# Airbus All Operators Transmission A24L007-20

Copy: No revision named ("A24L007-20 Rev 00 App1 and 2"), 14 pages: PDF https://openairdocs.org/files/sha256/c7/f7/c7f7d065c7c0eea09bd9a8ff684f5da8fa5eb91a835d627e170071077ef20b6c; text https://openairdocs.org/service-documents/airbus/aot-a24l007-20/file/c7f7d065c7c0.md. Rights: © Airbus S.A.S. Filed by the FAA in regulations.gov docket FAA-2021-0547, the docket of AD 2021-21-02. Not covered by OpenAirDocs’ CC0 dedication.

## Details

- Manufacturer: [Airbus](https://openairdocs.org/service-documents/airbus.md)
- Type: Other document (All Operators Transmission)
- Number: A24L007-20
- Page: https://openairdocs.org/service-documents/airbus/aot-a24l007-20

Also cited in [1 proposed AD](https://openairdocs.org/service-documents/airbus/aot-a24l007-20/proposed.md).

## Text (14 pages)

Rights: © Airbus S.A.S. Filed by the FAA in regulations.gov docket FAA-2021-0547, the docket of AD 2021-21-02. Not covered by OpenAirDocs’ CC0 dedication. Some pages are OCR from a scan. OCR can misread letters and numbers. Each page's text from the PDF; open the PDF at a page with #page=N.

### Page 1

CUSTOMER SERVICES DIRECTORATE
2 ROND POINT EMILE DEWOITINE
31700 BLAGNAC FRANCE
TELEPHONE + 33 (0)5 61 93 33 33
ALERT OPERATORS TRANSMISSION - AOT
AOT ref: A24L007-20 Rev 00 Page 1 of 6 Date: 23-SEP-2020
© AIRBUS S.A.S. 2020. ALL RIGHTS RESERVED. CONFIDENTIAL AND PROPRIETARY DOCUMENT
SUBJECT: ATA 24 – Ni-Cd Batteries - Risk of capacity reduction during aircraft parking & storage
AIRCRAFT TYPE: A330,A340
OUR REF.: A24L007-20 Rev 00 dated 23-SEP-2020
EFFECTIVITY DATE: 23-SEP-2020
1. AIRCRAFT AFFECTED
 
All Aircraft
2. REFERENCED DOCUMENTATION                                          
2.1 APPENDIX
Appendix 1: Short term action
Appendix 2: On-wing battery preservation procedure
 2.2 REFERENCES
Ref 1: ISI 24.00.00046 (ATA 24 - Recommendations for parking & storage during COVID19       
period)
Ref 2: Task in AMM PB 10-10-00 (Parking and storage procedure)
Ref 3: Task in AMM PB 10-11-00 (Parking periodic ground checks)
Ref 4: Task in AMM PB 10-12-00 (Storage periodic ground checks)
Ref 5: Task in AMM PB 10-30-00 (Return to service)
Ref 6: Task in AMM PB 24-38-51 & 24-38 -52 (Removal of the battery)
Ref 7: Task in AMM PB 31-21-00 (Adjustment of the Clock)
Ref 8: Task in AMM PB 24-41-00 (Energize the aircraft electrical circuits)
Ref 9: Task in AMM PB 24-41-00 (De-energize the aircraft electrical circuits)
Ref 10: Task in AMM PB 24-42-00 (Energize the ground service network from the external power)
Ref 11: Task in AMM PB 24-42-00 (De-energize the ground service network from the external
         power)
Ref 12: SAFT Battery CMM 24-38-52 (Battery PN 4059)
Ref 13: SAFT Battery CMM 24-38-53 (Battery PN 405CH)
Ref 14: SAFT Battery CMM 24-38-54 (Battery PN 505CH)

