness issue and has been re-classified and
confirmed by EASA as minor in accordance with EU Part 21.A.91. As such, this is
handled by Airbus under the Design Organisation Approval ref. EASA.21J.031.
CONF 003
MODIFICATION CLASSIFICATION
MAJOR None
MINOR 111826L26476
NOTE: As per EASA IR 21, a minor change is one that has no appreciable effect on the
mass, balance, structural strength, reliability, operational characteristics affecting
the airworthiness of the product. All other changes are major changes.
NOTE: This modification is related to an airworthiness issue and has been re-classified and
confirmed by EASA as minor in accordance with EU Part 21.A.91. As such, this is
handled by Airbus under the Design Organisation Approval ref. EASA.21J.031.
CONF 004
MODIFICATION CLASSIFICATION
MAJOR None

### Page 23

A350
SERVICE BULLETIN
SUMMARY
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 23
MODIFICATION CLASSIFICATION
MINOR 111826L26476
NOTE: As per EASA IR 21, a minor change is one that has no appreciable effect on the
mass, balance, structural strength, reliability, operational characteristics affecting
the airworthiness of the product. All other changes are major changes.
NOTE: This modification is related to an airworthiness issue and has been re-classified and
confirmed by EASA as minor in accordance with EU Part 21.A.91. As such, this is
handled by Airbus under the Design Organisation Approval ref. EASA.21J.031.
CONF ALL
B. REASON
(1) History
During flight test and EF2 test, it has been detected that some fasteners rotates inside
their fastener holes of the Center Wing Box (CWB). This rotation can cause a crack of
the fastener head sealant cover followed by a fuel vapour leakage which could affect
the inside cabin.
(2) Objective/Action
This Service Bulletin details the replacement of B code hi-lites with titanium nuts by V
code hi-lites with steel nuts in the CWB.
(3) Advantages
Accomplishment of this Service Bulletin will ensure the tightness of the CWB fasteners
and prevent for risk of fuel and fuel vapour leakages.
(4) Operational/Maintenance Consequences
None
C. GENERAL EVALUATION
EVALUATION TABLE
COMPLIANCE MANDATORY COST SAVING NO
A/C OPERATION
AFFECTED
NO VENDOR SB NO
CANCELS INSPECTION SB NO ETOPS AFFECTED NO
PAX COMFORT AFFECTED NO POTENTIAL AD YES
RELIABILITY AFFECTED NO STRUCTURAL LIFE EXTENSION NO
LIFE LIMIT NO LINE MAINTENANCE AFFECTED NO
NOTE: Service Bulletin must be accomplished.
D. MAINTENANCE CONFIGURATION
CONF 001
MAINTENANCE CONFIGURATION
FUEL TANKS OPENED YES
CONF 002

### Page 24

A350
SERVICE BULLETIN
SUMMARY
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 24
MAINTENANCE CONFIGURATION
FUEL TANKS OPENED YES
CONF 003
MAINTENANCE CONFIGURATION
FUEL TANKS OPENED YES
CONF 004
MAINTENANCE CONFIGURATION
FUEL TANKS OPENED YES
CONF ALL
E. MATERIAL PRICE INFORMATION
CONF 001
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
MATERIAL PRICE INFORMATION TABLE
MATERIAL SET QTYPER A/C PRICE PER A/C MAIN PARTS
T ool kit 57P036T01R01 1 See SB CWB rotating fasteners
wrench
Part kit 57P036A01R03 1 6400.00 USD Bolts, nuts and washers
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
No material
CONF 002
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
MATERIAL PRICE INFORMATION TABLE
MATERIAL SET QTYPER A/C PRICE PER A/C MAIN PARTS
T ool kit 57P036T01R01 1 See SB CWB rotating fasteners
wrench
Part kit 57P036A04R04 1 6800.00 USD Bolts, nuts and washers
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
No material
CONF 003

### Page 25

A350
SERVICE BULLETIN
SUMMARY
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 25
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
MATERIAL PRICE INFORMATION TABLE
MATERIAL SET QTYPER A/C PRICE PER A/C MAIN PARTS
T ool kit 57P036T01R01 1 See SB CWB rotating fasteners
wrench
Part kit 57P036A04R04 1 6800.00 USD Bolts, nuts and washers
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
No material
CONF 004
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
MATERIAL PRICE INFORMATION TABLE
MATERIAL SET QTYPER A/C PRICE PER A/C MAIN PARTS
T ool kit 57P036T01R01 1 See SB CWB rotating fasteners
wrench
Part kit 57P036A04R04 1 6800.00 USD Bolts, nuts and washers
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
No material
CONF ALL
F. APPLICABILITY
This Service Bulletin is applicable to this (these) operator(s):
36V AAR CAL CPA CSC DAL DLH ETH FIN FWI HVN QTR SIA THA
G. CONCURRENT REQUIREMENTS
None
H. NATURE OF THE WORK
CONF 001
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
AIRCRAFT YES
EQUIPMENT NO

### Page 26

A350
SERVICE BULLETIN
SUMMARY
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 26
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
AIRCRAFT YES
EQUIPMENT NO
CONF 002
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
AIRCRAFT YES
EQUIPMENT NO
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
AIRCRAFT YES
EQUIPMENT NO
CONF 003
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
AIRCRAFT YES
EQUIPMENT NO
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
AIRCRAFT YES
EQUIPMENT NO
CONF 004
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
AIRCRAFT YES
EQUIPMENT NO
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
AIRCRAFT YES
EQUIPMENT NO

### Page 27

A350
SERVICE BULLETIN
SUMMARY
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 27
CONF ALL
I. MANPOWER
CONF 001
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
MANPOWER
TOTAL MAN-HOURS 307.25
h
ELAPSED TIME (HOURS) 62.00 h
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
MANPOWER
TOTAL MAN-HOURS 173.50
h
ELAPSED TIME (HOURS) 56.00 h
CONF 002
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
MANPOWER
TOTAL MAN-HOURS 307.25
h
ELAPSED TIME (HOURS) 62.00 h
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
MANPOWER
TOTAL MAN-HOURS 173.50
h
ELAPSED TIME (HOURS) 56.00 h
CONF 003
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
MANPOWER
TOTAL MAN-HOURS 307.25
h
ELAPSED TIME (HOURS) 62.00 h

### Page 28

A350
SERVICE BULLETIN
SUMMARY
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 28
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
MANPOWER
TOTAL MAN-HOURS 173.50
h
ELAPSED TIME (HOURS) 56.00 h
CONF 004
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
MANPOWER
TOTAL MAN-HOURS 307.25
h
ELAPSED TIME (HOURS) 62.00 h
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
MANPOWER
TOTAL MAN-HOURS 173.50
h
ELAPSED TIME (HOURS) 56.00 h

### Page 29

A350
SERVICE BULLETIN
SUMMARY
Figure ICN-A350-A-57XXP036-A-FAPE3-04FRC-A-002-01 Fig.SA Sol.AA SHEET 1/1
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22
General Overview
Page 29
CONF ALL
J. GENERAL OVERVIEW
CONF ALL
A
Z140
A
NOTE:
FASTENERS TO BE REPLACED.
FR46
FR47
FR48
FR49
FR50
FR51
FR52
FR53
FR54
FR60
ICN-A350-A-57XXP036-A-FAPE3-04FRC-A-002-01

### Page 30

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 30
ATA SYSTEM: 57
TITLE: WINGS - CENTER WING - CHANGE CWB FASTENERS FOR FUEL
TIGHTNESS REQUIREMENT ADHERENCE
1. PLANNING INFORMATION
A. APPLICABILITY
NOTE: This modification is applicable by Service Bulletin only.
NOTE: The intent of this modification is achieved in production on aircraft with
Manufacturer Serial Number (MSN) 0005 through modification No. 109911L26301
and on aircraft with MSN 0098 and subsequent through modification No.
109912L26299.
(1) Models
ON A/C 0006-0058, 0060-0064, 0066-0070, 0072-0087, 0089-0097
350-941
CONF ALL
(2) Applicability by MSN
0006-0058 0060-0064 0066-0070 0072-0087 0089-0097
(3) MSN by configuration
CONF 001
MSN CONFIGURATION
0006 0007 0008 0009 0010 0011 0012 0013 0014 0015 0016
0017 0018 0019 0020
001
CONF 002
MSN CONFIGURATION
0021 0022 0023 0024 0025 0026 0027 0028 0029 0030 0031
0032 0033 0034 0035 0036 0037 0038 0039
002
CONF 003
MSN CONFIGURATION
0040 0041 0042 0043 0044 0045 0046 0047 0048 0049 003
CONF 004
MSN CONFIGURATION
0050 0051 0052 0053 0054 0055 0056 0057 0058 0060 0061
0062 0063 0064 0066 0067 0068 0069 0070 0072 0073 0074
0075 0076 0077 0078 0079 0080 0081 0082 0083 0084 0085
0086 0087 0089 0090 0091 0092 0093 0094 0095 0096 0097
004
CONF ALL
(4) Configuration definition
CONF 001
Configuration 001
Config. 001 is applicable for aircraft on which:

### Page 31

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 31
- MOD No. 106823L25833 is not embodied,
- MOD No. 107114L25848 is not embodied,
- MOD No. 103385L25410 is not embodied.
 
