# Boeing Alert Service Bulletin 747-53A2785: Revision 1

- Rights: © The Boeing Company. Filed by the FAA in regulations.gov docket FAA-2009-0794; AD 2012-22-03 incorporates this document by reference. Not covered by OpenAirDocs’ CC0 dedication.
- Document: [Boeing Alert Service Bulletin 747-53A2785](https://openairdocs.org/service-documents/boeing/747-53a2785.md)
- Title as filed: U.S. DOT/FAA - Boeing - SB-747-53A2785-01
- Pages: 63
- PDF: https://openairdocs.org/files/sha256/c9/b4/c9b46b7ab966d686b655384827d9cc7a035dfe7884a3562cd19f293514329394
- Page: https://openairdocs.org/service-documents/boeing/747-53a2785/file/c9b46b7ab966

## Text

Some pages are OCR from a scan. OCR can misread letters and numbers. Each page's text from the PDF; open the PDF at a page with #page=N.

### Page 1

Commercial 
Airplanes
747
Service Bulletin
ALERT
Number: 747-53A2785
Original Issue: February 12, 2009
Revision 1: July 15, 2010
ATA System: 5310
SUBJECT: FUSELAGE - Nose Section: Station 90 to Station 520 - Main Entry Door 1 Upper Main
Sill From STA 440 to STA 480 - Inspection and Repair
Export of this technology is controlled under the United States Export Administration Regulations (EAR) (15
CFR 730-774). An export license may be required before it is used for development, production or use by foreign
persons from specific countries. The controller of this data has the individual responsibility to abide by all export
laws.
9E991ECCN:
BOEING PROPRIETARY, CONFIDENTIAL, AND/OR TRADE SECRET
Copyright © 2009 The Boeing Company
Unpublished Work - All Rights Reserved
Boeing claims copyright in each page of this document only to the extent that the page contains copyrightable
subject matter. Boeing also claims copyright in this document as a compilation and/or collective work.
This document includes proprietary information owned by The Boeing Company and/or one or more third parties.
Treatment of the document and the information it contains is governed by contract with Boeing. For more
information, contact The Boeing Company, P.O. Box 3707, Seattle, Washington 98124.
Boeing, the Boeing signature, the Boeing symbol, 707, 717, 727, 737, 747, 757, 767, 777, 787, Dreamliner,
BBJ, DC-8, DC-9, DC-10, KC-10, KDC-10, MD-10, MD-11, MD-80, MD-88, MD-90, P-8A, Poseidon and the
Boeing livery are all trademarks owned by The Boeing Company; and no trademark license is granted in
connection with this document unless provided in writing by Boeing.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
1 of 63
6.0

### Page 2

BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
2 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT
BLANK PAGE

### Page 3

Table of Contents
Revision Transmittal Sheet ............................................ 5
Summary ...................................................... 7
1. PLANNING INFORMATION ........................................ 1 1
A. Effectivity ............................................... 1 1
1. Airplanes ............................................ 1 1
2. Spares Affected ........................................ 2 2
B. Concurrent Requirements ...................................... 2 2
C. Reason ................................................ 2 2
D. Description .............................................. 2 3
E. Compliance .............................................. 2 4
F. Approval ............................................... 2 8
G. Manpower .............................................. 2 9
H. Weight and Balance Changes .................................... 2 9
I. Electrical Load Data ......................................... 3 0
J. References .............................................. 3 0
1. Existing Data .......................................... 3 0
2. Data supplied with this Service Bulletin ............................ 3 0
3. Installation Drawings Used in the Preparation of this Service Bulletin ............ 3 1
K. Publications Affected ........................................ 3 1
L. Interchangeability and Intermixability of Parts ........................... 3 1
2. MATERIAL INFORMATION ........................................ 3 3
A. Material - Price and Availability ................................... 3 3
B. Industry Support Information .................................... 3 4
C. Parts Necessary For Each Airplane ................................. 3 4
1. Kits/Parts ............................................ 3 4
2. Parts and Materials Supplied by the Operator ........................ 4 3
3. Parts Modified and Reidentified ................................ 4 3
4. Parts Removed and Not Replaced .............................. 4 3
D. Parts Necessary to Change Spares ................................. 4 3
E. Special Tooling - Price and Availability ............................... 4 3
F. Special Tooling Necessary to do this Service Bulletin ....................... 4 3
3. ACCOMPLISHMENT INSTRUCTIONS .................................. 4 5
A. GENERAL INFORMATION ..................................... 4 5
B. WORK INSTRUCTIONS ....................................... 4 6
FIGURE 1: LEFT MAIN ENTRY DOOR 1 MAIN UPPER SILL INSPECTION .............. 5 2
FIGURE 2: RIGHT MAIN ENTRY DOOR 1 MAIN UPPER SILL INSPECTION ............. 5 6
FIGURE 3: REPAIRED LEFT MAIN ENTRY DOOR UPPER SILL AFTER-REPAIR INSPECTION . . 60
FIGURE 4: REPAIRED RIGHT MAIN ENTRY DOOR UPPER SILL AFTER-REPAIR INSPECTION . . 62
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
3 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 4

BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
4 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT
BLANK PAGE

### Page 5

Commercial 
Airplanes
747
Service Bulletin
ALERT
Revision Transmittal SheetNumber: 747-53A2785Original Issue: February 12, 2009
Revision 1: July 15, 2010
ATA System: 5310
SUBJECT: FUSELAGE - Nose Section: Station 90 to Station 520 - Main Entry Door 1 Upper Main
Sill From STA 440 to STA 480 - Inspection and Repair
This revision includes all pages of the service bulletin.
COMPLIANCE INFORMATION RELATED TO THIS REVISION
No more work is necessary on airplanes inspected or repaired in accordance with the original issue of this
service bulletin. Continue to do repeated inspections or after-repair inspections at the times given in this service
bulletin.
No airplanes were added to the service bulletin effectivity. However, 747-400 airplanes that have been modified
by Boeing to the Large Cargo Freighter (LCF) configuration have been moved from Group 3 to new Group 5.
All other 747-400 and 747-400D airplanes have been moved from Group 3 to new Group 6. All 747-400F
airplanes have been moved from Group 4 to new Group 7.
Federal Aviation Administration (FAA) Notice of Proposed Rule Making 2009-NM-035-AD is related to this service
bulletin.
REASON FOR REVISION
This Alert revision is sent to include reduced inspection thresholds and repeat inspection intervals for airplanes
modified by Boeing to the Large Cargo Freighter (LCF) configuration. LCF airplanes have been removed from
Group 3 and included in new Group 5.
In addition, 747-400, 747-400D, and 747-400F airplanes were moved from Groups 3 and 4 and placed in new
Groups 6 and 7. This change was made to make it more clear that the actions in Paragraph 3.B., Part 2 and
Part 3 related to existing Structural Repair Manual (SRM) outer chord repairs are not applicable to 747-400
airplanes.
Optional repair kits 141U0062-( ) have been created to provide kits of parts that are equivalent to the repairs
previously described on repair drawing 691U0145. Drawing 141U0062 Sheets 1 through 4 and Sheet PSDL are
sent with this revision. The contents of the 141U0062-( ) repair kits are listed in Paragraph 2.C.1., Parts Necessary
For Each Airplane, but operators should refer to Drawing 141U0062, Sheet 1 or Sheet PSDL for kit applicability.
References to FAA NPRM 2009-NM-035-AD have also been added.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
5 of 63

### Page 6

The data given in Information Notice 747-53A2785 IN 01 and IN 02 is included in this revision. IN 01 was sent
to make it clear that it was only necessary to remove existing outer chord repairs before doing the inspection in
this service bulletin. IN 02 was sent to clarify that the escape rope and retainer assembly, which is to be removed
for access, is not installed on all airplanes.
Vertical lines are put on the left edge of each page, except in Paragraph 1.A., Effectivity, to show the location
of important changes.
Pages with no vertical lines have no important changes.
REVISION HISTORY
February 12, 2009Original Issue:
July 15, 2010Revision 1:
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
6 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 7