### Page 2

ALERT OPERATORS TRANSMISSION - AOT 
AOT ref: A24L007-20 Rev 00 Page 2 of 6 Date: 23-SEP-2020
© AIRBUS S.A.S. 2020. ALL RIGHTS RESERVED. CONFIDENTIAL AND PROPRIETARY DOCUMENT
3. REASON
The purpose of this AOT is to inform the operators:
that the capacity of the batteries (FINs 2PB1, 2PB2 and 2PB3) may be reduced due to repetitive 
disconnections and connections during an aircraft parking or storage period, as detailed in            
§ 3.1 and § 4.2.1 of this AOT.
and of the need of restoring the capacity of these batteries per ref 12 (or ref 13 or ref 14), within 
a defined time frame.
3.1 FACTS
In the frame of massive aircraft grounding due to COVID-19 pandemic, several engineering reviews 
have been organised between Airbus and the battery supplier SAFT. During these reviews, it was 
highlighted that the current AMM aircraft parking and storage procedures (per ref 2, ref 3 & ref 4) 
requiring physical disconnection and periodic reconnection of batteries may induce a reduction in 
capacity for Ni-Cd batteries, when repetitively done.
The current AMM aircraft parking and storage procedures require:
to disconnect the batteries when the aircraft is parked or stored and de-energized for more than 
2 days (per ref 2).
to reconnect the batteries when aircraft is energized during aircraft periodic ground checks (per 
ref 3 or ref 4). 
to disconnect the batteries again at the end of the aircraft periodic ground checks (per ref 3 or 
ref 4).
When a Ni-Cd battery is physically disconnected from the aircraft loads, it self-discharges, due to an 
electrochemical phenomenon, thus, inducing a permanent reduction of battery capacity. 
After each cycle of battery self-discharge, the available battery capacity will decrease progressively and 
will not be recovered to 100% of its initial capacity even when the battery is charged again from the 
aircraft electrical network during the periodic ground checks per ref 3 or ref 4.
In order to restore the battery capacity, the battery must be sent to an approved battery shop for a 
periodical check or a battery regular check or a battery general overhaul per ref 12 (or ref 13 or ref 14).
Note 1: This action in shop includes a battery charge at constant current which allows to restore the   
              battery capacity. 
Note 2: On aircraft, it is not possible to:
restore the battery capacity as the battery is charged at constant voltage.
check the battery capacity.
3.2 CONSEQUENCES
As the battery capacity may be significantly reduced, the battery performance may be affected and 
hence, the battery functions may be not fully guaranteed.

### Page 3

ALERT OPERATORS TRANSMISSION - AOT 
AOT ref: A24L007-20 Rev 00 Page 3 of 6 Date: 23-SEP-2020
© AIRBUS S.A.S. 2020. ALL RIGHTS RESERVED. CONFIDENTIAL AND PROPRIETARY DOCUMENT
4. SHORT TERM ACTION
NOTE: This AOT is classified mandatory or expected to be classified mandatory by an Airworthiness 
Directive (AD). The accomplishment instructions marked as Required for Compliance (RC) must be 
done to comply with the AD. “RC” is indicating these paragraphs accordingly. If an AD is issued, 
reference should be made to the AD for the mandated accomplishment timescale.
NOTE: The accomplishment instructions of this AOT include procedures given in other documents or 
in other sections of the AOT. When the words ’refer to’ are used and the operator has a procedure 
accepted by the local authority he belongs to, the accepted alternative procedure can be used. When 
the words ’in accordance with’ are used then the given procedure must be followed.
NOTE: The access and close-up instructions, not comprising return to service tests, in this AOT do not 
constitute or affect the technical intent of the AOT. Operators can therefore, as deemed necessary, omit 
or add access and/or close-up steps to add flexibility to their maintenance operations as long as the 
technical intent of the AOT is met within the set parameters.
4.1 PLANNING AND MANPOWER
4.1.1 ACCOMPLISHMENT TIMESCALE (RC)
The compliance time for this AOT is defined as follows: 
          Within 6 months after the AOT effective date or prior to next flight, whichever occurs latest.
For additional information, refer to appendix 1 of this AOT.
4.1.2 MANPOWER
N/A
4.2 DESCRIPTION
4.2.1 APPLICABILITY
Group A
This AOT is applicable to Ni-Cd batteries (PN 4059 or PN 405CH or PN 505CH) which have been 
disconnected, kept (on aircraft) and reconnected on aircraft per ref 2 and ref 3 or ref 4 more than 4 
times during an aircraft parking or storage period since last battery periodical check, battery regular 
check or battery general overhaul per ref 12 (or ref 13 or ref 14) and which are still installed on aircraft, 
at the effectivity date of this AOT.
Refer to § 4.2.2 and § 4 .2.3.1 of this AOT for the accomplishment of the required actions.
Group B
This AOT is also applicable to all other Ni-Cd batteries (PN 4059 or PN 405CH or PN 505CH) not 
identified in group A.
Refer to § 4.2.3.2 of this AOT for the accomplishment of the required actions.