 
CONF 001 retrofits following modifications: 111826L26476.
CONF 002
Configuration 002
Config. 002 is applicable for aircraft on which:
- MOD No. 106823L25833 is not embodied,
- MOD No. 107114L25848 is not embodied,
- MOD No. 103385L25410 is embodied.
 
CONF 002 retrofits following modifications: 111826L26476.
CONF 003
Configuration 003
Config. 003 is applicable for aircraft on which:
- MOD No. 106823L25833 is not embodied,
- MOD No. 107114L25848 is embodied,
- MOD No. 103385L25410 is embodied.
 
CONF 003 retrofits following modifications: 111826L26476.
CONF 004
Configuration 004
Config. 004 is applicable for aircraft on which:
- MOD No. 106823L25833 is embodied,
- MOD No. 107114L25848 is embodied,
- MOD No. 103385L25410 is embodied.
 
CONF 004 retrofits following modifications: 111826L26476.
CONF ALL
B. CONCURRENT REQUIREMENTS
None
C. REASON
(1) History
During flight test and EF2 test, it has been detected that some fasteners rotates inside
their fastener holes of the Center Wing Box (CWB). This rotation can cause a crack of
the fastener head sealant cover followed by a fuel vapour leakage which could affect
the inside cabin.

### Page 32

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 32
(2) Objective/Action
This Service Bulletin details the replacement of B code hi-lites with titanium nuts by V
code hi-lites with steel nuts in the CWB.
(3) Advantages
Accomplishment of this Service Bulletin will ensure the tightness of the CWB fasteners
and prevent for risk of fuel and fuel vapour leakages.
(4) Operational/Maintenance Consequences
None
D. DESCRIPTION
T o accomplish this Service Bulletin it is necessary to:
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
CONF 001
1 Replace the Fasteners at FR47 and FR49 on the LH Side
CONF 002-004
1 Replace the Fasteners at FR47 and FR49 on the LH Side
CONF 001
2 Replace the Fasteners at FR47 and FR49 on the RH Side
CONF 002-004
2 Replace the Fasteners at FR47 and FR49 on the RH Side
CONF 001
3 Replace the Fasteners on the CWB Front Panel at FR46 on the LH Side
CONF 002-004
3 Replace the Fasteners on the CWB Front Panel at FR46 on the LH Side
CONF 001
4 Replace the Fasteners on the CWB Front Panel at FR46 on the RH Side
CONF 002-004
4 Replace the Fasteners on the CWB Front Panel at FR46 on the RH Side
CONF 001
5 Replace the Fasteners on the CWB Front Panel at STGR27, FR46 on the LH
Side
CONF 002-004
5 Replace the Fasteners on the CWB Front Panel at STGR27, FR46 on the LH
Side
CONF 001
6 Replace the Fasteners on the CWB Front Panel at STGR27, FR46 on the RH
Side
CONF 002-004
6 Replace the Fasteners on the CWB Front Panel at STGR27, FR46 on the RH
Side
CONF 001
7 Replace the Fasteners on the CWB at FR54 on the LH Side
CONF 002-004
7 Replace the Fasteners on the CWB at FR54 on the LH Side

### Page 33

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 33
CONF 001
8 Replace the Fasteners on the CWB at FR54 on the RH Side
CONF 002-004
8 Replace the Fasteners on the CWB at FR54 on the RH Side
CONF 001
9 Replace the Fasteners at STGR29, FR46 on the LH Side
CONF 003 004
9 Replace the Fasteners at STGR29, FR46 on the LH Side
CONF 002
9 Replace the Fasteners at STGR29, FR46 on the LH Side
CONF 001
10 Replace the Fasteners at STGR29, FR46 on the RH Side
CONF 003 004
10 Replace the Fasteners at STGR29, FR46 on the RH Side
CONF 002
10 Replace the Fasteners at STGR29, FR46 on the RH Side
CONF 001
11 Replace the Fasteners between FR53 and FR54 on the LH Side
CONF 002-004
11 Replace the Fasteners between FR53 and FR54 on the LH Side
CONF 001
12 Replace the Fasteners between FR53 and FR54 on the RH side
CONF 002-004
12 Replace the Fasteners between FR53 and FR54 on the RH Side
CONF ALL
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
1 Do an Inspection of the CWB from the Outside
E. COMPLIANCE
(1) Classification
MANDATORY: Service Bulletin must be accomplished.
(2) Accomplishment Timescale
This Service Bulletin has been classified Mandatory by the issue of an Airworthiness
Directive (AD) published by the European Union Aviation Safety Agency (EASA). The
AD must be used as the reference document for the mandated accomplishment
timescale.
F. APPROVAL
The technical content of this document is approved under the authority of the Design
Organisation Approval ref. EASA.21J.031.
If an aircraft listed in the applicability has a modification or repair embodied that is not
of AIRBUS origin, and which affects the content of this Service Bulletin, the operator
is responsible for obtaining approval by its airworthiness authority for any adaptation
necessary before incorporation of the Service Bulletin.

### Page 34

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 34
G. MANPOWER
CONF 001
The manpower estimates given in this Service Bulletin are based on the direct labor cost to
do the work. These estimates assume that the work will be done by experienced personnel,
and may need to be revised upwards to suit operator’s circumstances. The estimates do not
include the time to prepare, plan or inspect the work. Manufacture and procurement of parts
and tools, drying times for paints, sealants, etc., and general administration work are also
not included.
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
PREPARATION
General Job Set-up 0.25 h
Front Panel Access 64.00 h
CWB access 3.00 h
Access T op Skin Panel of the CWB 20.00 h
Report Rotated and Different Installed Fasteners 0.25 h
PROCEDURE
Replace the Fasteners at FR47 and FR49 on the LH Side 9.50 h
Replace the Fasteners at FR47 and FR49 on the RH Side 9.50 h
Replace the Fasteners on the CWB Front Panel at FR46 on
the LH Side
9.50 h
Replace the Fasteners on the CWB Front Panel at FR46 on
the RH Side
9.50 h
Replace the Fasteners on the CWB Front Panel at STGR27,
FR46 on the LH Side
9.50 h
Replace the Fasteners on the CWB Front Panel at STGR27,
FR46 on the RH Side
9.50 h
Replace the Fasteners on the CWB at FR54 on the LH Side 4.50 h
Replace the Fasteners on the CWB at FR54 on the RH Side 4.50 h
Replace the Fasteners at STGR29, FR46 on the LH Side 9.50 h
Replace the Fasteners at STGR29, FR46 on the RH Side 9.50 h
Replace the Fasteners between FR53 and FR54 on the LH
Side
20.00 h
Replace the Fasteners between FR53 and FR54 on the RH
side
20.00 h
PREPARATION FOR TEST
None
TEST
T esting 7.50 h
CLOSE-UP
T op Skin Panel of the CWB Close-up 20.00 h
CWB Close-up 3.00 h
Front Panel Close-up 64.00 h
General Close-up 0.25 h

### Page 35

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 35
TOTAL MAN-HOURS 307.25 h
ELAPSED TIME (HOURS) 62.00 h
NOTE: For an explanation of the man-hours and elapsed time, refer to the
Gantt Chart given in Appendix Manpower Gantt Chart.
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
PREPARATION
Do a check of the Fasteners to be Inspected 0.50 h
Job Set-up 0.25 h
Front Panel Access 64.00 h
Access T op Skin Panel of the CWB 20.00 h
PROCEDURE
Do an Inspection of the CWB from the Outside 3.00 h
PREPARATION FOR TEST
None
TEST
T est 1.50 h
CLOSE-UP
T op Skin Panel of the CWB Close-up 20.00 h
Front Panel Close-up 64.00 h
Close-up 0.25 h
TOTAL MAN-HOURS 173.50 h
ELAPSED TIME (HOURS) 56.00 h
CONF 002
The manpower estimates given in this Service Bulletin are based on the direct labor cost to
do the work. These estimates assume that the work will be done by experienced personnel,
and may need to be revised upwards to suit operator’s circumstances. The estimates do not
include the time to prepare, plan or inspect the work. Manufacture and procurement of parts
and tools, drying times for paints, sealants, etc., and general administration work are also
not included.
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
PREPARATION
General Job Set-up 0.25 h
Front Panel Access 64.00 h
CWB access 3.00 h
Access T op Skin Panel of the CWB 20.00 h
Report Rotated and Different Installed Fasteners 0.25 h
PROCEDURE
Replace the Fasteners at FR47 and FR49 on the LH Side 9.50 h
Replace the Fasteners at FR47 and FR49 on the RH Side 9.50 h