Commercial 
Airplanes
747
Service Bulletin
ALERT
SummaryNumber: 747-53A2785Original Issue: February 12, 2009
Revision 1: July 15, 2010
ATA System: 5310
SUBJECT: FUSELAGE - Nose Section: Station 90 to Station 520 - Main Entry Door 1 Upper Main
Sill From STA 440 to STA 480 - Inspection and Repair
THIS BULLETIN IS SENT TO THE OPERATORS OF RECORD OF THE AIRPLANES SHOWN IN PARAGRAPH
1.A., EFFECTIVITY. IF AN AIRPLANE HAS BEEN LEASED OR SOLD, SEND THIS SERVICE BULLETIN TO
THE NEW OPERATOR. IF APPLICABLE SPARES HAVE BEEN SOLD, SEND THIS SERVICE BULLETIN TO
THE NEW OWNER.
CONCURRENT REQUIREMENTS
None.
BACKGROUND
This service bulletin gives instructions for the inspection for and repair of cracks in the Main Entry Door 1 upper
main sill outer chord, web, and frame attach angles or clips. Fatigue cracks in the sill can become large and
result in loss of structural integrity, which could result in cracks in adjacent parts.
Multiple operators have reported cracks up to 8 inches long in the Main Entry Door 1 upper main sill outer chord,
along the radius, on multiple airplanes. The upper main sill is replaced as part of the Zone 3 modification in
Boeing Service Bulletin 747-53-2272, "Fuselage - Nose Section 41 Body Frame Structure Replacement and
Reinforcement". The upper main sill installed as part of Service Bulletin 747-53-2272 and in subsequent production
airplanes has a thicker outer chord.
One operator has reported a 4.35 inch long crack in the new, thicker upper main sill outer chord, along the
radius, at STA 460 on a 747-400 airplane with 11,539 flight-cycles. A 0.5 inch long crack was also found in the
STA 460 upper sill to frame attach angle on this airplane. These cracks have been attributed to fatigue.
Accomplishment of the inspections shown in this service bulletin will make sure that fatigue cracks in the Main
Entry Door 1 main upper sill outer chord, web, and frame attach angles or clips are found and repaired before
they can become large and result in cracks in adjacent parts.
Boeing Service Related Problem (SRP) 747-SRP-53-0325 is related to this service bulletin.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
7 of 63

### Page 8

ACTION (PRR 85672-R)
Get access to the Main Entry Door 1 upper main sill. Do a detailed inspection of the upper main sill outer chord,
web, and frame attach angles or clips from STA 440 to STA 480 for cracks. If cracks are found, repair before
further flight. Replace the cracked parts, repair in accordance with this service bulletin, or ask Boeing for repair
data. If no cracks are found, put the airplane back in a serviceable condition. Do the inspections in this service
bulletin again at the time given in Paragraph 1.E., Compliance.
EFFECTIVITY
All 747-100, 747-100B, 747-100B SUD, 747-200B, 747-200C, 747-200F, 747-300, 747-400, 747-400D, 747-400F,
747SP, and 747SR airplanes. Refer to Paragraph 1.A.1., Airplanes for the list of affected airplanes.
COMPLIANCE
Refer to Paragraph 1.E., Compliance.
Federal Aviation Administration (FAA) Notice of Proposed Rule Making NPRM 2009-NM-035-AD is related to
this service bulletin.
FAA Airworthiness Directives AD 90-06-06, AD 2005-08-01, AD 2009-18-07  and AD 2010-01-01  are related
to the subject of this service bulletin.
INDUSTRY SUPPORT INFORMATION
Boeing warranty remedies are not available for the inspection or repair procedures given in this service bulletin.
MANPOWER
Elapsed HoursTotal Task HoursAirplanes
8.517.0Group 1, Group
3, Group 5 and
Group 6
8.08.0Group 2, Group
4, and Group 7
MATERIAL INFORMATION
Operator Supplied Parts/Materials.
Refer to Paragraph 2.A., Material - Price and Availability
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
8 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 9 (OCR)

BOEING SERVICE BULLETIN 747-53A2785
ALERT  ALERT
UPPER DECK
FLOOR BEAMS
00000000000  UPPER  MAIN SILL
- S-13
• S-14
S-15
-S-16
35-17
S-18
• S-19
- S-20
• S-22
S-23
• S-24
DO A DETAILED INSPECTION /
OF THE UPPER MAIN SILL  • S-26
OUTER CHORD, WEB, AND
FRAME ATTACHMENT CLIPS  AND ANGLES FOR CRACKS.  ASSEMBLY  REVEAL  → S-27
• S-28
- S-30
STA
400
LOWER
STA  MAIN SILL
420
STA
LOWER AUXILLIARY SILL  440
STA
460
STA
480
STA  STA  500  1664192
520
MAIN ENTRY DOOR NO. 1
Original Issue: February 12, 2009
Revision 1: July 15, 2010  747-53A2785
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.  9 of 63

### Page 10

BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
10 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT
BLANK PAGE

### Page 11

Commercial 
Airplanes
747
Service Bulletin
ALERT
Number: 747-53A2785
Original Issue: February 12, 2009
Revision 1: July 15, 2010
ATA System: 5310
SUBJECT: FUSELAGE - Nose Section: Station 90 to Station 520 - Main Entry Door 1 Upper Main
Sill From STA 440 to STA 480 - Inspection and Repair
THIS BULLETIN IS SENT TO THE OPERATORS OF RECORD OF THE AIRPLANES SHOWN IN PARAGRAPH
1.A., EFFECTIVITY. IF AN AIRPLANE HAS BEEN LEASED OR SOLD, SEND THIS SERVICE BULLETIN TO
THE NEW OPERATOR. IF APPLICABLE SPARES HAVE BEEN SOLD, SEND THIS SERVICE BULLETIN TO
THE NEW OWNER.
1.    PLANNING INFORMATION
A. Effectivity
1. Airplanes
Refer to Service Bulletin Index Document D6-30300 Part 3 for Airplane Variable Number, Line
Number, and Serial Number data.
This service bulletin is for the airplanes shown below. Refer to PRR 85672-R for data about this
change.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
11 of 63

### Page 12

DESCRIPTIONCONFIGURATIONGROUP
Airplanes line number 1 - 686, 688, and 690 - 695, except 747-200F
airplanes, which are affected by Boeing Service Bulletin 747-53-2272.
-1
Not converted by Boeing to the Special Freighter or Boeing Converted
Freighter configuration, with the Zone 3 modification in Boeing Service
Bulletin 747-53-2272 previously accomplished. Zone 3 includes
replacement of the Main Entry Door 1 main upper sill.
1
Converted by Boeing to the Special Freighter or Boeing Converted
Freighter configuration, with the Zone 3 modification in Boeing Service
Bulletin 747-53-2272 previously accomplished. Zone 3 includes
replacement of the Main Entry Door 1 main upper sill.
2
Not converted by Boeing to the Special Freighter or Boeing Converted
Freighter configuration, with the Zone 3 modification in Boeing Service
Bulletin 747-53-2272 not previously accomplished.
3
Converted by Boeing to the Special Freighter or Boeing Converted
Freighter configuration, with the Zone 3 modification in Boeing Service
Bulletin 747-53-2272 not previously accomplished.
4
747-200F airplanes through line number 686, which are affected by
Boeing Service Bulletin 747-53-2272.
-2
With the Zone 3 modification in Boeing Service Bulletin 747-53-2272
previously accomplished. Zone 3 includes replacement of the Main
Entry Door 1 main upper sill.
1
With the Zone 3 modification in Boeing Service Bulletin 747-53-2272
not previously accomplished.
2
747 Classic airplanes line number 696 - 810, except 747-200F
airplanes.
-3
Not converted by Boeing to the Special Freighter configuration.1
Converted by Boeing to the Special Freighter configuration.2
747-200F airplanes line number 687 and on.-4
747-400 airplanes modified by Boeing to the Large Cargo Freighter
(LCF) configuration.
-5
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
12 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 13

DESCRIPTIONCONFIGURATIONGROUP
All 747-400 and 747-400D airplanes, except Group 5 airplanes.-6
Not converted by Boeing to the Boeing Converted Freighter (BCF)
configuration.
1
Converted by Boeing to the BCF configuration.2
All 747-400F airplanes.-7
Airplane Models:
747-100, 747-100B, 747-100B SUD, 747-200B, 747-200C, 747-200F, 747-300, 747-400,
747-400D, 747-400F, 747SP, 747SR
GroupVariable Number
1RA001 - RA034
1RA101 - RA115
1RA161 - RA164
1RA201 - RA203
1RA216 - RA217
1RA245 - RA246
1RA251 - RA266
1RA301 - RA318
1RA351 - RA360
1RA369 - RA373
1RA401 - RA418
1RA501 - RA502
1RA521 - RA528
1RA532 - RA548
1RA551 - RA552
1RA559 - RA561
1RA581 - RA582
1RA585
1RA601 - RA602
1RA631 - RA635
1RA651 - RA652
1RA671 - RA677
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
13 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 14