### Page 4

ALERT OPERATORS TRANSMISSION - AOT 
AOT ref: A24L007-20 Rev 00 Page 4 of 6 Date: 23-SEP-2020
© AIRBUS S.A.S. 2020. ALL RIGHTS RESERVED. CONFIDENTIAL AND PROPRIETARY DOCUMENT
4.2.2 TERMINATING ACTIONS (RC)
The restoration of the capacity of the batteries, identified in group A in § 4.2.1 of this AOT, is the 
terminating action for this AOT and is defined as follows:
-   Do a battery periodical check or a battery regular check or a battery general overhaul per ref 
12 (or ref 13 or ref 14) in an approved battery shop.
Note: This action in shop includes a battery charge at constant current allowing to restore 
the battery capacity.
4.2.3 APPLICATION OF NEW AMM PROCEDURES (RC)
In order to preserve the capacity of the batteries, the AMM will be revised to introduce, as detailed in               
§ 5.2 of this AOT:
the off-wing battery preservation or the on-wing battery preservation, when the aircraft is 
parked and de-energized for more than 2 days. 
the off-wing battery preservation when the aircraft is stored and de-energized for more than 2 
days.
4.2.3.1 For Batteries identified in group A in § 4.2.1 of this AOT and installed on aircraft
After the terminating action, as detailed in § 4.2.2 of this AOT, is completed, 
the off-wing battery preservation or the on-wing battery preservation must be applied when the 
aircraft is parked and de-energized for more than 2 days. 
the off-wing battery preservation must be applied when the aircraft is stored and de-energized 
for more than 2 days
From the effectivity date of this AOT, operators can start applying: 
the off-wing battery preservation or the on-wing battery preservation when the aircraft is parked 
and de-energized more than 2 days. However, it is recommended that the battery capacity 
restoration, as detailed in § 4.2.2 of this AOT, is performed before the application of the on-
wing battery preservation.
Note 1: A battery, affected by the issue detailed in § 3.1 of this AOT, cannot be restored through 
the application of the on-wing battery preservation.
Note 2: If the on-wing preservation procedure is applied for batteries with a reduced capacity, 
there is a risk that these batteries are over discharged before the aircraft is energised again per 
ref 3 or ref 4. This situation may prevent the battery from being recharged on aircraft.
the off-wing battery preservation when the aircraft is stored and de-energized for more than 2 
days.

### Page 5

ALERT OPERATORS TRANSMISSION - AOT 
AOT ref: A24L007-20 Rev 00 Page 5 of 6 Date: 23-SEP-2020
© AIRBUS S.A.S. 2020. ALL RIGHTS RESERVED. CONFIDENTIAL AND PROPRIETARY DOCUMENT
4.2.3.2 For batteries identified in group B in § 4.2.1 of this AOT and installed on aircraft
After the effectivity date of this AOT, 
the off-wing battery preservation or the on-wing battery preservation must be applied when the 
aircraft is parked and de-energized more than 2 days. 
the off-wing battery preservation must be applied when the aircraft is stored and de-energized 
for more than 2 days.
4.2.4 ACCESS
 N/A
 4.2.5 INSPECTION REQUIREMENTS 
 N/A
 4.2.6 FINDINGS 
N/A
 4.3 SPARES AND TOOLING
 N/A
5. FURTHER INFORMATION
 5.1 FOLLOW-UP PLAN
A webinar will be organized within two weeks after the publication of this AOT to answer all questions 
pertaining to this AOT.  
Additional information related to this AOT (for instance, frequently asked questions, complementary 
recommendations if any) will be provided through ref 1.
5.2 IMPACTED DOCUMENTATION
The AMM will be revised (currently planned for JAN 2021) to introduce, as detailed below, the off-wing 
battery preservation or the on-wing battery preservation. The availability of the AMM advance copies is 
currently planned for 19-NOV-2020.
 A - Off Wing Battery Preservation
If the aircraft is parked or stored and de-energized more than 2 days, the batteries have to be 
disconnected and removed from aircraft per ref 6.
Note 1: To allow ground periodic checks during an aircraft parking per ref 3 or a storage period 
per ref 4, batteries must be re-installed on aircraft and re-connected to the aircraft electrical 
network.
Note 2: Batteries removed from aircraft in parking or storage have to be stored per ref 12 (or 
ref 13 or ref 14).