### Page 36

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 36
Replace the Fasteners on the CWB Front Panel at FR46 on
the LH Side
9.50 h
Replace the Fasteners on the CWB Front Panel at FR46 on
the RH Side
9.50 h
Replace the Fasteners on the CWB Front Panel at STGR27,
FR46 on the LH Side
9.50 h
Replace the Fasteners on the CWB Front Panel at STGR27,
FR46 on the RH Side
9.50 h
Replace the Fasteners on the CWB at FR54 on the LH Side 4.50 h
Replace the Fasteners on the CWB at FR54 on the RH Side 4.50 h
Replace the Fasteners at STGR29, FR46 on the LH Side 9.50 h
Replace the Fasteners at STGR29, FR46 on the RH Side 9.50 h
Replace the Fasteners between FR53 and FR54 on the LH
Side
20.00 h
Replace the Fasteners between FR53 and FR54 on the RH
Side
20.00 h
PREPARATION FOR TEST
None
TEST
T esting 7.50 h
CLOSE-UP
T op Skin Panel of the CWB Close-up 20.00 h
CWB Close-up 3.00 h
Front Panel Close-up 64.00 h
General Close-up 0.25 h
TOTAL MAN-HOURS 307.25 h
ELAPSED TIME (HOURS) 62.00 h
NOTE: For an explanation of the man-hours and elapsed time, refer to the
Gantt Chart given in Appendix Manpower Gantt Chart.
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
PREPARATION
Do a check of the Fasteners to be Inspected 0.50 h
Job Set-up 0.25 h
Front Panel Access 64.00 h
Access T op Skin Panel of the CWB 20.00 h
PROCEDURE
Do an Inspection of the CWB from the Outside 3.00 h
PREPARATION FOR TEST
None
TEST
T est 1.50 h

### Page 37

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 37
CLOSE-UP
T op Skin Panel of the CWB Close-up 20.00 h
Front Panel Close-up 64.00 h
Close-up 0.25 h
TOTAL MAN-HOURS 173.50 h
ELAPSED TIME (HOURS) 56.00 h
CONF 003
The manpower estimates given in this Service Bulletin are based on the direct labor cost to
do the work. These estimates assume that the work will be done by experienced personnel,
and may need to be revised upwards to suit operator’s circumstances. The estimates do not
include the time to prepare, plan or inspect the work. Manufacture and procurement of parts
and tools, drying times for paints, sealants, etc., and general administration work are also
not included.
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
PREPARATION
General Job Set-up 0.25 h
Front Panel Access 64.00 h
CWB access 3.00 h
Access T op Skin Panel of the CWB 20.00 h
Report Rotated and Different Installed Fasteners 0.25 h
PROCEDURE
Replace the Fasteners at FR47 and FR49 on the LH Side 9.50 h
Replace the Fasteners at FR47 and FR49 on the RH Side 9.50 h
Replace the Fasteners on the CWB Front Panel at FR46 on
the LH Side
9.50 h
Replace the Fasteners on the CWB Front Panel at FR46 on
the RH Side
9.50 h
Replace the Fasteners on the CWB Front Panel at STGR27,
FR46 on the LH Side
9.50 h
Replace the Fasteners on the CWB Front Panel at STGR27,
FR46 on the RH Side
9.50 h
Replace the Fasteners on the CWB at FR54 on the LH Side 4.50 h
Replace the Fasteners on the CWB at FR54 on the RH Side 4.50 h
Replace the Fasteners at STGR29, FR46 on the LH Side 9.50 h
Replace the Fasteners at STGR29, FR46 on the RH Side 9.50 h
Replace the Fasteners between FR53 and FR54 on the LH
Side
20.00 h
Replace the Fasteners between FR53 and FR54 on the RH
Side
20.00 h
PREPARATION FOR TEST
None
TEST
T esting 7.50 h

### Page 38

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 38
CLOSE-UP
T op Skin Panel of the CWB Close-up 20.00 h
CWB Close-up 3.00 h
Front Panel Close-up 64.00 h
General Close-up 0.25 h
TOTAL MAN-HOURS 307.25 h
ELAPSED TIME (HOURS) 62.00 h
NOTE: For an explanation of the man-hours and elapsed time, refer to the
Gantt Chart given in Appendix Manpower Gantt Chart.
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
PREPARATION
Do a check of the Fasteners to be Inspected 0.50 h
Job Set-up 0.25 h
Front Panel Access 64.00 h
Access T op Skin Panel of the CWB 20.00 h
PROCEDURE
Do an Inspection of the CWB from the Outside 3.00 h
PREPARATION FOR TEST
None
TEST
T est 1.50 h
CLOSE-UP
T op Skin Panel of the CWB Close-up 20.00 h
Front Panel Close-up 64.00 h
Close-up 0.25 h
TOTAL MAN-HOURS 173.50 h
ELAPSED TIME (HOURS) 56.00 h
CONF 004
The manpower estimates given in this Service Bulletin are based on the direct labor cost to
do the work. These estimates assume that the work will be done by experienced personnel,
and may need to be revised upwards to suit operator’s circumstances. The estimates do not
include the time to prepare, plan or inspect the work. Manufacture and procurement of parts
and tools, drying times for paints, sealants, etc., and general administration work are also
not included.
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
PREPARATION
General Job Set-up 0.25 h
Front Panel Access 64.00 h
CWB access 3.00 h

### Page 39

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 39
Access T op Skin Panel of the CWB 20.00 h
Report Rotated and Different Installed Fasteners 0.25 h
PROCEDURE
Replace the Fasteners at FR47 and FR49 on the LH Side 9.50 h
Replace the Fasteners at FR47 and FR49 on the RH Side 9.50 h
Replace the Fasteners on the CWB Front Panel at FR46 on
the LH Side
9.50 h
Replace the Fasteners on the CWB Front Panel at FR46 on
the RH Side
9.50 h
Replace the Fasteners on the CWB Front Panel at STGR27,
FR46 on the LH Side
9.50 h
Replace the Fasteners on the CWB Front Panel at STGR27,
FR46 on the RH Side
9.50 h
Replace the Fasteners on the CWB at FR54 on the LH Side 4.50 h
Replace the Fasteners on the CWB at FR54 on the RH Side 4.50 h
Replace the Fasteners at STGR29, FR46 on the LH Side 9.50 h
Replace the Fasteners at STGR29, FR46 on the RH Side 9.50 h
Replace the Fasteners between FR53 and FR54 on the LH
Side
20.00 h
Replace the Fasteners between FR53 and FR54 on the RH
Side
20.00 h
PREPARATION FOR TEST
None
TEST
T esting 7.50 h
CLOSE-UP
T op Skin Panel of the CWB Close-up 20.00 h
CWB Close-up 3.00 h
Front Panel Close-up 64.00 h
General Close-up 0.25 h
TOTAL MAN-HOURS 307.25 h
ELAPSED TIME (HOURS) 62.00 h
NOTE: For an explanation of the man-hours and elapsed time, refer to the
Gantt Chart given in Appendix Manpower Gantt Chart.
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
PREPARATION
Do a check of the Fasteners to be Inspected 0.50 h
Job Set-up 0.25 h
Front Panel Access 64.00 h
Access T op Skin Panel of the CWB 20.00 h
PROCEDURE

### Page 40

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 40
Do an Inspection of the CWB from the Outside 3.00 h
PREPARATION FOR TEST
None
TEST
T est 1.50 h
CLOSE-UP
T op Skin Panel of the CWB Close-up 20.00 h
Front Panel Close-up 64.00 h
Close-up 0.25 h
TOTAL MAN-HOURS 173.50 h
ELAPSED TIME (HOURS) 56.00 h
CONF ALL
H. WEIGHT AND BALANCE
Not changed
I. ELECTRICAL LOAD DATA
Not changed
J. REFERENCES
CONF 001
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
AIRCRAFT STRUCTURAL REPAIR (ASR)
A350-A-51-24-XX-01ZZZ-667Z-A A350-A-51-4X-XX-01ZZZ-667Z-A
A350-A-51-42-XX-01ZZZ-667Z-A A350-A-51-43-XX-01ZZZ-667Z-A
A350-A-51-75-12-00ZZZ-660Z-A
ELECTRICAL STANDARD PRACTICES (ESP)
A350-A-20-55-XX-01ZZZ-042Z-A
INTRODUCTION (INTRO)
A350-A-00-61-04-11ZZZ-018Z-D
MAINTENANCE PROCEDURE (MP)
A350-A-20-51-20-00ZZZ-25BZ-A
A350-A-20-51-20-04ZZZ-264Z-A
A350-A-20-51-50-01ZZZ-25BZ-A
A350-A-21-2X-XX-00ZZZ-520Z-A
A350-A-21-2X-XX-00ZZZ-720Z-A
A350-A-21-21-67-00ZZZ-520Z-A
A350-A-21-21-67-00ZZZ-720Z-A
A350-A-24-41-XX-00ZZZ-170Z-A A350-A-25-21-46-00ZZZ-520Z-A
A350-A-25-21-46-00ZZZ-720Z-A
A350-A-25-28-61-00ZZZ-520Z-A
A350-A-25-28-61-00ZZZ-720Z-A
A350-A-25-81-63-00ZZZ-520Z-A
A350-A-25-81-63-00ZZZ-720Z-A
A350-A-28-1X-XX-02ZZZ-200Z-A A350-A-28-11-XX-00ZZZ-270Z-A