GroupVariable Number
1RA701 - RA702
1RA721 - RA731
1RA741 - RA745
1RA749 - RA750
1RA761 - RA762
1RA781 - RA784
1RA901 - RA916
1RB001 - RB016
1RB041 - RB044
1RB071 - RB075
1RB101 - RB102
1RB411 - RB412
3RB413
3RB421
1RB601 - RB607
1RB681 - RB697
1RB711
1RB721 - RB723
1RB741 - RB748
1RD001 - RD004
1RD021 - RD022
1RD041 - RD059
1RD071 - RD072
1RD081 - RD083
1RD091 - RD092
1RD101 - RD104
1RD121 - RD127
1RD131 - RD144
1RD166 - RD167
1RD171 - RD172
1RD181 - RD183
1RD201 - RD204
1RD221 - RD227
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
14 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 15

GroupVariable Number
1RD231 - RD234
3RD235
1RD241 - RD243
1RD251 - RD262
1RD271 - RD272
1RD291 - RD292
1RD301 - RD302
1RD311
1RD351 - RD358
1RD361 - RD366
1RD381 - RD383
1RD411 - RD414
1RD421 - RD426
1RD431 - RD435
1RD441 - RD442
1RD451 - RD456
1RD461
1RD471 - RD475
1RD513 - RD519
1RD531 - RD533
1RD551
1RD561
1RD571
1RD581 - RD583
1RD591 - RD593
1RD601 - RD607
1RD621 - RD623
1RD641 - RD649
1RD651 - RD659
1RD661
1RD671
1RD681 - RD682
1RD691 - RD692
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
15 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 16

GroupVariable Number
1RD701 - RD702
1RD721 - RD722
1RD741 - RD742
1RD751 - RD755
1RD761
1RD771 - RD775
1RD781 - RD783
1RD791
3RD792
1RE001
6RF001 - RF006
1RG001 - RG009
1RG091
1RG095
1RG101 - RG104
1RG121 - RG126
1RG141 - RG142
1RG161 - RG164
1RG171 - RG174
1RG191 - RG193
1RG211 - RG213
1RG221 - RG222
1RH101 - RH102
1RH111 - RH112
1RH121 - RH122
1RJ131 - RJ133
1RJ151 - RJ152
1RJ301 - RJ303
1RJ321
3RJ322
1RJ331 - RJ333
7RL401 - RL403
7RL411 - RL436
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
16 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 17

GroupVariable Number
7RL451 - RL456
7RL461 - RL462
7RL471 - RL481
7RL491 - RL492
7RL501 - RL502
7RL511 - RL516
7RL521 - RL522
7RL531 - RL534
7RL551
7RL561 - RL568
7RL571 - RL572
7RL576 - RL577
7RL579
7RL581 - RL586
7RL651 - RL655
7RL671 - RL675
7RL681 - RL684
7RL751 - RL752
6RM001 - RM007
6RM010 - RM013
6RM021 - RM024
6RM026 - RM030
6RM036 - RM045
6RM051 - RM053
6RM071
6RM081 - RM084
6RM091
6RM096 - RM097
6RM116 - RM117
6RM126 - RM132
6RM136 - RM147
6RM156 - RM158
6RM166 - RM177
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
17 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 18

GroupVariable Number
6RM191 - RM192
6RM231 - RM233
6RM241 - RM246
6RM261 - RM264
6RM316 - RM318
6RM331 - RM333
6RM341
6RM351 - RM355
6RM366 - RM367
6RM401 - RM403
6RM426
6RM431
6RM441 - RM443
6RM445
6RM801 - RM803
6RM811 - RM813
7RM851 - RM859
7RM861 - RM863
7RM871 - RM899
7RM901 - RM906
7RM911
2RR001 - RR005
2RR021 - RR023
4RR024 - RR025
2RR031
2RR201 - RR205
4RR206
2RR221 - RR226
2RR261 - RR267
2RR301 - RR306
4RR307 - RR310
2RR331 - RR332
2RR336
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
18 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 19

GroupVariable Number
2RR341 - RR345
2RR361 - RR362
2RR421 - RR422
2RR431 - RR432
4RR441 - RR442
4RR451
2RR501 - RR504
2RR521
4RR522
4RR526
2RR531
2RR551 - RR553
4RR554 - RR556
2RR561
4RR566
7RR701
7RR721 - RR724
7RR746 - RR748
7RR851 - RR856
7RR861 - RR862
7RR951 - RR952
1RS001 - RS002
1RS201
1RS211 - RS212
1RS221 - RS222
1RS231 - RS241
1RS251 - RS259
3RS263
1RS265 - RS268
1RS271 - RS276
1RS291 - RS292
1RS301 - RS305
3RS306
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
19 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 20

GroupVariable Number
1RS311 - RS320
3RS331 - RS333
1RS341 - RS342
1RS699
1RS701 - RS703
1RS711 - RS713
1RS721 - RS722
3RS731 - RS732
1RS741 - RS743
1RS751 - RS752
1RS761
3RS762
1RS771
3RS781 - RS782
3RS786
6RT001 - RT014
6RT021 - RT022
6RT031 - RT035
6RT041 - RT047
6RT061
6RT071 - RT075
6RT101 - RT103
6RT121
6RT131 - RT137
6RT151 - RT152
6RT161 - RT168
6RT401 - RT412
6RT431 - RT447
6RT451 - RT469
6RT471 - RT499
6RT501 - RT535
6RT551 - RT568
6RT571 - RT591
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
20 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 21

GroupVariable Number
6RT601 - RT630
5RT631 - RT632
6RT633 - RT657
6RT671 - RT673
6RT681 - RT682
6RT691 - RT699
6RT701 - RT704
6RT711 - RT717
6RT741 - RT742
5RT743
6RT744 - RT757
6RT776 - RT777
6RT781 - RT784
6RT801 - RT803
6RT811 - RT814
6RT831 - RT837
6RT861 - RT864
5RT876
6RT877 - RT880
6RT931 - RT932
6RT945 - RT949
6RT951 - RT955
6RT966 - RT967
6RU001 - RU006
6RU016 - RU017
6RU031 - RU032
6RU051 - RU052
6RU059 - RU062
6RU081 - RU083
6RU101 - RU102
6RU121 - RU132
6RU801 - RU809
6RU831 - RU841
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
21 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 22

2. Spares Affected
None.
B. Concurrent Requirements
None.
C. Reason
This service bulletin gives instructions for the inspection for and repair of cracks in the Main Entry Door
1 upper main sill outer chord, web, and frame attach angles or clips. Fatigue cracks in the sill can
become large and result in loss of structural integrity, which could result in cracks in adjacent parts.
Multiple operators have reported cracks up to 8 inches long in the Main Entry Door 1 upper main sill
outer chord, along the radius, on multiple airplanes. The upper main sill is replaced as part of the Zone
3 modification in Boeing Service Bulletin 747-53-2272, "Fuselage - Nose Section 41 Body Frame
Structure Replacement and Reinforcement". The upper main sill installed as part of Service Bulletin
747-53-2272 and in subsequent production airplanes has a thicker outer chord.
One operator has reported a 4.35 inch long crack in the new, thicker upper main sill outer chord, along
the radius, at STA 460 on a 747-400 airplane with 11,539 flight-cycles. A 0.5 inch long crack was also
found in the STA 460 upper sill to frame attach angle on this airplane. These cracks have been attributed
to fatigue.
Accomplishment of the inspections given in this service bulletin will make sure that fatigue cracks in
the Main Entry Door 1 main upper sill outer chord, web, and frame attach angles or clips are found and
repaired before they can become large and result in cracks in adjacent parts.
Alert Revision 1 is sent to include reduced inspection thresholds and repeat inspection intervals for
airplanes modified by Boeing to the Large Cargo Freighter (LCF) configuration. LCF airplanes have
been removed from Group 3 and included in new Group 5. In addition, 747-400, 747-400D, and 747-400F
airplanes were moved from Groups 3 and 4 and placed in new Groups 6 and 7. This change was made
to make it more clear that the actions in Paragraph 3.B., Part 2 and Part 3 related to existing Structural
Repair Manual (SRM) outer chord repairs are not applicable to 747-400 airplanes. Optional repair kits
141U0062-( ) have been created to provide kits of parts that are equivalent to the repairs previously
described on repair drawing 691U0145. Drawing 141U0062 Sheets 1 through 4 and Sheet PSDL are
sent with this revision. The contents of the 141U0062-( ) repair kits are listed in Paragraph 2.C.1., Parts
Necessary For Each Airplane, but operators should refer to Drawing 141U0062, Sheet 1 or Sheet
PSDL for kit applicability. References to FAA NPRM 2009-NM-035-AD have also been added. The
data given in Information Notice 747-53A2785 IN 01 and IN 02 is included in Revision 1. IN 01 was
sent to make it clear that it was only necessary to remove existing outer chord repairs before doing the
inspection in this service bulletin. IN 02 was sent to clarify that the escape rope and retainer assembly,
which is to be removed for access, is not installed on all airplanes.
Boeing Service Related Problem (SRP) 747-SRP-53-0325 is related to this service bulletin.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
22 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 23