### Page 6

ALERT OPERATORS TRANSMISSION - AOT 
AOT ref: A24L007-20 Rev 00 Page 6 of 6 Date: 23-SEP-2020
© AIRBUS S.A.S. 2020. ALL RIGHTS RESERVED. CONFIDENTIAL AND PROPRIETARY DOCUMENT
B - On-Wing Battery Preservation
The on-wing battery preservation is a new procedure consisting in leaving the battery physically 
connected to the aircraft electrical network and keeping a minimum battery hot bus consumption, when 
the aircraft is parked and de-energized more than 2 days. This is achieved by pulling the circuit breakers 
of some loads supplied by the battery hot buses, as detailed in the appendix 2 of this AOT. In this 
configuration, there is no battery self-discharge and hence, the battery  progressive and permanent 
reduction of the capacity of the batteries is avoided.
When the on-wing preservation procedure is applied, batteries must be sent to an approved battery 
shop for a battery regular check per ref 12 (or ref 13 or ref 14), every six months during the aircraft 
parking period.   
6. AOT APPROVAL
The technical content of this document is approved under the authority of the DOA ref.EASA.21J.031.
7. REPORTING
Questions about this AOT are to be addressed to Airbus Customer Services through  TechRequest on 
Airbus World, selecting Maintenance Engineering Domain, Engineering Support Section and                      
ATA 24-38.
As per latest reporting policy (Ref to OIT 999.0018/16), inspection results (with or without findings) are 
to be addressed to Airbus Customer Services through the generic e-mail address:  
inspection.results@airbus.com.
  
Best Regards,
Christian FREMONT
VICE PRESIDENT ENGINEERING SUPPORT
CUSTOMER SERVICES
 
Stéphane GOSSELIN
VICE PRESIDENT A330/340 PROGRAMME
CUSTOMER SERVICES

### Page 7 (OCR)

Appendix 1 : Short Term Action
TcT = To + 6 months
[AOT effectivity date]  [Compliance Time]
[Example 1]
[Example 2]
[Example 3]
• Aircraft in parking  Aircraft returns to service  Aircraft in service
Figure 1
Examples as  per Figure 1  Applicability  AOT  Terminating action needed?  When?  needed, if aircraft is parked again or remain  Application of new AMM procedures  in parking?
Example 1  Group A  Tcr, at the latest  Yes  Recommended before AOT terminating action  Required after AOT terminating action
Yes
Example 2  Group A  Tcr, at the latest  Recommended before AOT terminating action  Required after AOT terminating action
Example 3  Group A  Prior to next flight  Yes  Recommended before AOT terminating action  Required after AOT terminating action
Example 1  Group B  No  Required after AOT effectivity date
Example 2  Group B  No  Required after AOT effectivity date
Example 3  Group B  No  Required after AOT effectivity date
AOT ref: A24L007-20 Rev 00  Page 1 of 1  Date: 23-SEP-2020

### Page 8 (OCR)

Appendix 2: On-wing battery preservation procedure
The procedures per ref 2, ref 3 and ref 5 are modified to include the instructions for
the on-wing battery preservation, as detailed below:
A/ The parking and storage procedure (ref 2) is modified as follows:
• Perform all steps from step 3.A. (1) to step 4.T.(2) of ref 2.
• If the parking period is more than 2 days, perform the following steps instead of step 4.T.(3) of
ref 2 :
(1) In the cockpit, on overhead panel 235VU, release the pushbutton switches of BAT 1(2) (APU).
(2) In the cockpit, on the overhead panel 235VU, check the voltage of the BAT 1(2) (APU):
(a) If one of the battery voltages is less than 26V, perform a cycle of battery charge as
follows:
• On the ECAM control panel:
- Push the ELEC DC key to get the ELEC DC system page.
On the control panel 235VU:
- Push the related BAT 1(2) (APU) pushbutton switch (OFF and FAULT legends
off) to start the charging cycle of the battery 1(2)(APU),
On the lower ECAM DU:
The green line between the BAT 1(2)(APU) indication and the DC BAT
busbar indication comes into view. The arrow points to the BAT 1(2)(APU)
indication.
The related parameter indications (voltage and current) come into view
green.
• Wait until the battery contactor opens.
The green line between the BAT 1(2) (APU) indication and the DC BAT
busbar indication:
- Goes out of view if the battery is correctly charged
- Stays in view if a battery charging is necessary.
Note: The time for the battery to charge can be 30 minutes.
• On the lower ECAM DU, on the ELEC page, make sure that the battery voltage is
more than 26VDC and the battery discharge current is equal to or less than 1A.
(b) Otherwise, push the BAT 1(2)(APU) pushbutton switch (OFF and FAULT legends off).
• Perform step 4.T. (4) of ref 2
• If the parking period is more than 2 days, perform the following steps after step 4.T.(4) of ref 2.
(1) Energize the ground service network from the external power per ref 10
AOT ref: A24L007-20 Rev 00  Page 1 of 7  Date: 23-SEP- 2020