### Page 41

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 41
MAINTENANCE PROCEDURE (MP)
A350-A-28-11-XX-03ZZZ-270Z-A
A350-A-50-1X-XX-00ZZZ-170Z-A
A350-A-50-1X-XX-01ZZZ-170Z-A
A350-A-50-13-61-00ZZZ-520Z-A
A350-A-50-13-61-00ZZZ-720Z-A
A350-A-53-XX-XX-0BZZZ-520Z-A
A350-A-53-XX-XX-0BZZZ-720Z-A
A350-A-57-11-65-00ZZZ-310Z-A
PROCESS AND MATERIAL SPECIFICATION (PMS)
01-04-45 01-04-58
SYSTEM DESCRIPTION (SD)
A350-A-06-2X-XX-01ZZZ-04CZ-A A350-A-06-3X-XX-01ZZZ-04CZ-A
A350-A-20-51-20-01ZZZ-04CZ-A
TECHNICAL FOLLOW UP (TFU)
57.10.00.011
STANDARDS MANUAL (SM)
CONSUMABLE MATERIAL LIST (CML)
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
AIRCRAFT STRUCTURAL REPAIR (ASR)
A350-A-51-24-XX-01ZZZ-667Z-A A350-A-51-75-12-00ZZZ-660Z-A
ELECTRICAL STANDARD PRACTICES (ESP)
A350-A-20-55-XX-01ZZZ-042Z-A
INTRODUCTION (INTRO)
A350-A-00-61-04-11ZZZ-018Z-D
MAINTENANCE PROCEDURE (MP)
A350-A-21-2X-XX-00ZZZ-520Z-A
A350-A-21-2X-XX-00ZZZ-720Z-A
A350-A-21-21-67-00ZZZ-520Z-A
A350-A-21-21-67-00ZZZ-720Z-A
A350-A-24-41-XX-00ZZZ-170Z-A A350-A-25-21-46-00ZZZ-520Z-A
A350-A-25-21-46-00ZZZ-720Z-A
A350-A-25-28-61-00ZZZ-520Z-A
A350-A-25-28-61-00ZZZ-720Z-A
A350-A-25-81-63-00ZZZ-520Z-A
A350-A-25-81-63-00ZZZ-720Z-A
A350-A-50-1X-XX-00ZZZ-170Z-A
A350-A-50-1X-XX-01ZZZ-170Z-A
A350-A-50-13-61-00ZZZ-520Z-A
A350-A-50-13-61-00ZZZ-720Z-A
A350-A-53-XX-XX-0BZZZ-520Z-A
A350-A-53-XX-XX-0BZZZ-720Z-A
SYSTEM DESCRIPTION (SD)
A350-A-06-3X-XX-01ZZZ-04CZ-A

### Page 42

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 42
TECHNICAL FOLLOW UP (TFU)
57.10.00.011
STANDARDS MANUAL (SM)
CONSUMABLE MATERIAL LIST (CML)
CONF 002
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
AIRCRAFT STRUCTURAL REPAIR (ASR)
A350-A-51-24-XX-01ZZZ-667Z-A A350-A-51-4X-XX-01ZZZ-667Z-A
A350-A-51-42-XX-01ZZZ-667Z-A A350-A-51-43-XX-01ZZZ-667Z-A
A350-A-51-75-12-00ZZZ-660Z-A
ELECTRICAL STANDARD PRACTICES (ESP)
A350-A-20-55-XX-01ZZZ-042Z-A
INTRODUCTION (INTRO)
A350-A-00-61-04-11ZZZ-018Z-D
MAINTENANCE PROCEDURE (MP)
A350-A-20-51-20-00ZZZ-25BZ-A
A350-A-20-51-20-04ZZZ-264Z-A
A350-A-20-51-50-01ZZZ-25BZ-A
A350-A-21-2X-XX-00ZZZ-520Z-A
A350-A-21-2X-XX-00ZZZ-720Z-A
A350-A-21-21-67-00ZZZ-520Z-A
A350-A-21-21-67-00ZZZ-720Z-A
A350-A-24-41-XX-00ZZZ-170Z-A A350-A-25-21-46-00ZZZ-520Z-A
A350-A-25-21-46-00ZZZ-720Z-A
A350-A-25-28-61-00ZZZ-520Z-A
A350-A-25-28-61-00ZZZ-720Z-A
A350-A-25-81-63-00ZZZ-520Z-A
A350-A-25-81-63-00ZZZ-720Z-A
A350-A-28-1X-XX-02ZZZ-200Z-A A350-A-28-11-XX-00ZZZ-270Z-A
A350-A-28-11-XX-03ZZZ-270Z-A
A350-A-50-1X-XX-00ZZZ-170Z-A
A350-A-50-1X-XX-01ZZZ-170Z-A
A350-A-50-13-61-00ZZZ-520Z-A
A350-A-50-13-61-00ZZZ-720Z-A
A350-A-53-XX-XX-0BZZZ-520Z-A
A350-A-53-XX-XX-0BZZZ-720Z-A
A350-A-57-11-65-00ZZZ-310Z-A
PROCESS AND MATERIAL SPECIFICATION (PMS)
01-04-45 01-04-58
SYSTEM DESCRIPTION (SD)
A350-A-06-2X-XX-01ZZZ-04CZ-A A350-A-06-3X-XX-01ZZZ-04CZ-A
A350-A-20-51-20-01ZZZ-04CZ-A

### Page 43

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 43
TECHNICAL FOLLOW UP (TFU)
57.10.00.011
STANDARDS MANUAL (SM)
CONSUMABLE MATERIAL LIST (CML)
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
AIRCRAFT STRUCTURAL REPAIR (ASR)
A350-A-51-24-XX-01ZZZ-667Z-A A350-A-51-75-12-00ZZZ-660Z-A
ELECTRICAL STANDARD PRACTICES (ESP)
A350-A-20-55-XX-01ZZZ-042Z-A
INTRODUCTION (INTRO)
A350-A-00-61-04-11ZZZ-018Z-D
MAINTENANCE PROCEDURE (MP)
A350-A-21-2X-XX-00ZZZ-520Z-A
A350-A-21-2X-XX-00ZZZ-720Z-A
A350-A-21-21-67-00ZZZ-520Z-A
A350-A-21-21-67-00ZZZ-720Z-A
A350-A-24-41-XX-00ZZZ-170Z-A A350-A-25-21-46-00ZZZ-520Z-A
A350-A-25-21-46-00ZZZ-720Z-A
A350-A-25-28-61-00ZZZ-520Z-A
A350-A-25-28-61-00ZZZ-720Z-A
A350-A-25-81-63-00ZZZ-520Z-A
A350-A-25-81-63-00ZZZ-720Z-A
A350-A-50-1X-XX-00ZZZ-170Z-A
A350-A-50-1X-XX-01ZZZ-170Z-A
A350-A-50-13-61-00ZZZ-520Z-A
A350-A-50-13-61-00ZZZ-720Z-A
A350-A-53-XX-XX-0BZZZ-520Z-A
A350-A-53-XX-XX-0BZZZ-720Z-A
SYSTEM DESCRIPTION (SD)
A350-A-06-3X-XX-01ZZZ-04CZ-A
TECHNICAL FOLLOW UP (TFU)
57.10.00.011
STANDARDS MANUAL (SM)
CONSUMABLE MATERIAL LIST (CML)
CONF 003
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
AIRCRAFT STRUCTURAL REPAIR (ASR)
A350-A-51-24-XX-01ZZZ-667Z-A A350-A-51-4X-XX-01ZZZ-667Z-A
A350-A-51-42-XX-01ZZZ-667Z-A A350-A-51-43-XX-01ZZZ-667Z-A

### Page 44

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 44
AIRCRAFT STRUCTURAL REPAIR (ASR)
A350-A-51-75-12-00ZZZ-660Z-A
ELECTRICAL STANDARD PRACTICES (ESP)
A350-A-20-55-XX-01ZZZ-042Z-A
INTRODUCTION (INTRO)
A350-A-00-61-04-11ZZZ-018Z-D
MAINTENANCE PROCEDURE (MP)
A350-A-20-51-20-00ZZZ-25BZ-A
A350-A-20-51-20-04ZZZ-264Z-A
A350-A-20-51-50-01ZZZ-25BZ-A
A350-A-21-2X-XX-00ZZZ-520Z-A
A350-A-21-2X-XX-00ZZZ-720Z-A
A350-A-21-21-67-00ZZZ-520Z-A
A350-A-21-21-67-00ZZZ-720Z-A
A350-A-24-41-XX-00ZZZ-170Z-A A350-A-25-21-46-00ZZZ-520Z-A
A350-A-25-21-46-00ZZZ-720Z-A
A350-A-25-28-61-00ZZZ-520Z-A
A350-A-25-28-61-00ZZZ-720Z-A
A350-A-25-81-63-00ZZZ-520Z-A
A350-A-25-81-63-00ZZZ-720Z-A
A350-A-28-1X-XX-02ZZZ-200Z-A A350-A-28-11-XX-00ZZZ-270Z-A
A350-A-28-11-XX-03ZZZ-270Z-A
A350-A-50-1X-XX-00ZZZ-170Z-A
A350-A-50-1X-XX-01ZZZ-170Z-A
A350-A-50-13-61-00ZZZ-520Z-A
A350-A-50-13-61-00ZZZ-720Z-A
A350-A-53-XX-XX-0BZZZ-520Z-A
A350-A-53-XX-XX-0BZZZ-720Z-A
A350-A-57-11-65-00ZZZ-310Z-A
PROCESS AND MATERIAL SPECIFICATION (PMS)
01-04-45 01-04-58
SYSTEM DESCRIPTION (SD)
A350-A-06-2X-XX-01ZZZ-04CZ-A A350-A-06-3X-XX-01ZZZ-04CZ-A
A350-A-20-51-20-01ZZZ-04CZ-A
TECHNICAL FOLLOW UP (TFU)
57.10.00.011
STANDARDS MANUAL (SM)
CONSUMABLE MATERIAL LIST (CML)
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
AIRCRAFT STRUCTURAL REPAIR (ASR)
A350-A-51-24-XX-01ZZZ-667Z-A A350-A-51-75-12-00ZZZ-660Z-A
ELECTRICAL STANDARD PRACTICES (ESP)
A350-A-20-55-XX-01ZZZ-042Z-A