D. Description
Get access to the Main Entry Door 1 upper main sill. Do a detailed inspection of the upper main sill
outer chord, web, and frame attach angles or clips from STA 440 to STA 480 for cracks. If cracks are
found, repair before further flight. Replace the cracked parts, repair in accordance with this service
bulletin, or ask Boeing for repair data. If no cracks are found, put the airplane back in a serviceable
condition. Do the inspections in this service bulletin again at the time given in Paragraph 1.E.,
Compliance.
No more work is necessary on airplanes inspected or repaired in accordance with the original issue of
this service bulletin. Continue to do repeated inspections or after-repair inspections at the times given
in this service bulletin.
The work in this service bulletin is done in the maintenance zone(s) given below.
Group 1:
Affected Maintenance Zones
ZoneModel
211, 212747-100, 747-100B, 747-100B
SUD, 747-200B, 747-200C,
747-300, 747SP, 747SR
Group 2, 4:
Affected Maintenance Zones
ZoneModel
211747-200F
Group 3:
Affected Maintenance Zones
ZoneModel
211, 212747-200B, 747-200C, 747-300
Group 5:
Affected Maintenance Zones
ZoneModel
211, 212747-400
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
23 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 24

Group 6:
Affected Maintenance Zones
ZoneModel
211, 212747-400, 747-400D
Group 7:
Affected Maintenance Zones
ZoneModel
211747-400F
E. Compliance
Federal Aviation Administration (FAA) Notice of Proposed Rule Making NPRM 2009-NM-035-AD is
related to this service bulletin.
Federal Aviation Administration (FAA) Airworthiness Directives AD 90-06-06, AD 2005-08-01, AD
2009-18-07  and AD 2010-01-01  are related to the subject of this service bulletin.
Boeing recommends that the inspection and repair given in this service bulletin be done in accordance
with the table that follows:
Table 1: Main Entry Door 1 Upper Sill Inspection
Repeat Interval (Not
to Exceed)
Compliance Time (Whichev-
er Occurs Last)
ActionCondition
-Within 1,500
flight-cycles
after original
issue date of
this service
bulletin.
Within 9,000
total flight cy-
cles.
Do a general visual inspection
for existing SRM outer chord
repair and a detailed inspec-
tion of the Main Entry Door 1
upper main sill outer chord,
web, and frame attachment
angles (or clips) for crack(s)
in accordance with Paragraph
3.B., PART 2. (a) (b)
Group 1, Configura-
tion 3 and Configura-
tion 4 and Group 2,
Configuration 2 air-
planes
-Within 1,500
flight-cycles
after the origi-
nal issue date
of this service
bulletin.
Within 12,000
flight-cycles
after the Zone
3 modification
in accordance
with Service
Bulletin 747-
53-2272 was
installed.
Do a general visual inspection
for existing SRM outer chord
repair and a detailed inspec-
tion of the Main Entry Door 1
upper main sill outer chord,
web, and frame attachment
angles (or clips) for crack(s)
in accordance with Paragraph
3.B., PART 2. (a) (b)
Group 1, Configura-
tion 1 and Configura-
tion 2 and Group 2,
Configuration 1 air-
planes
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
24 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 25

Table 1: Main Entry Door 1 Upper Sill Inspection
Repeat Interval (Not
to Exceed)
Compliance Time (Whichev-
er Occurs Last)
ActionCondition
-Within 1,500
flight-cycles
after the origi-
nal issue date
of this service
bulletin.
Within 12,000
total flight-cy-
cles.
Do a general visual inspection
for existing SRM outer chord
repair and a detailed inspec-
tion of the Main Entry Door 1
upper main sill outer chord,
web, and frame attachment
angles (or clips) for crack(s)
in accordance with Paragraph
3.B., PART 2. (a) (b)
Group 3 and Group 4
airplanes.
-Within 1,500
flight-cycles
after the Revi-
sion 1 date of
this service
bulletin.
Within 10,000
total flight-cy-
cles.
Do a detailed inspection of the
Main Entry Door 1 upper main
sill outer chord, web, and
frame attachment angles (or
clips) for crack(s) in accor-
dance with Paragraph 3.B.,
PART 2. (a)
Group 5 airplanes.
-Within 1,500
flight-cycles
after the origi-
nal issue date
of this service
bulletin.
Within 12,000
total flight-cy-
cles.
Do a detailed inspection of the
Main Entry Door 1 upper main
sill outer chord, web, and
frame attachment angles (or
clips) for crack(s) in accor-
dance with Paragraph 3.B.,
PART 2. (a)
Group 6 and Group 7
airplanes.
6,000 flight-cyclesWithin 1,500
flight-cycles
after the origi-
nal issue date
of this service
bulletin.
Within 6,000
flight-cycles
from the last
inspection.
Do a detailed inspection of the
Main Entry Door 1 upper main
sill outer chord, web, and
frame attachment angles (or
clips) for crack(s) in accor-
dance with Paragraph 3.B.,
PART 2. (a).
Group 1 - 4:  No
crack, and no existing
SRM outer chord re-
pair found. (b)
-Before further flight. (c).As an alternative, install the
Drawing 691U0145 or
141U0062 outer chord repair
in accordance with Paragraph
3.B. PART 3.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
25 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 26

Table 1: Main Entry Door 1 Upper Sill Inspection
Repeat Interval (Not
to Exceed)
Compliance Time (Whichev-
er Occurs Last)
ActionCondition
3,000 flight-cyclesWithin 1,500
flight-cycles
after the date
on Revision 1
of this service
bulletin.
Within 3,000
flight-cycles
from the last
inspection.
Do a detailed inspection of the
Main Entry Door 1 upper main
sill outer chord, web, and
frame attachment angles (or
clips) for crack(s) in accor-
dance with Paragraph 3.B.,
PART 2. (a).
Group 5: No crack
found.
Before further flight. (c).As an alternative, install the
Drawing 691U0145 or
141U0062 outer chord repair
in accordance with Paragraph
3.B. PART 3.
6,000 flight-cyclesWithin 1,500
flight-cycles
after the origi-
nal issue date
of this service
bulletin.
Within 6,000
flight-cycles
from the last
inspection.
Do a detailed inspection of the
Main Entry Door 1 upper main
sill outer chord, web, and
frame attachment angles (or
clips) for crack(s) in accor-
dance with Paragraph 3.B.,
PART 2. (a).
Group 6 and 7: No
crack found.
Before further flight. (c).As an alternative, install the
Drawing 691U0145 or
141U0062 outer chord repair
in accordance with Paragraph
3.B. PART 3.
-Before further flight. (c).Install the Drawing 691U0145
or 141U0062 outer chord re-
pair in accordance with Para-
graph 3.B. PART 3.
Outer chord crack(s)
found.
-Before further flight. (c).Remove the existing repair,
do a detailed inspection of the
upper main sill web and frame
attachment angles (or clips)
for crack(s), and install the
Drawing 691U0145 or
141U0062 outer chord repair
in accordance with Paragraph
3.B. PART 3.
Existing SRM outer
chord repair found.
(Group 1 - 4 only) (b)
-Before further flightReplace in accordance with
Paragraph 3.B. PART 3.
Cracked frame attach-
ment angles or clips
found
-Before further flightDo repair. Contact Boeing for
repair instructions.
Sill web crack(s)
found.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
26 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 27