### Page 9 (OCR)

Note: This step is necessary only to have light in the avionic bay and in the cockpit. If a torch
is used to perform steps (2) to (4) below, step (1) above can be disregarded.
(2) In the cockpit, on overhead panel 235VU, put the WARNING NOTICE(S) in position "Do not to
operate the batteries".
(3) Get access to the avionics compartment:
- Put the ACCESS PLATFORM 3М (10 FT) - ADJUSTABLE in position at the avionics
compartment door 811.
- Open access door 811.
- Open emergency circuit-breaker panels 740VU and 742VU.
(4) Immediately open, safety and tag these circuit breakers after the aircraft is de-energized. :
Panel  Designation  Location
740VU  C/B 470PP BAT1 SPLY  24PB1  T64
740VU  C/B 470PP BAT2 SPLY  24PB2  T65
742VU  C/B CLOCK TBU  4FS  K73
742VU  C/B ECMU 2 ESS  3XM2  H77
742VU  C/B REFUEL BAT/GND SW  10PR  G73
742VU  C/B ADIRU 2 BAT  7FP2  G75
742VU  C/B ADIRU 3 BAT  7FP3  G76
742VU  C/B AUTOEXTING  31WF  G78
Note: C/Bs 24PB1 and 24PB2 could be installed depending on aircraft configuration. If these
C/Bs are not installed, disregard the step (4) for these two C/Bs
(5) Put the ELEC/BAT/1/2/APU switch (1PV) on the overhead panel (235VU) in the APU BAT
position.
(6) De-energize the ground service network from the external power per ref 11
Note: If a torch has been used to perform steps (2) to (4) above, step (6) above can be
disregarded.
• Perform all steps from step 5.A.(1) to step 5.B.(3) of ref 2.
AOT ref: A24L007-20 Rev 00  Page 2 of 7  Date: 23-SEP- 2020

### Page 10 (OCR)

B/ The parking periodic ground checks procedure (ref 3) is modified as
follows:
• Perform all steps from step 3.A. (1) to step 3.B.(2) of ref 3.
• If the parking period is more than 2 days, perform the following steps after step 3.B. (2) of ref 3 :
(1) Energize the ground service network from the external power per ref 10
Note: This step is necessary only to have light in the avionic bay and in the cockpit. If a torch
is used to perform steps (2) to (4) below, step (1) above can be disregarded.
(2) Get access to the avionics compartment.
- Put the ACCESS PLATFORM 3M (10 FT) - ADJUSTABLE in position at the avionics
compartment door 811.
- Open access door 811.
- Open emergency circuit-breaker panels 740VU and 742VU.
(3) Remove safety clips and tags and close these circuit breakers:
Panel  Designation  FIN  Location
740VU  C/B 470PP BAT1 SPLY  24PB1  T64
740VU  C/B 470PP BAT2 SPLY  24PB2  T65
742VU  C/B CLOCK TBU  4FS  K73
742VU  C/B ECMU 2 ESS  3XM2  H77
742VU  C/B REFUEL BAT/GND SW  10PR  G73
742VU  C/B ADIRU 2 BAT  7FP2  G75
742VU  C/B ADIRU 3 BAT  7FP3  G76
142V0  C/B AUTOEXTING  31WF  G78
Note: C/Bs 24PB1 and 24PB2 could be installed depending on aircraft configuration. If these
C/Bs are not installed, disregard the step (3) for these two C/Bs
(4) In the cockpit, on overhead panel 235VU, remove the WARNING NOTICE(S) in position "Do
not to operate the batteries".
(5) De-energize the ground service network from the external power per ref 11.
Note: If a torch has been used to perform steps (2) to (4) above, step (5) can be disregarded.
AOT ref: A24L007-20 Rev 00  Page 3 of 7  Date: 23-SEP- 2020