### Page 45

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 45
INTRODUCTION (INTRO)
A350-A-00-61-04-11ZZZ-018Z-D
MAINTENANCE PROCEDURE (MP)
A350-A-21-2X-XX-00ZZZ-520Z-A
A350-A-21-2X-XX-00ZZZ-720Z-A
A350-A-21-21-67-00ZZZ-520Z-A
A350-A-21-21-67-00ZZZ-720Z-A
A350-A-24-41-XX-00ZZZ-170Z-A A350-A-25-21-46-00ZZZ-520Z-A
A350-A-25-21-46-00ZZZ-720Z-A
A350-A-25-28-61-00ZZZ-520Z-A
A350-A-25-28-61-00ZZZ-720Z-A
A350-A-25-81-63-00ZZZ-520Z-A
A350-A-25-81-63-00ZZZ-720Z-A
A350-A-50-1X-XX-00ZZZ-170Z-A
A350-A-50-1X-XX-01ZZZ-170Z-A
A350-A-50-13-61-00ZZZ-520Z-A
A350-A-50-13-61-00ZZZ-720Z-A
A350-A-53-XX-XX-0BZZZ-520Z-A
A350-A-53-XX-XX-0BZZZ-720Z-A
SYSTEM DESCRIPTION (SD)
A350-A-06-3X-XX-01ZZZ-04CZ-A
TECHNICAL FOLLOW UP (TFU)
57.10.00.011
STANDARDS MANUAL (SM)
CONSUMABLE MATERIAL LIST (CML)
CONF 004
(1) Replacement of Fasteners on the CWB
(a) T ask set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners on the
CWB
AIRCRAFT STRUCTURAL REPAIR (ASR)
A350-A-51-24-XX-01ZZZ-667Z-A A350-A-51-4X-XX-01ZZZ-667Z-A
A350-A-51-42-XX-01ZZZ-667Z-A A350-A-51-43-XX-01ZZZ-667Z-A
A350-A-51-75-12-00ZZZ-660Z-A
ELECTRICAL STANDARD PRACTICES (ESP)
A350-A-20-55-XX-01ZZZ-042Z-A
INTRODUCTION (INTRO)
A350-A-00-61-04-11ZZZ-018Z-D
MAINTENANCE PROCEDURE (MP)
A350-A-20-51-20-00ZZZ-25BZ-A
A350-A-20-51-20-04ZZZ-264Z-A
A350-A-20-51-50-01ZZZ-25BZ-A
A350-A-21-2X-XX-00ZZZ-520Z-A
A350-A-21-2X-XX-00ZZZ-720Z-A
A350-A-21-21-67-00ZZZ-520Z-A
A350-A-21-21-67-00ZZZ-720Z-A
A350-A-24-41-XX-00ZZZ-170Z-A A350-A-25-21-46-00ZZZ-520Z-A

### Page 46

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 46
MAINTENANCE PROCEDURE (MP)
A350-A-25-21-46-00ZZZ-720Z-A
A350-A-25-28-61-00ZZZ-520Z-A
A350-A-25-28-61-00ZZZ-720Z-A
A350-A-25-81-63-00ZZZ-520Z-A
A350-A-25-81-63-00ZZZ-720Z-A
A350-A-28-1X-XX-02ZZZ-200Z-A A350-A-28-11-XX-00ZZZ-270Z-A
A350-A-28-11-XX-03ZZZ-270Z-A
A350-A-50-1X-XX-00ZZZ-170Z-A
A350-A-50-1X-XX-01ZZZ-170Z-A
A350-A-50-13-61-00ZZZ-520Z-A
A350-A-50-13-61-00ZZZ-720Z-A
A350-A-53-XX-XX-0BZZZ-520Z-A
A350-A-53-XX-XX-0BZZZ-720Z-A
A350-A-57-11-65-00ZZZ-310Z-A
PROCESS AND MATERIAL SPECIFICATION (PMS)
01-04-45 01-04-58
SYSTEM DESCRIPTION (SD)
A350-A-06-2X-XX-01ZZZ-04CZ-A A350-A-06-3X-XX-01ZZZ-04CZ-A
A350-A-20-51-20-01ZZZ-04CZ-A
TECHNICAL FOLLOW UP (TFU)
57.10.00.011
STANDARDS MANUAL (SM)
CONSUMABLE MATERIAL LIST (CML)
(2) Additional Work for Aircraft Modified by any Previous Issue
(a) T ask set A350-A-57-XX-P036-01000-93BA-A Additional Work for Aircraft Modified
by any Previous Issue
AIRCRAFT STRUCTURAL REPAIR (ASR)
A350-A-51-24-XX-01ZZZ-667Z-A A350-A-51-75-12-00ZZZ-660Z-A
ELECTRICAL STANDARD PRACTICES (ESP)
A350-A-20-55-XX-01ZZZ-042Z-A
INTRODUCTION (INTRO)
A350-A-00-61-04-11ZZZ-018Z-D
MAINTENANCE PROCEDURE (MP)
A350-A-21-2X-XX-00ZZZ-520Z-A
A350-A-21-2X-XX-00ZZZ-720Z-A
A350-A-21-21-67-00ZZZ-520Z-A
A350-A-21-21-67-00ZZZ-720Z-A
A350-A-24-41-XX-00ZZZ-170Z-A A350-A-25-21-46-00ZZZ-520Z-A
A350-A-25-21-46-00ZZZ-720Z-A
A350-A-25-28-61-00ZZZ-520Z-A
A350-A-25-28-61-00ZZZ-720Z-A
A350-A-25-81-63-00ZZZ-520Z-A
A350-A-25-81-63-00ZZZ-720Z-A
A350-A-50-1X-XX-00ZZZ-170Z-A
A350-A-50-1X-XX-01ZZZ-170Z-A
A350-A-50-13-61-00ZZZ-520Z-A
A350-A-50-13-61-00ZZZ-720Z-A

### Page 47

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 47
MAINTENANCE PROCEDURE (MP)
A350-A-53-XX-XX-0BZZZ-520Z-A
A350-A-53-XX-XX-0BZZZ-720Z-A
SYSTEM DESCRIPTION (SD)
A350-A-06-3X-XX-01ZZZ-04CZ-A
TECHNICAL FOLLOW UP (TFU)
57.10.00.011
STANDARDS MANUAL (SM)
CONSUMABLE MATERIAL LIST (CML)
CONF ALL
K. PUBLICATION AFFECTED
None
L. INDUSTRY SUPPORT INFORMATION
AIRBUS will share the costs of accomplishment of this Service Bulletin by providing the kits
at no charge for orders placed before Dec 31/24.
For the accomplishment of this Service Bulletin before Dec 31/24, AIRBUS will credit the
man-hours indicated in this Service Bulletin at the agreed in-house warranty labor rate.
Claims for this allowance shall be received no later than 90 days after completion of the last
affected aircraft of your fleet fulfilling above timeframe conditions.
For the accomplishment of the additional work before Dec 31/28, AIRBUS will credit the
man-hours indicated in this Service Bulletin at the agreed in-house warranty labor rate.
Claims for this allowance shall be received no later than 90 days after completion of the last
affected aircraft of your fleet fulfilling above timeframe conditions.
This Service Bulletin is the subject of an AIRBUS monitored retrofit campaign.
For the organization of this retrofit, you are kindly requested to contact AIRBUS retrofit
management department: monitored.retrofit@airbus.com.