Table 1: Main Entry Door 1 Upper Sill Inspection
Repeat Interval (Not
to Exceed)
Compliance Time (Whichev-
er Occurs Last)
ActionCondition
--Go to Table 2 or Table 3.Drawing 691U0145 or
141U0062 outer
chord repair installed
in accordance with
Paragraph 3.B.,
PART 3.
6,000 flight-cyclesWithin 1,500
flight-cycles
after the origi-
nal issue date
of this service
bulletin.
Within 6,000
flight-cycles
from the last
inspection.
Repeat detailed inspection of
the Main Entry Door 1 upper
main sill outer chord, web,
and frame attachment angles
(or clips) for crack(s) in accor-
dance with Paragraph 3.B.,
PART 2. (a).
Group 1 - 4, 6 and 7:
Sill web or frame at-
tachment angles (or
clips) repaired or re-
placed, and the
Drawing 691U0145 or
141U0062 outer
chord repair not in-
stalled.
3,000 flight-cyclesWithin 1,500
flight-cycles
after the Revi-
sion 1 date of
this service
bulletin.
Within 3,000
flight-cycles
from the last
inspection.
Repeat detailed inspection of
the Main Entry Door 1 upper
main sill outer chord, web,
and frame attachment angles
(or clips) for crack(s) in accor-
dance with Paragraph 3.B.,
PART 2. (a).
Group 5: Sill web or
frame attachment an-
gles (or clips) repaired
or replaced, and the
Drawing 691U0145 or
141U0062 outer
chord repair not in-
stalled.
(a) The detailed inspection is not required if the Main Entry Door 1 cutout is being inspected in accordance
with FAA AD 2009-18-07  or FAA AD 2010-01-01 . For airplanes with 22,000 total flight cycles or more,
FAA AD 2009-18-07  requires the inspection of this area every 3,000 flight-cycles in accordance with
Service Bulletin 747-53A2349, "Fuselage - Inspections Based on Fatigue Test Results", and FAA AD
2010-01-01  requires the inspections in accordance with Service Bulletin 747-53A2500, "Fuselage - Main
Frame - Inspections Based on Fatigue Test Results".
(b) Existing SRM repair in accordance with 747-100/200/300 SRM 53-10-04, Figure 93 or 747-SP SRM 53-
19-02, Figure 52.
(c) Table 2 or Table 3 have the post-modification/repair inspection compliance times.
Group 1-4, 6-7:
Table 2: Inspection of Main Entry Door 1 Upper Sills with the Outer Chord Repair Installed
Repeat Interval
(Not to Exceed)
Compliance Time (Whichever
Occurs Later)
ActionCondition
3,000 flight-cycles.Within 1,500
flight-cycles af-
ter the original
issue date of
this service bul-
letin.
Within 15,000
flight cycles af-
ter the repair.
Do the after-repair inspec-
tions in accordance with
Paragraph 3.B., PART 5.
Airplanes with the Drawing
691U0145 or 141U0062
outer chord repair installed
in accordance with Para-
graph 3.B. PART 3.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
27 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 28

Group 1-4, 6-7:
Table 2: Inspection of Main Entry Door 1 Upper Sills with the Outer Chord Repair Installed
Repeat Interval
(Not to Exceed)
Compliance Time (Whichever
Occurs Later)
ActionCondition
-Before further flightDo repair. Contact Boeing
for repair instructions.
Crack(s) found
Group 5:
Table 3: Inspection of Main Entry Door 1 Upper Sills with the Outer Chord Repair Installed
Repeat Interval
(Not to Exceed)
Compliance Time (Whichever
Occurs Later)
ActionCondition
1,500 flight-cycles.Within 1,500
flight-cycles af-
ter the Revision
1 date of this
service bulletin.
Within 6,000
flight cycles af-
ter the repair.
Do the after-repair inspec-
tions in accordance with
Paragraph 3.B., PART 5.
Airplanes with the Drawing
691U0145 or 141U0062
outer chord repair installed
in accordance with Para-
graph 3.B. PART 3.
-Before further flightDo repair. Contact Boeing
for repair instructions.
Crack(s) found
F. Approval
This service bulletin was examined by the Federal Aviation Administration (FAA). The changes specified
in this service bulletin comply with the applicable regulations and are FAA approved, as well as European
Aviation Safety Agency (EASA)/Joint Aviation Authorities (JAA) approved for all EASA/JAA approved
airplanes listed in the service bulletin effectivity. This service bulletin and its approval were based on
the airplane in its original Boeing delivery configuration or as modified by other approved Boeing
changes.
If an airplane has a non-Boeing modification or repair that affects a component or system also affected
by this service bulletin, the operator is responsible for obtaining appropriate regulatory agency approval
before incorporating this service bulletin.
The manager of the FAA Seattle Aircraft Certification Office (ACO) approves the accomplishment of
the main entry door 1 upper main sill outer chord inspection and repair procedures of this service
bulletin at the compliance times given in paragraph 1.E., Compliance of this service bulletin as an
AMOC to the corresponding main entry door 1 upper main sill outer chord inspection and repair
requirements of paragraphs (f) and (h) of AD 2005-08-01. When this service bulletin specifies contacting
Boeing for repair instructions, the repair instructions must be approved by the FAA in accordance with
paragraph (t) of AD 2005-08-01. All provisions of AD 2005-08-01 that are not specifically in this paragraph
remain fully applicable and must be complied with, including inspection of structure adjacent to the
main entry door upper main sill outer chord.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
28 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 29

The manager of the FAA Seattle Aircraft ACO also approves the accomplishment of the main entry
door 1 upper main sill outer chord repair procedures of this service bulletin as an AMOC to the
corresponding main entry door 1 upper main sill outer chord modification requirement defined in SB
747-53-2272, Revision 12 required by paragraph A. of AD 90-06-06. When this service bulletin specifies
contacting Boeing for repair instructions, the repair instructions must be approved by the FAA in
accordance with paragraph C. of AD 90-06-06. All provisions of AD 90-06-06 that are not specifically
in this paragraph remain fully applicable and must be complied with, including inspection of structure
adjacent to the main entry door upper main sill outer chord.
G. Manpower
The table below shows an estimate of the task hours necessary to do this inspection for each airplane.
This estimate is for direct labor only, done by an experienced crew. Adjust the estimate with operator
task hour data if necessary. The estimate does not include lost time. These are some examples of lost
time:
 Time to adjust to the workplace
 Time to schedule the work
 Time to inspect the work
 Time to cure the materials
 Time to make the parts
 Time to find the tools.
Group 1, 3, 5-6:
Elapsed HoursTask HoursNumber of Per-
sons
Task
2.755.52Open Access
3.06.02Inspect
2.755.52Close Access
4.258.5TOTAL FOR EACH SIDE
8.517.0TOTAL FOR EACH AIRPLANE
Group 2, 4, 7:
Elapsed HoursTask HoursNumber of Per-
sons
Task
2.52.51Open Access
3.03.01Inspect
2.52.51Close Access
8.08.0TOTAL FOR EACH AIRPLANE
NOTE: More time will be necessary for repairs or part replacement if cracks are found.
H. Weight and Balance Changes
None.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
29 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 30

I. Electrical Load Data
Not changed.
J. References
1. Existing Data
a. Service Related Problem (SRP) 747-SRP-53-0325
b. Standard Overhaul Practices Manual (SOPM) 20-41-02, 20-43-03
c. 747 Non-Destructive Testing (NDT) Manual Part 6, 51-00-00
d. 747-100/200/300 Aircraft Maintenance Manual (AMM) 25-21-03, 25-21-04, 25-22-04, 25-23-04,
25-59-01, 25-59-05, 25-61-03, 52-11-00, 52-11-01
e. 747-400 Aircraft Maintenance Manual (AMM) 25-21-03, 25-21-04, 25-22-01, 25-23-04,
25-59-01, 25-59-05, 25-61-03, 52-11-00, 52-11-01
f. 747-100/200/300 Structural Repair Manual (SRM) 53-10-04
g. 747-SP Structural Repair Manual (SRM) 53-19-02
h. Boeing Service Bulletin 747-53-2349, 747-53A2265, 747-53A2500, 747-53A2732, 747-53A2753
i. Boeing Parts Standards Document D-590
j. Boeing Drawing 012W6100
k. Federal Aviation Administration (FAA) Airworthiness Directive AD 90-06-06, AD 2005-08-01,
AD 2009-18-07 , AD 2010-01-01
l. Federal Aviation Administration (FAA) Notice of Proposed Rule Making NPRM
2009-NM-035-AD
m. Engineering Change Memo PRR 85672-R
2. Data supplied with this Service Bulletin
a. Drawings:
ADCNDCN/REVSheetTitleDrawing No
--1Kit - Door #1 Upper Sill Chord Repair141U0062
--2
--3
--4
--PSDL
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
30 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 31