### Page 11 (OCR)

• Perform step 3.B.(3) but without performing step "Connect batteries 2PB1, 2PB2 and 2PB3 and
make sure that the charge is correct Ref. AMM TASK 24-38-51-400-801 and Ref. AMM TASK
24-38-52-400-801" per ref 3.
Note: Batteries are already connected at this step.
• If the parking period is more than 2 days, After step 3.B. (3) per ref 3, adjust the clock per ref 7
• Perform all steps from step 3.C. (1) to step 4.P.(2) per ref 3.
• If the parking period is more than 2 days, Perform the following steps instead of step 4.P.(3) per
ref 3:
(1) In the cockpit, on overhead panel 235VU, release the pushbutton switches of BAT 1(2) (APU).
(2) In the cockpit, on the overhead panel 235VU, check the voltage of the BAT 1(2) (APU):
(a) If one of the battery voltages is less than 26V, perform a cycle of battery charge as
follows:
• On the ECAM control panel:
- Push the ELEC DC key to get the ELEC DC system page.
• On the control panel 235VU:
- Push the related BAT 1(2)(APU) pushbutton switch (OFF and FAULT legends
off) to start the charging cycle of the battery 1(2)(APU),
• On the lower ECAM DU:
The green line between the BAT 1(2)(APU) indication and the DC BAT
busbar indication comes into view. The arrow points to the BAT 1(2) (APU)
indication.
The related parameter indications (voltage and current) come into view
green.
• Wait until the battery contactor opens.
The green line between the BAT 1(2) (APU) indication and the DC BAT
busbar indication:
Goes out of view if the battery is correctly charged
Stays in view if a battery charging is necessary.
Note: The time for the battery to charge can be 30 minutes.
• On the lower ECAM DU, on the ELEC page, make sure that the battery voltage is
more than 26VDC and the battery discharge current is equal to or less than 1A.
(b) Otherwise, push the BAT 1(2)(APU) pushbutton switch (OFF and FAULT legends off).
• Perform step 4.P. (4) of ref 3.
• If the parking period is more than 2 days, perform the following steps after step 4.P. (4) of ref 3 :
(1) Energize the ground service network from the external power per ref 10
Note: This step is necessary only to have light in the avionic bay and in the cockpit. If a torch
is used to perform steps (2) to (4) below, step (1) above can be disregarded.
AOT ref: A24L007-20 Rev 00  Page 4 of 7  Date: 23-SEP- 2020

### Page 12 (OCR)

(2) In the cockpit, on overhead panel 235VU, put the WARNING NOTICE(S) in position "Do not to
operate the batteries".
(3) Get access to the avionics compartment:
- Put the ACCESS PLATFORM 3M (10 FT) - ADJUSTABLE in position at the avionics
compartment door 811.
- Open access door 811.
- Open emergency circuit-breaker panels 740VU and 742VU.
(4) Immediately open, safety and tag these circuit breakers after the aircraft is de-energized.:
Panel  Designation  FIN  Location
740VU  C/B 470PP BAT1 SPLY  24PB1  T64
740VU  C/B 470PP BAT2 SPLY  24PB2  T65
742VU  C/B CLOCK TBU  4FS  K73
742VU  C/B ECMU 2 ESS  3XM2  H77
742VU  C/B REFUEL BAT/GND SW  10PR  G73
742VU  C/B ADIRU 2 BAT  7FP2  G75
742VU  C/B ADIRU 3 BAT  7FP3  G76
742VU  C/B AUTOEXTING  31WF  G78
Note: C/Bs 24PB1 and 24PB2 could be installed depending on aircraft configuration. If these
C/Bs are not installed, disregard the step (4) for these two C/Bs
(5) Put the ELEC/BAT/1/2/APU switch (1PV) on the overhead panel (235VU) in the APU BAT
position.
(6) De-energize the ground service network from the external power per ref 11
Note: If a torch has been used to perform steps (2) to (4) above, step (6) above can be
disregarded.
• Perform all steps from step 4.P.(5) to step 5.A. (5) per ref 3.
AOT ref: A24L007-20 Rev 00  Page 5 of 7  Date: 23-SEP- 2020