### Page 48

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 48
2. MATERIAL INFORMATION
A. MATERIAL APPLICABILITY
CONF 001
Material for task set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners
on the CWB
MATERIAL QTY SEE NOTES
T ool kit 57P036T01R01 1
Referenced tools See SB
Consumables See SB
Referenced consumables See SB
Part kit 57P036A01R03 1 (1)
NOTE(S)
(1): T o cover any possible deviation of fastener installation additional shipping sets of
fasteners with oversize and additional length should be ordered in reference to RIL
V57M19004719. The part number of these fasteners and the positions in the CWB
structure should be recorded in the report sheets, refer to Appendix REPORTING
SHEET.
Material for task set A350-A-57-XX-P036-01000-93BA-A Additional Work for
Aircraft Modified by any Previous Issue
MATERIAL QTY SEE NOTES
Consumables See SB
Referenced consumables See SB
CONF 002
Material for task set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners
on the CWB
MATERIAL QTY SEE NOTES
T ool kit 57P036T01R01 1
Referenced tools See SB
Consumables See SB
Referenced consumables See SB
Part kit 57P036A04R04 1 (1)
NOTE(S)
(1): T o cover any possible deviation of fastener installation additional shipping sets of
fasteners with oversize and additional length should be ordered in reference to RIL
V57M19004719. The part number of these fasteners and the positions in the CWB
structure should be recorded in the report sheets, refer to Appendix REPORTING
SHEET.
Material for task set A350-A-57-XX-P036-01000-93BA-A Additional Work for
Aircraft Modified by any Previous Issue
MATERIAL QTY SEE NOTES
Consumables See SB
Referenced consumables See SB

### Page 49

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 49
CONF 003
Material for task set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners
on the CWB
MATERIAL QTY SEE NOTES
T ool kit 57P036T01R01 1
Referenced tools See SB
Consumables See SB
Referenced consumables See SB
Part kit 57P036A04R04 1 (1)
NOTE(S)
(1): T o cover any possible deviation of fastener installation additional shipping sets of
fasteners with oversize and additional length should be ordered in reference to RIL
V57M19004719. The part number of these fasteners and the positions in the CWB
structure should be recorded in the report sheets, refer to Appendix REPORTING
SHEET.
Material for task set A350-A-57-XX-P036-01000-93BA-A Additional Work for
Aircraft Modified by any Previous Issue
MATERIAL QTY SEE NOTES
Consumables See SB
Referenced consumables See SB
CONF 004
Material for task set A350-A-57-XX-P036-01000-93AA-A Replacement of Fasteners
on the CWB
MATERIAL QTY SEE NOTES
T ool kit 57P036T01R01 1
Referenced tools See SB
Consumables See SB
Referenced consumables See SB
Part kit 57P036A04R04 1 (1)
NOTE(S)
(1): T o cover any possible deviation of fastener installation additional shipping sets of
fasteners with oversize and additional length should be ordered in reference to RIL
V57M19004719. The part number of these fasteners and the positions in the CWB
structure should be recorded in the report sheets, refer to Appendix REPORTING
SHEET.
Material for task set A350-A-57-XX-P036-01000-93BA-A Additional Work for
Aircraft Modified by any Previous Issue
MATERIAL QTY SEE NOTES
Consumables See SB
Referenced consumables See SB

### Page 50

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 50
CONF ALL
B. TOOLING
Tool kit 57P036T01R01
Availability 090 d (calendar days from receipt of order)
Procurement address
D4296
AIRBUS Material, Logistics and Suppliers
Customer Order Fulfilment
Weg beim Jaeger 150
22335 HAMBURG
GERMANY
Phone: +49 (0) 40 50 76 40 02
E-mail: Please contact your Single Point of Contact
(SPOC)
Internet: http://spares.airbus.com
D4296
AIRBUS Material, Logistics and Suppliers
Weg beim Jaeger 150
22335 HAMBURG
GERMANY
Fax: +49 40 50 76 3225
E-mail: T ool.LEASE@airbus.com
Internet: http://spares.airbus.com
NOTE(S)
Customers with aircraft shown in the applicability of this Service Bulletin should send
a purchase order to AIRBUS at the address given above and quote the number of this
Service Bulletin.
Operators interested in the lease of standard tools should contact AIRBUS at the
address given above.
Airbus will provide two specific tool kits per customer to reduce the man hours while
using this specific tool on different work steps at the same time.
ITEM PART No. QTY (UM) KEYWORD DRAWING SEE NOTES
98V57103007000 2 CWB
CONF 001
Referenced tools for task set A350-A-57-XX-P036-01000-93AA-A Replacement of
Fasteners on the CWB
T o accomplish this Service Bulletin it is necessary to use the tools listed in:
Ref. MP A350-A-28-11-XX-03ZZZ-270Z-A
CONF 002
Referenced tools for task set A350-A-57-XX-P036-01000-93AA-A Replacement of
Fasteners on the CWB
T o accomplish this Service Bulletin it is necessary to use the tools listed in:
Ref. MP A350-A-28-11-XX-03ZZZ-270Z-A
CONF 003
Referenced tools for task set A350-A-57-XX-P036-01000-93AA-A Replacement of
Fasteners on the CWB
T o accomplish this Service Bulletin it is necessary to use the tools listed in:
Ref. MP A350-A-28-11-XX-03ZZZ-270Z-A

### Page 51

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 51
CONF 004
Referenced tools for task set A350-A-57-XX-P036-01000-93AA-A Replacement of
Fasteners on the CWB
T o accomplish this Service Bulletin it is necessary to use the tools listed in:
Ref. MP A350-A-28-11-XX-03ZZZ-270Z-A
CONF ALL
C. CONSUMABLES
CONF 001
Consumables for task set A350-A-57-XX-P036-01000-93AA-A Replacement of
Fasteners on the CWB
ITEM REFERENCE CML DESCRIPTION DRAWING SEE NOTES
04PAG2
Polyurethane Coating
- - Fuel Vapour Barrier
Structure
04QAC5
Coating - - Corrosion
Inhibiting Fastener Head
Protection
04TMB2 Varnish - - ElectricalBonding Structure
06AAC1 Polysulfide Sealant -General Purpose Interfay
06ABA1 Polysulfide Sealant - FuelT ank Brushable
08BAA9 Non Aqueous Cleaner -General
12AEB1
Corrosion Preventive
Compound - Heavy Duty
Long Durability Hard Film
14SBA1 T extile - Lint free Cotton
14SBB1 T extile - Lint free Fuel T ank
Consumables for task set A350-A-57-XX-P036-01000-93BA-A Additional Work for
Aircraft Modified by any Previous Issue
ITEM REFERENCE CML DESCRIPTION DRAWING SEE NOTES
04PAG2
Polyurethane Coating
- - Fuel Vapour Barrier
Structure
08BAA9 Non Aqueous Cleaner -General
12AEB1
Corrosion Preventive
Compound - Heavy Duty
Long Durability Hard Film
14SBA1 T extile - Lint free Cotton
CONF 002
Consumables for task set A350-A-57-XX-P036-01000-93AA-A Replacement of
Fasteners on the CWB

### Page 52

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 52
ITEM REFERENCE CML DESCRIPTION DRAWING SEE NOTES
04PAG2
Polyurethane Coating
- - Fuel Vapour Barrier
Structure
04QAC5
Coating - - Corrosion
Inhibiting Fastener Head
Protection
04TMB2 Varnish - - ElectricalBonding Structure
06AAC1 Polysulfide Sealant -General Purpose Interfay
06ABA1 Polysulfide Sealant - FuelT ank Brushable
08BAA9 Non Aqueous Cleaner -General
12AEB1
Corrosion Preventive
Compound - Heavy Duty
Long Durability Hard Film
14SBA1 T extile - Lint free Cotton
14SBB1 T extile - Lint free Fuel T ank
Consumables for task set A350-A-57-XX-P036-01000-93BA-A Additional Work for
Aircraft Modified by any Previous Issue
ITEM REFERENCE CML DESCRIPTION DRAWING SEE NOTES
04PAG2
Polyurethane Coating
- - Fuel Vapour Barrier
Structure
08BAA9 Non Aqueous Cleaner -General
12AEB1
Corrosion Preventive
Compound - Heavy Duty
Long Durability Hard Film
14SBA1 T extile - Lint free Cotton
CONF 003
Consumables for task set A350-A-57-XX-P036-01000-93AA-A Replacement of
Fasteners on the CWB
ITEM REFERENCE CML DESCRIPTION DRAWING SEE NOTES
04PAG2
Polyurethane Coating
- - Fuel Vapour Barrier
Structure
04QAC5
Coating - - Corrosion
Inhibiting Fastener Head
Protection
04TMB2 Varnish - - ElectricalBonding Structure
06AAC1 Polysulfide Sealant -General Purpose Interfay