ADCNDCN/REVSheetTitleDrawing No
--1Door #1 Upper Sill Chord Repair691U0145
--2
3. Installation Drawings Used in the Preparation of this Service Bulletin
TitleDrawing Number
Sill Installation - Upper Main, Fwd Entry Door65B08301
Sill Installation - Upper Main, Fwd Entry Door Retrofit Kit141U1029
These drawings were used to prepare this service bulletin. These drawings are not necessary to
make the specified changes, and are not supplied with this service bulletin. These drawings may
not be applicable to all airplane configurations or operators.
K. Publications Affected
1. Publications
None.
2. Damage Tolerance Based Structural Inspections
Boeing has evaluated the repairs and/or changes in this service bulletin for effects on Fatigue
Critical Structure (FCS) and for changes to Damage Tolerance Inspections (DTI) required in the
Maintenance Program. New DTI requirements for the structure affected are contained in Paragraph
1.E., Compliance of this service bulletin.
L. Interchangeability and Intermixability of Parts
Accomplishment of this service bulletin does not affect interchangeability or intermixability of parts.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
31 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 32

BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
32 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT
BLANK PAGE

### Page 33

2.    MATERIAL INFORMATION
A. Material - Price and Availability
The operator can supply the parts and materials shown in Paragraph 2.C., Parts Necessary for Each
Airplane, if needed. As an alternative, operators can purchase kits from Boeing Spares. The Boeing
price data shown below is given for planning purposes. Kit availability is shown in the Reorder Lead
Time (ROLT). ROLT is calculated from the date Boeing gets the purchase order.
Unit Price through
Feb 28, 2011
ROLT
(Weeks)
NameKit Number
$3,398.00(a)REPAIR KIT - LEFT SIDE141U0062-1
$3,398.00(a)REPAIR KIT - RIGHT SIDE141U0062-2
$3,899.00(a)REPAIR KIT - LEFT SIDE141U0062-3
$3,972.00(a)REPAIR KIT - RIGHT SIDE141U0062-4
$5,319.00(a)REPAIR KIT - LEFT SIDE141U0062-5
$175.00(a)VARIABLE FASTENER KIT141U0062-6
$169.00(a)VARIABLE FASTENER KIT141U0062-7
$169.00(a)VARIABLE FASTENER KIT141U0062-8
$132.00(a)VARIABLE FASTENER KIT141U0062-9
$132.00(a)VARIABLE FASTENER KIT141U0062-10
$134.00(a)VARIABLE FASTENER KIT141U0062-11
$134.00(a)VARIABLE FASTENER KIT141U0062-12
(a) Schedule data was not available for these kits at the time of release of this service bulletin.
Contact the Director of Spares for data about kit availability.
The kits are subject to the terms and conditions of the Boeing standard purchase order acknowledgment.
After the Unit Price date, new price and ROLT data is applicable. Prices are in United States dollars.
Terms: Net 30 days.
Reference this service bulletin and submit your purchase order by one of the methods that follow:
1. Order on-line via ATA Spec 2000 or Boeing Part Page
2. Fax to (206) 662-7145
3. Mail to:
Spares Customer Support - MC 36-65
Boeing Spares Department
P.O. Box 3707
Seattle, Washington 98124-2207 USA
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
33 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 34

B. Industry Support Information
Boeing warranty remedies are not available for the inspection or repair procedures given in this service
bulletin.
C. Parts Necessary For Each Airplane
1. Kits/Parts
NOTE: Refer to Drawing 141U0062 Sheet PSDL or Sheet 1, sent with Revision 1 of
this service bulletin, for kit applicability.
1.
2. The kits listed below are an alternative to manufacture of your own parts in
accordance with Drawing 691U0145 Sheet 1 or Sheet 2, which was sent with
the original issue of this service bulletin.
Kit 141U0062
NotesExisting Part
Number
NameQTYNew Part Number
-5-4-3-2-1
(c) (d)REPAIR KIT - BA-
SIC, LEFT SIDE
....-141U0062-1
(c) (d)REPAIR KIT - BA-
SIC, RIGHT SIDE
...-.141U0062-2
(c) (d)REPAIR KIT - BA-
SIC, LEFT SIDE
..-..141U0062-3
(c) (d)REPAIR KIT - BA-
SIC, RIGHT SIDE
.-...141U0062-4
(c) (d)REPAIR KIT - BA-
SIC, LEFT SIDE
-....141U0062-5
(a) (b)REPLACEMENT
CHORD
1.1..141U0063-1
(a) (b)REPLACEMENT
CHORD
.1...141U0063-2
(a) (b)REPLACEMENT
CHORD
...11141U0063-3
(a) (b)STEEL REPAIR
ANGLE
1.1.1141U0063-5
(a) (b)STEEL REPAIR
ANGLE
.1.1.141U0063-6
(a) (b)STEEL REPAIR
STRAP
1.1.1141U0063-7
(a) (b)STEEL REPAIR
STRAP
.1.1.141U0063-8
BOLT2....BACB30MY8K7X
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
34 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 35

Kit 141U0062
NotesExisting Part
Number
NameQTYNew Part Number
-5-4-3-2-1
BOLT1616161616BACB30NW6K10X
BOLT2....BACB30NW6K11Y
BOLT33333BACB30NW6K6X
BOLT2..22BACB30NW6K8Y
BOLT333..BACB30NW8K10X
BOLT111..BACB30NW8K8X
BOLT111..BACB30NW8K9X
BOLT2....BACB30NX6K11Y
BOLT51111BACB30NX6K3Y
BOLT111..BACB30NX6K4X
BOLT1922222224BACB30NX6K4Y
BOLT.11...BACB30NX6K5X
BOLT4331412BACB30NX6K5Y
BOLT1125..BACB30NX6K6X
BOLT.4.22BACB30NX6K6Y
BOLT1123..BACB30NX6K7Y
BOLT53322BACB30NX6K8Y
BOLT...11BACB30NX8K2
BOLT...99BACB30NX8K3
BOLT...22BACB30NX8K7
BOLT111..BACB30VT6K10
BOLT666..BACB30VT6K11
BOLT212121..BACB30VT6K5
BOLT111..BACB30VT6K9
BOLT333..BACB30VT8K11
BOLT333..BACB30VT8K5
BOLT333..BACB30VT8K8
BOLT121212..BACB30VT8K9
BOLT,202020..BACB30YP6K11
BOLT222..BACB30YP6K12
BOLT303030..BACB30YP6K5
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
35 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 36

Kit 141U0062
NotesExisting Part
Number
NameQTYNew Part Number
-5-4-3-2-1
BOLT333..BACB30YP6K6
BOLT111..BACB30YP6K7
BOLT222..BACB30YP6K8
BOLT222..BACB30YP8K10
BOLT555..BACB30YP8K11
BOLT222..BACB30YP8K13
BOLT999..BACB30YP8K6
BOLT222..BACB30YP8K9
COLLAR5139354545BACC30AC6
COLLAR2246..BACC30BH6
COLLAR...1212BACC30BH8
COLLAR969696..BACC30BL6
COLLAR454545..BACC30BL8
COLLAR.16161616BACC30M6
COLLAR755..BACC30M8
COLLAR4..22BACC30R6
FILLER.1111BACF3F008G019NN
FILLER1....BACF3F008G089NN
FILLER, FLAT1....BACF3F008G162NN
FILLER1....BACF3F008J008NN
FILLER111..BACF3F008J042NN
FILLER.11..BACF3F009X042NN
FILLER, FLAT11111BACF3F013L058NN
FILLER, FLAT11111BACF3F013L062NN
FILLER, RECTAN-
GULAR
4....BACF3H06DA031HN
FILLER, RECTAN-
GULAR
1....BACF3H09DA024HN
FILLER, RECTAN-
GULAR
3....BACF3H09DA027HN
FILLER, RECTAN-
GULAR
11111BACF3H11LM074HN
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
36 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 37

Kit 141U0062
NotesExisting Part
Number
NameQTYNew Part Number
-5-4-3-2-1
FILLER, RECTAN-
GULAR
11111BACF3H11LM089HN
FILLER1....BACF3T06E19-10
FILLER, TAPERED1....BACF3T08F20-10
NUT33333BACN10JC3CD
RIVET2..22BACR15BA6D10C
RIVET...33BACR15BA6D5C
RIVET....2BACR15BA6D6C
RIVET...22BACR15BA6D7C
RIVET...33BACR15BA6D9C
RIVET3....BACR15BB5D3C
RIVET...33BACR15BB5D5C
RIVET33333BACR15BB5D6C
RIVET13.544BACR15BB6D10C
RIVET..31717BACR15BB6D5C
RIVET13771922BACR15BB6D6C
RIVET723126BACR15BB6D7C
RIVET14435BACR15BB6D8C
RIVET431166BACR15BB6D9C
RIVET20222222BACR15FV6KE10
RIVET333..BACR15FV6KE11
RIVET111..BACR15FV6KE12
RIVET333..BACR15FV6KE8
RIVET222..BACR15FV6KE9
RIVET...22BACR15GF6D5
RIVET, 100 DEG2....BACR15GF7D10
SHIM,LAMINATED111..BACS40R008B032F
SHIM, LAMINAT-
ED
.1111BACS40R008B339F
SHIM,LAMINATED111..BACS40R008E008F
SHIM, LAMINAT-
ED
.11..BACS40R008E022F
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
37 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 38