### Page 13 (OCR)

C/ The return to operation after a parking period procedure (ref 5) is modified
as follows:
• Perform the steps 3.A.(1) and 3.A.(2) of ref 5.
• If the parking period is more than 2 days, perform the following steps instead of step 3.B.(1) of
ref 5:
(1) Energize the ground service network from the external power per ref 10
Note: This step is necessary only to have light in the avionic bay and in the cockpit. If a torch
is used to perform steps (2) to (4) below, step (1) above can be disregarded.
(2) Get access to the avionics compartment.
- Put the ACCESS PLATFORM 3M (10 FT) - ADJUSTABLE in position at the avionics
compartment door 811.
- Open access door 811.
- Open emergency circuit-breaker panels 740VU and 742VU.
(3) Remove safety clips and tags and close these circuit breakers:
Panel  Designation  FIN  Location
740VU  C/B 470PP BAT1 SPLY  24PB1  T64
740VU  C/B 470PP BAT2 SPLY  24PB2  T65
742VU  C/B CLOCK TBU  4FS  K73
742VU  C/B ECMU 2 ESS  3XM2  H77
742VU  C/B REFUEL BAT/GND SW  10PR  G73
742VU  C/B ADIRU 2 BAT  7FP2  G75
742VU  C/B ADIRU 3 BAT  7FP3  G76
742VU  C/B AUTOEXTING  31WF  G78
Note: C/Bs 24PB1 and 24PB2 could be installed depending on aircraft configuration. If these
C/Bs are not installed, disregard the step (3) for these two C/Bs
(4) In the cockpit, on overhead panel 235VU, remove the WARNING NOTICE(S) in position "Do
not to operate the batteries".
(5) De-energize the ground service network from the external power per ref 11
Note: If a torch has been used to perform steps (2) to (4) above, step (5) can be disregarded.
• Perform step 3.B.(2) per ref 5.
AOT ref: A24L007-20 Rev 00  Page 6 of 7  Date: 23-SEP- 2020

### Page 14 (OCR)

• If the parking period is more than 2 days, perform the following steps after step 3.B. (2) per ref 5:
(1) Adjust the clock per ref 7.
(2) In the cockpit, on overhead panel 235VU, release the pushbutton switches of BAT 1(2) (APU).
(3) In the cockpit, on the overhead panel 235VU, check the voltage of the BAT 1(2)(APU):
(a) If one of the battery voltages is less than 26V, perform a cycle of battery charge as
follows:
• On the ECAM control panel:
- Push the ELEC DC key to get the ELEC DC system page.
• On the control panel 235VU:
- Push the related BAT 1(2)(APU) pushbutton switch (OFF and FAULT legends
off) to start the charging cycle of the battery 1(2) (APU),
• On the lower ECAM DU:
The green line between the BAT 1(2) (APU) indication and the DC BAT
busbar indication comes into view. The arrow points to the BAT 1(2) (APU)
indication.
The related parameter indications (voltage and current) come into view
green.
• Wait until the battery contactor opens.
The green line between the BAT 1(2)(APU) indication and the DC BAT
busbar indication:
Goes out of view if the battery is correctly charged
- Stays in view if a battery charging is necessary.
Note: The time for the battery to charge can be 30 minutes.
• On the lower ECAM DU, on the ELEC page, make sure that the battery voltage is
more than 26VDC and the battery discharge current is equal to or less than 1A.
(b) Otherwise, push the BAT 1(2) (APU) pushbutton switch (OFF and FAULT legends off).
• Perform all steps from step 3.B. (3) to step 5.A. (3) of ref 5.
AOT ref: A24L007-20 Rev 00  Page 7 of 7  Date: 23-SEP- 2020

---
OpenAirDocs.org is an independent research project of [Contrail Labs](https://contraillabs.com/). It is not affiliated with the FAA or the NTSB. Source documents are U.S. government works in the public domain, except the copies of manufacturers’ service documents, which belong to their rights holders.