### Page 53

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 53
ITEM REFERENCE CML DESCRIPTION DRAWING SEE NOTES
06ABA1 Polysulfide Sealant - FuelT ank Brushable
08BAA9 Non Aqueous Cleaner -General
12AEB1
Corrosion Preventive
Compound - Heavy Duty
Long Durability Hard Film
14SBA1 T extile - Lint free Cotton
14SBB1 T extile - Lint free Fuel T ank
Consumables for task set A350-A-57-XX-P036-01000-93BA-A Additional Work for
Aircraft Modified by any Previous Issue
ITEM REFERENCE CML DESCRIPTION DRAWING SEE NOTES
04PAG2
Polyurethane Coating
- - Fuel Vapour Barrier
Structure
08BAA9 Non Aqueous Cleaner -General
12AEB1
Corrosion Preventive
Compound - Heavy Duty
Long Durability Hard Film
14SBA1 T extile - Lint free Cotton
CONF 004
Consumables for task set A350-A-57-XX-P036-01000-93AA-A Replacement of
Fasteners on the CWB
ITEM REFERENCE CML DESCRIPTION DRAWING SEE NOTES
04PAG2
Polyurethane Coating
- - Fuel Vapour Barrier
Structure
04QAC5
Coating - - Corrosion
Inhibiting Fastener Head
Protection
04TMB2 Varnish - - ElectricalBonding Structure
06AAC1 Polysulfide Sealant -General Purpose Interfay
06ABA1 Polysulfide Sealant - FuelT ank Brushable
08BAA9 Non Aqueous Cleaner -General
12AEB1
Corrosion Preventive
Compound - Heavy Duty
Long Durability Hard Film
14SBA1 T extile - Lint free Cotton
14SBB1 T extile - Lint free Fuel T ank
Consumables for task set A350-A-57-XX-P036-01000-93BA-A Additional Work for
Aircraft Modified by any Previous Issue

### Page 54

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 54
ITEM REFERENCE CML DESCRIPTION DRAWING SEE NOTES
04PAG2
Polyurethane Coating
- - Fuel Vapour Barrier
Structure
08BAA9 Non Aqueous Cleaner -General
12AEB1
Corrosion Preventive
Compound - Heavy Duty
Long Durability Hard Film
14SBA1 T extile - Lint free Cotton
CONF 001
Referenced consumables for task set A350-A-57-XX-P036-01000-93AA-A
Replacement of Fasteners on the CWB
T o accomplish this Service Bulletin it is necessary to use the consumable materials listed in:
Ref. MP A350-A-20-51-20-00ZZZ-25BZ-A
Ref. MP A350-A-20-51-20-04ZZZ-264Z-A
Ref. MP A350-A-21-2X-XX-00ZZZ-720Z-A
Ref. MP A350-A-25-28-61-00ZZZ-720Z-A
Ref. MP A350-A-25-81-63-00ZZZ-720Z-A
Ref. MP A350-A-28-11-XX-00ZZZ-270Z-A
Ref. MP A350-A-28-1X-XX-02ZZZ-200Z-A
Ref. MP A350-A-50-13-61-00ZZZ-720Z-A
Ref. MP A350-A-53-XX-XX-0BZZZ-720Z-A
Ref. MP A350-A-57-11-65-00ZZZ-310Z-A
Referenced consumables for task set A350-A-57-XX-P036-01000-93BA-A
Additional Work for Aircraft Modified by any Previous Issue
T o accomplish this Service Bulletin it is necessary to use the consumable materials listed in:
Ref. MP A350-A-21-2X-XX-00ZZZ-720Z-A
Ref. MP A350-A-25-28-61-00ZZZ-720Z-A
Ref. MP A350-A-25-81-63-00ZZZ-720Z-A
Ref. MP A350-A-50-13-61-00ZZZ-720Z-A
Ref. MP A350-A-53-XX-XX-0BZZZ-720Z-A
CONF 002
Referenced consumables for task set A350-A-57-XX-P036-01000-93AA-A
Replacement of Fasteners on the CWB
T o accomplish this Service Bulletin it is necessary to use the consumable materials listed in:
Ref. MP A350-A-20-51-20-00ZZZ-25BZ-A
Ref. MP A350-A-20-51-20-04ZZZ-264Z-A
Ref. MP A350-A-21-2X-XX-00ZZZ-720Z-A
Ref. MP A350-A-25-28-61-00ZZZ-720Z-A
Ref. MP A350-A-25-81-63-00ZZZ-720Z-A

### Page 55

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 55
Ref. MP A350-A-28-11-XX-00ZZZ-270Z-A
Ref. MP A350-A-28-1X-XX-02ZZZ-200Z-A
Ref. MP A350-A-50-13-61-00ZZZ-720Z-A
Ref. MP A350-A-53-XX-XX-0BZZZ-720Z-A
Ref. MP A350-A-57-11-65-00ZZZ-310Z-A
Referenced consumables for task set A350-A-57-XX-P036-01000-93BA-A
Additional Work for Aircraft Modified by any Previous Issue
T o accomplish this Service Bulletin it is necessary to use the consumable materials listed in:
Ref. MP A350-A-21-2X-XX-00ZZZ-720Z-A
Ref. MP A350-A-25-28-61-00ZZZ-720Z-A
Ref. MP A350-A-25-81-63-00ZZZ-720Z-A
Ref. MP A350-A-50-13-61-00ZZZ-720Z-A
Ref. MP A350-A-53-XX-XX-0BZZZ-720Z-A
CONF 003
Referenced consumables for task set A350-A-57-XX-P036-01000-93AA-A
Replacement of Fasteners on the CWB
T o accomplish this Service Bulletin it is necessary to use the consumable materials listed in:
Ref. MP A350-A-20-51-20-00ZZZ-25BZ-A
Ref. MP A350-A-20-51-20-04ZZZ-264Z-A
Ref. MP A350-A-21-2X-XX-00ZZZ-720Z-A
Ref. MP A350-A-25-28-61-00ZZZ-720Z-A
Ref. MP A350-A-25-81-63-00ZZZ-720Z-A
Ref. MP A350-A-28-11-XX-00ZZZ-270Z-A
Ref. MP A350-A-28-1X-XX-02ZZZ-200Z-A
Ref. MP A350-A-50-13-61-00ZZZ-720Z-A
Ref. MP A350-A-53-XX-XX-0BZZZ-720Z-A
Ref. MP A350-A-57-11-65-00ZZZ-310Z-A
Referenced consumables for task set A350-A-57-XX-P036-01000-93BA-A
Additional Work for Aircraft Modified by any Previous Issue
T o accomplish this Service Bulletin it is necessary to use the consumable materials listed in:
Ref. MP A350-A-21-2X-XX-00ZZZ-720Z-A
Ref. MP A350-A-25-28-61-00ZZZ-720Z-A
Ref. MP A350-A-25-81-63-00ZZZ-720Z-A
Ref. MP A350-A-50-13-61-00ZZZ-720Z-A
Ref. MP A350-A-53-XX-XX-0BZZZ-720Z-A
CONF 004
Referenced consumables for task set A350-A-57-XX-P036-01000-93AA-A
Replacement of Fasteners on the CWB
T o accomplish this Service Bulletin it is necessary to use the consumable materials listed in:

### Page 56

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 56
Ref. MP A350-A-20-51-20-00ZZZ-25BZ-A
Ref. MP A350-A-20-51-20-04ZZZ-264Z-A
Ref. MP A350-A-21-2X-XX-00ZZZ-720Z-A
Ref. MP A350-A-25-28-61-00ZZZ-720Z-A
Ref. MP A350-A-25-81-63-00ZZZ-720Z-A
Ref. MP A350-A-28-11-XX-00ZZZ-270Z-A
Ref. MP A350-A-28-1X-XX-02ZZZ-200Z-A
Ref. MP A350-A-50-13-61-00ZZZ-720Z-A
Ref. MP A350-A-53-XX-XX-0BZZZ-720Z-A
Ref. MP A350-A-57-11-65-00ZZZ-310Z-A
Referenced consumables for task set A350-A-57-XX-P036-01000-93BA-A
Additional Work for Aircraft Modified by any Previous Issue
T o accomplish this Service Bulletin it is necessary to use the consumable materials listed in:
Ref. MP A350-A-21-2X-XX-00ZZZ-720Z-A
Ref. MP A350-A-25-28-61-00ZZZ-720Z-A
Ref. MP A350-A-25-81-63-00ZZZ-720Z-A
Ref. MP A350-A-50-13-61-00ZZZ-720Z-A
Ref. MP A350-A-53-XX-XX-0BZZZ-720Z-A
CONF ALL
D. LIST OF NEW PARTS
CONF 001
Part kit 57P036A01R03
Cost 6400.00 USD
Availability 210 d (calendar days from receipt of order)
NOTE(S)
The sales terms (costs and availability) are estimated in relation to economic
conditions. The latest valid price and lead time for ordering purposes shall be
obtained through the AIRBUS Spares portal or through a request for quotation to
airbus.kit@airbus.com.
The availability given above is the standard lead time from the date of your purchase
order. If items are required before this time, please include a retrofit planning
schedule with your order so that we can try to comply with your requirements.
Procurement address D4296
AIRBUS
Material, Logistics and Suppliers ATP II B,
Hein-Sass-Weg 24
21129 HAMBURG
GERMANY
Phone: +49 40 743 51775
E-mail: airbus.kit@airbus.com
Internet: http://spares.airbus.com
NOTE(S)

### Page 57

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 57
Customers with aircraft shown in the applicability of this Service Bulletin should send
a purchase order to AIRBUS at the address given above and quote the number of this
Service Bulletin.
T o cover any possible deviation of fastener installation additional shipping sets of
fasteners with oversize and additional length should be ordered in reference to RIL
V57M19004719. The part number of these fasteners and the positions in the CWB
structure should be recorded in the report sheets, refer to Appendix REPORTING
SHEET.
ITEM PART No. QTY (UM) KEYWORD DRAWING SEE NOTES
1 EN6115V6-15 42 BOLT
4 ASNA2536-6 64 NUT
5 EN6115V6-16 32 BOLT
8 EN6115V5-14 24 BOLT
11 ASNA2536-5 64 NUT
12 EN6115V5-13 48 BOLT
15 EN6115V7-22 4 BOLT
18 ASNA2532-7 16 NUT
19 EN6115V7-20 4 BOLT
22 EN6115V7-19 4 BOLT
25 EN6115V7-18 4 BOLT
28 ASNA2538-6 10 NUT
29 EN6115V7-17 10 BOLT
32 ASNA2538P7 10 NUT
33 ABS0559VBV12-28 4 BOLT
36 ASNA2532-12 4 NUT
37 NSA5372E1216A 4 WASHER
38 ASNA2538P5 8 NUT
39 EN6115V6-17 10 BOLT
42 ASNA2538P6 8 NUT
43 ASNA2536P6 2 NUT
44 EN6115V10-30 8 BOLT
47 ASNA2536-10 8 NUT
48 EN6115V9-15 12 BOLT
51 ASNA2538P9 12 NUT
52 EN6115V8-15 64 BOLT
55 ASNA2538P8 112 NUT
56 EN6115V8-13 48 BOLT
59 EN6115V8-30 24 BOLT
65 ASNA2536-8 24 NUT
70 NSA5372E1216B 4 WASHER

### Page 58

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 58
ITEM PART No. QTY (UM) KEYWORD DRAWING SEE NOTES
71 NSA5372E1216C 4 WASHER
NOTE(S)
Refer to the AIRBUS Ref. SM if you find part numbers of hardware components which
you cannot identify. The SM will give you the correct part number to part number
relationship.
CONF 002-004
Part kit 57P036A04R04
Cost 6800.00 USD
Availability 210 d (calendar days from receipt of order)
NOTE(S)
The sales terms (costs and availability) are estimated in relation to economic
conditions. The latest valid price and lead time for ordering purposes shall be
obtained through the AIRBUS Spares portal or through a request for quotation to
airbus.kit@airbus.com.
The availability given above is the standard lead time from the date of your purchase
order. If items are required before this time, please include a retrofit planning
schedule with your order so that we can try to comply with your requirements.
Procurement address D4296
AIRBUS
Material, Logistics and Suppliers ATP II B,
Hein-Sass-Weg 24
21129 HAMBURG
GERMANY
Phone: +49 40 743 51775
E-mail: airbus.kit@airbus.com
Internet: http://spares.airbus.com
NOTE(S)
Customers with aircraft shown in the applicability of this Service Bulletin should send
a purchase order to AIRBUS at the address given above and quote the number of this
Service Bulletin.
T o cover any possible deviation of fastener installation additional shipping sets of
fasteners with oversize and additional length should be ordered in reference to RIL
V57M19004719. The part number of these fasteners and the positions in the CWB
structure should be recorded in the report sheets, refer to Appendix REPORTING
SHEET.
ITEM PART No. QTY (UM) KEYWORD DRAWING SEE NOTES
1 EN6115V6-15 42 BOLT
4 ASNA2536-6 64 NUT
5 EN6115V6-16 32 BOLT
8 EN6115V5-14 24 BOLT
11 ASNA2536-5 64 NUT
12 EN6115V5-13 48 BOLT
15 EN6115V7-22 4 BOLT
18 ASNA2532-7 16 NUT
19 EN6115V7-20 4 BOLT
22 EN6115V7-19 4 BOLT

### Page 59

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 59
ITEM PART No. QTY (UM) KEYWORD DRAWING SEE NOTES
25 EN6115V7-18 4 BOLT
28 ASNA2538-6 10 NUT
29 EN6115V7-17 10 BOLT
32 ASNA2538P7 10 NUT
33 ABS0559VBV12-28 4 BOLT
36 ASNA2532-12 4 NUT
37 NSA5372E1216A 4 WASHER
38 ASNA2538P5 8 NUT
39 EN6115V6-17 10 BOLT
42 ASNA2538P6 8 NUT
43 ASNA2536P6 2 NUT
44 EN6115V10-30 8 BOLT
47 ASNA2536-10 8 NUT
48 EN6115V9-15 12 BOLT
51 ASNA2538P9 12 NUT
52 EN6115V8-15 24 BOLT
55 ASNA2538P8 112 NUT
56 EN6115V8-13 48 BOLT
59 EN6115V8-30 24 BOLT
62 EN6115V8-14 40 BOLT
65 ASNA2536-8 24 NUT
70 NSA5372E1216B 4 WASHER
71 NSA5372E1216C 4 WASHER
NOTE(S)
The Part Kit 57P036A04R03 identified in the previous revision of this Service Bulletin
can be used and the additional quantity of the bolt EN6115V8-15 can be ordered in
reference to RIL V57M19004719.
Refer to the AIRBUS Ref. SM if you find part numbers of hardware components which
you cannot identify. The SM will give you the correct part number to part number
relationship.
CONF ALL
E. LIST OF EXISTING PARTS
No parts

### Page 60

A350
SERVICE BULLETIN
REV 00 Jan 17/20 A350-57-P036
REV 03 Dec 12/22 Page 60
3. ACCOMPLISHMENT INSTRUCTIONS
Task set A350-A-57-XX-P036-01000-93AA-A (A350-A-57-XX-P036-01ZZZ-93AZ-A)
Replacement of Fasteners on the CWB
WARNING: MAKE SURE THAT YOU OBEY ALL THE WARNINGS AND ALL THE CAUTIONS
INCLUDED IN THE REFERENCED PROCEDURES.
CAUTION: ALWAYS OBEY THE PRECAUTIONS THAT FOLLOW TO KEEP ELECTRICAL
WIRING IN A SATISFACTORY CONDITION (ELECTRICALLY AND MECHANICALLY
SERVICEABLE). WHEN YOU DO A MAINTENANCE WORK, REPAIRS OR
MODIFICATIONS, ALWAYS KEEP ELECTRICAL WIRING, COMPONENTS AND
THE WORK AREA AS CLEAN AS POSSIBLE. TO DO THIS:
- PUT PROTECTION, SUCH AS PLASTIC SHEETING, CLOTHS, ETC., AS
NECESSARY ON WIRING AND COMPONENTS.
- REGULARLY REMOVE ALL SHAVINGS, UNWANTED MATERIAL AND
OTHER CONTAMINATION.
THESE PRECAUTIONS WILL DECREASE THE RISK OF CONTAMINATION AND
DAMAGE TO THE ELECTRICAL WIRING INSTALLATION.
IF THERE IS CONTAMINATION, REFER TO Ref. ESP A350-A-20-55-XX-01ZZZ-
042Z-A.
NOTE: The accomplishment instructions of this Service Bulletin include procedures given in
other documents or in other sections of the Service Bulletin. When the words “refer to”
are used and the operator has a procedure accepted by the local authority he belongs to,
the accepted alternative procedure can be used. When the words “in accordance with”
are used then the given procedure must be followed.
NOTE: The access and close-up instructions, not comprising return to service tests, in this
Service Bulletin do not constitute or affect the technical intent of the Service Bulletin.
Operators can therefore, as deemed necessary, omit or add access and/or close-up steps
to add flexibility to their maintenance operations as long as the technical intent of the
Service Bulletin is met within the set parameters.
NOTE: Manual titles given in the accomplishment instructions are referred to by acronyms. Refer
to paragraph 1.J., References, for the definition of acronyms.
NOTE: This Service Bulletin is classified mandatory or expected to be classified mandatory by
an Airworthiness Directive (AD). The paragraphs 3.C. and 3.E. in these accomplishment
instructions are Required for Compliance (RC) and must be done to comply with the AD.
T o allow more flexibility, the rule "refer to" and "in accordance with" will apply to these
paragraphs 3.C. and 3.E. Other paragraphs are recommended and may be deviated from,
done as part of other actions or done with accepted methods different from those given
in the Service Bulletin, as long as the RC paragraphs can be done and the aircraft can be
put back into a serviceable condition.
NOTE: This Service Bulletin contains the instructions for the on-aircraft maintenance necessary
to ensure the continued airworthiness of the aircraft.
For any deviations to the instructions, including Required for Compliance paragraph
contained herein, contact AIRBUS for further instructions and approval.
NOTE: Discarded parts must be managed at the operator's discretion.
A. TASK SET ASSOCIATED INFORMATION
CONF 001
Maintenance Configuration
Fuel tanks opened

The text continues at https://openairdocs.org/service-documents/airbus/a350-57-p036/file/fd0e582aadae.md?from=61

---
OpenAirDocs.org is an independent research project of [Contrail Labs](https://contraillabs.com/). It is not affiliated with the FAA or the NTSB. Source documents are U.S. government works in the public domain, except the copies of manufacturers’ service documents, which belong to their rights holders.