Kit 141U0062
NotesExisting Part
Number
NameQTYNew Part Number
-5-4-3-2-1
SHIM, LAMINAT-
ED
.11..BACS40R008E046F
WASHER33333NAS1149D0316J
(a) This part is not used for Production
(b) You cannot use the existing part to replace the new or changed part
(c) There are more parts than are necessary
(d) If grip length shown is not available at Boeing, fasteners supplied in kits may be one grip length
longer than indicated. Also, if any fasteners part numbers listed are not available or have been su-
perseded, substitute fasteners may be supplied in kits. Boeing Document D-590 and Boeing
Drawing 65B88700 are used to determine the part numbers used as substitutes.
Kit 141U0062
NotesExisting Part
Number
NameQTYNew Part Number
-9-8-7-6
(a) (b)KIT - VARIABLE
FASTENERS
...-141U0062-6
(a) (b)KIT - VARIABLE
FASTENERS
..-.141U0062-7
(a) (b)KIT - VARIABLE
FASTENERS
.-..141U0062-8
(a) (b)KIT - VARIABLE
FASTENERS
-...141U0062-9
BOLT...2BACB30NW6K10Y
BOLT.1111.BACB30NW6K11Y
BOLT.22.BACB30NW6K12Y
BOLT...2BACB30NW6K4X
BOLT.19193BACB30NW6K5Y
BOLT.22.BACB30NW6K6Y
BOLT.22.BACB30NW6K7Y
BOLT...1BACB30NW6K8Y
BOLT...2BACB30NW6K9Y
BOLT333.BACB30NW8K10X
BOLT.33.BACB30NW8K11Y
BOLT111.BACB30NW8K8X
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
38 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 39

Kit 141U0062
NotesExisting Part
Number
NameQTYNew Part Number
-9-8-7-6
BOLT111.BACB30NW8K9X
BOLT...2BACB30NX6K10Y
BOLT...9BACB30NX6K2X
BOLT...10BACB30NX6K4X
BOLT...9BACB30NX6K5X
BOLT...5BACB30NX6K7Y
BOLT...3BACB30NX6K8Y
BOLT...1BACB30NX8K4
BOLT...7BACB30NX8K5
BOLT...2BACB30NX8K6
BOLT1...BACB30VT6K10
BOLT6...BACB30VT6K11
BOLT21...BACB30VT6K5
BOLT1...BACB30VT6K9
BOLT3...BACB30VT8K11
BOLT3...BACB30VT8K5
BOLT3...BACB30VT8K8
BOLT12...BACB30VT8K9
BOLT.11.BACB30YP6K10
BOLT202929.BACB30YP6K11
BOLT222.BACB30YP6K12
BOLT.22.BACB30YP6K2
BOLT305555.BACB30YP6K5
BOLT333.BACB30YP6K6
BOLT122.BACB30YP6K7
BOLT2...BACB30YP6K8
BOLT.11.BACB30YP6K9
BOLT222.BACB30YP8K10
BOLT588.BACB30YP8K11
BOLT222.BACB30YP8K13
BOLT..3.BACB30YP8K3
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
39 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 40

Kit 141U0062
NotesExisting Part
Number
NameQTYNew Part Number
-9-8-7-6
BOLT.1212.BACB30YP8K5
BOLT9...BACB30YP8K6
BOLT.3..BACB30YP8K8
BOLT21414.BACB30YP8K9
COLLAR...10BACC30AC6
COLLAR...31BACC30BH6
COLLAR...10BACC30BH8
COLLAR96105105.BACC30BL6
COLLAR454545.BACC30BL8
COLLAR...2BACC30M6
COLLAR555.BACC30M8
COLLAR.40408BACC30R6
COLLAR.33.BACC30R8
RIVET.33.BACR15BA6D10C
RIVET.2121.BACR15BA6D11C
RIVET...2BACR15BA6D6C
RIVET...1BACR15BA6D7C
RIVET.22.BACR15BA6D8C
RIVET.332BACR15BA6D9C
RIVET.33.BACR15BA7D10C
RIVET.2121.BACR15BA7D11C
RIVET.22.BACR15BA7D8C
RIVET.33.BACR15BA7D9C
RIVET...1BACR15BB6D7C
RIVET...4BACR15BB6D9C
RIVET20...BACR15FV6KE10
RIVET3...BACR15FV6KE11
RIVET1...BACR15FV6KE12
RIVET3...BACR15FV6KE8
RIVET2...BACR15FV6KE9
(a) There are more parts than are necessary
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
40 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 41

Kit 141U0062
NotesExisting Part
Number
NameQTYNew Part Number
-9-8-7-6
(b) If grip length shown is not available at Boeing, fasteners supplied in kits may be one grip
length longer than indicated. Also, if any fasteners part numbers listed are not available or
have been superseded, substitute fasteners may be supplied in kits. Boeing Document D-
590 and Boeing Drawing 65B88700 are used to determine the part numbers used as substi-
tutes.
Kit 141U0062
NotesExisting Part
Number
NameQTYNew Part Number
-12-11-10
(a) (b)KIT - VARIABLE
FASTENERS
..-141U0062-10
(a) (b)KIT - VARIABLE
FASTENERS
.-.141U0062-11
(a) (b)KIT - VARIABLE
FASTENERS
-..141U0062-12
BOLT77.BACB30NW6K5Y
BOLT11.BACB30NW6K6Y
BOLT22.BACB30NW6K7Y
BOLT333BACB30NW8K10X
BOLT33.BACB30NW8K11Y
BOLT111BACB30NW8K8X
BOLT111BACB30NW8K9X
BOLT..1BACB30VT6K10
BOLT..6BACB30VT6K11
BOLT..21BACB30VT6K5
BOLT..1BACB30VT6K9
BOLT..3BACB30VT8K11
BOLT..3BACB30VT8K5
BOLT..3BACB30VT8K8
BOLT..12BACB30VT8K9
BOLT11.BACB30YP6K10
BOLT292920BACB30YP6K11
BOLT222BACB30YP6K12
BOLT22.BACB30YP6K2
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
41 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 42

Kit 141U0062
NotesExisting Part
Number
NameQTYNew Part Number
-12-11-10
BOLT555530BACB30YP6K5
BOLT333BACB30YP6K6
BOLT221BACB30YP6K7
BOLT..2BACB30YP6K8
BOLT11.BACB30YP6K9
BOLT222BACB30YP8K10
BOLT885BACB30YP8K11
BOLT222BACB30YP8K13
BOLT1212.BACB30YP8K5
BOLT..9BACB30YP8K6
BOLT33.BACB30YP8K8
BOLT14142BACB30YP8K9
COLLAR10510596BACC30BL6
COLLAR454545BACC30BL8
COLLAR555BACC30M8
COLLAR1010.BACC30R6
COLLAR33.BACC30R8
RIVET33.BACR15BA6D10C
RIVET33.BACR15BA6D11C
RIVET33.BACR15BA7D10C
RIVET33.BACR15BA7D11C
RIVET181820BACR15FV6KE10
RIVET..3BACR15FV6KE11
RIVET..1BACR15FV6KE12
RIVET333BACR15FV6KE8
RIVET222BACR15FV6KE9
(a) There are more parts than are necessary
(b) If grip length shown is not available at Boeing, fasteners supplied in kits may be one
grip length longer than indicated. Also, if any fasteners part numbers listed are not
available or have been superseded, substitute fasteners may be supplied in kits.
Boeing Document D-590 and Boeing Drawing 65B88700 are used to determine the
part numbers used as substitutes.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
42 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 43

2. Parts and Materials Supplied by the Operator
NotesNameQTYPart Number /
Specification
-Sealant8
ounces
BMS 5-95
-Primer8
ounces
BMS 10-11, Type I
(a) Refer to 747 Structural Repair Manual Chapter 51 for alternative fasteners.
(b) See the Qualified Products List at the end of the Boeing Material Specification (BMS) for
supplier data.
NOTE: Drawing 691U0145 Sheet 1 and Sheet 2 list additional parts that will be required if chord
repair is necessary.
3. Parts Modified and Reidentified
None.
4. Parts Removed and Not Replaced
None.
D. Parts Necessary to Change Spares
None.
E. Special Tooling - Price and Availability
None.
F. Special Tooling Necessary to do this Service Bulletin
No special tools or equipment are necessary to do the change in this service bulletin. But, maintenance
and overhaul tools in the manuals given in Paragraph 1.J., References, can be necessary. Examine
operator tool supply to make sure all necessary tools are available.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
43 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 44

BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
44 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT
BLANK PAGE

### Page 45

3.    ACCOMPLISHMENT INSTRUCTIONS
A. GENERAL INFORMATION
CAUTION: KEEP THE WORK AREA, WIRES AND ELECTRICAL BUNDLES CLEAN OF METAL
PARTICLES OR CONTAMINATION WHEN YOU USE TOOLS. UNWANTED MATERIAL,
METAL PARTICLES OR CONTAMINATION CAUGHT IN WIRE BUNDLES CAN CAUSE
DAMAGE TO THE BUNDLES. DAMAGED WIRE BUNDLES CAN CAUSE SPARKS OR
OTHER ELECTRICAL DAMAGE.
NOTE: 1. The instructions identified in Paragraph 3.B., Work Instructions and the Figure(s)
give the recommended sequence of steps. The sequence of steps to do this service
bulletin can be changed.
2. Manual titles are referred to by acronyms. Refer to Paragraph 1.J., References, for
definition of the acronyms.
3. Obey all of the warnings and cautions given in the specified manual sections.
4. Unless shown differently, these dimensions and tolerances are used:
– Linear dimensions are in inches
– Tolerance on linear dimensions, other than rivet and bolt edge margins, is plus
or minus 0.03
– Tolerance on rivet and bolt edge margin is plus or minus 0.05
– Angular tolerance is plus or minus 2 degrees
– Hole dimensions for standard solid rivets are given in 747 SRM, Chapter 51
– Torque limits to tighten nuts and bolts are given in 747 SRM, Chapter 51
5. For approved fastener and process material substitutions, refer to 747 SRM, Chapter
51. Alternate fasteners are given in 747 SRM Chapter 51 and Boeing Drawing
012W6100.
6. If the length of any fastener specified in this service bulletin does not meet the
installation standards given in SRM Chapter 51, then a fastener of the same
specification, or an approved substitute, with a length which meets the installation
standards given in SRM Chapter 51 may be used.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
45 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 46

7. A Detailed Inspection is defined as: An intensive examination of a specific item,
installation, or assembly to detect damage, failure, or irregularity. Available lighting
is normally supplemented with a direct source of good lighting at an intensity deemed
appropriate. Inspection aids such as mirrors, magnifying lenses, etc. may be
necessary. Surface cleaning and elaborate procedures may be required.
8. These work instructions refer to procedures included in other Boeing documents.
When the words "refer to" are used and the operator has an accepted alternative
procedure, the accepted alternative procedure can be used. When the words "in
accordance with" are included in the instruction, the procedure in the Boeing document
must be used.
9. A General Visual Inspection is defined as: A visual examination of an interior or
exterior area, installation or assembly to detect obvious damage, failure or irregularity.
This level of inspection is made from within touching distance unless otherwise
specified. A mirror may be necessary to enhance visual access to all exposed surfaces
in the inspection area. This level of inspection is made under normally available
lighting conditions such as daylight, hangar lighting, flashlight or drop-light and may
require removal or opening of access panels or doors. Stands, ladders or platforms
may be required to gain proximity to the area being checked.
B. WORK INSTRUCTIONS
PART 1 - ACCESS
1. Group 1, Configuration 1, 3; Group 3, Configuration 1; Group 5; Group 6, Configuration 1:
Get access to the Left and Right Main Entry Door 1 main upper sill from above as follows:
a. Open left and right Main Entry Door 1. Refer to 747-100/200/300 AMM 52-11-00 or 747-400
AMM 52-11-00 as accepted procedures.
b. Install safety barriers in the door openings. Refer to 747-100/200/300 AMM 52-11-01 or
747-400 AMM 52-11-01 as accepted procedures.
c. Remove the left and right Main Entry Door 1 Sidewall Lining Doorway Panel. Refer to
747-100/200/300 AMM 25-21-03 or 747-400 AMM 25-21-03 as accepted procedures.
d. Remove the left and right Main Entry Door 1 Attendant's Service Unit. Refer to 747-100/200/300
AMM 25-23-04 or 747-400 AMM 25-23-04 as accepted procedures.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
46 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 47

e. If installed, remove the emergency escape rope from above left and right Main Entry Door 1.
Refer to 747-100/200/300 AMM 25-61-03 or 747-400 AMM 25-61-03 as accepted procedures.
Also remove the escape rope retainer assembly, if installed, for access to the main upper sill
from above.
f. Remove the ceiling panel above left and right Main Entry Door 1. Refer to 747-100/200/300
AMM 25-22-04 or 747-400 AMM 25-22-01 as accepted procedures.
g. Loosen and move or remove sidewall and ceiling insulation above left and right Main Entry
Door 1 as necessary for access to the main upper sill. Refer to 747-100/200/300 AMM 25-21-04
or 747-400 AMM 25-21-04 as accepted procedures.
2. Group 1, Configuration 2, 4; Group 3, 6, Configuration 2:
Get access to the Left and Right Main Entry Door 1 main upper sill from above as follows:
a. Open left and right Main Entry Door 1. Refer to 747-100/200/300 AMM 52-11-00 or 747-400
AMM 52-11-00 as accepted procedures.
b. Install safety barriers in the door openings. Refer to 747-100/200/300 AMM 52-11-01 or
747-400 AMM 52-11-01 as accepted procedures.
c. Remove the sidewall lining above left and right Main Entry Door 1. Refer to 747-100/200/300
AMM 25-59-01 or 747-400 AMM 25-59-01 as accepted procedures.
d. If installed, remove the emergency escape rope from above left and right Main Entry Door 1.
Refer to 747-100/200/300 AMM 25-61-03 or 747-400 AMM 25-61-03 as accepted procedures.
Also remove the escape rope retainer assembly, if installed, for access to the main upper sill
from above.
e. Remove the ceiling lining above left and right Main Entry Door 1. Refer to 747-100/200/300
AMM 25-59-01 or 747-400 AMM 25-59-01 as accepted procedures.
f. Loosen and move or remove sidewall and ceiling insulation above left and right Main Entry
Door 1 as necessary for access to the main upper sill. Refer to 747-100/200/300 AMM 25-59-05
or 747-400 AMM 25-59-05 as accepted procedures.
3. Group 2, 4, 7:
Get access to the Left Main Entry Door 1 main upper sill from above as follows:
a. Open left Main Entry Door 1. Refer to 747-100/200/300 AMM 52-11-00 or 747-400 AMM
52-11-00 as accepted procedures.
b. Install a safety barrier in the door opening. Refer to 747-100/200/300 AMM 52-11-01 or 747-400
AMM 52-11-01 as accepted procedures.
c. Remove the sidewall lining above Main Entry Door 1. Refer to 747-100/200/300 AMM 25-59-01
or 747-400 AMM 25-59-01 as accepted procedures.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
47 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 48

d. If installed, remove the emergency escape rope from above Main Entry Door 1. Refer to
747-100/200/300 AMM 25-61-03 or 747-400 AMM 25-61-03 as accepted procedures. Also
remove the escape rope retainer assembly, if installed, for access to the main upper sill from
above.
e. Remove the ceiling lining above Main Entry Door 1. Refer to 747-100/200/300 AMM 25-59-01
or 747-400 AMM 25-59-01 as accepted procedures.
f. Loosen and move or remove sidewall and ceiling insulation above Main Entry Door 1 as
necessary for access to the main upper sill. Refer to 747-100/200/300 AMM 25-59-05 or
747-400 AMM 25-59-05 as accepted procedures.
4. Do inspections in accordance with PART 2 or PART 5.
PART 2 - INSPECTION
1. Group 1-4:
Do a general visual inspection of the left Main Entry Door 1 upper main sill for an existing outer
chord repair installed in accordance with 747-100/200/300 SRM 53-10-04 Figure 93 or 747-SP
SRM 53-19-02 Figure 52. Remove any outer chord repair that is found.
NOTE: The 747-100/200/300 SRM 53-10-04, Figure 93, or 747-SP SRM 53-19-02, Figure 52
outer chord repairs are not applicable to 747-400 airplanes.
2. Group 1, 3:
Do a general visual inspection of the right Main Entry Door 1 upper main sill for an existing outer
chord repair installed in accordance with 747-100/200/300 SRM 53-10-04, Figure 93, or 747-SP
SRM 53-19-02, Figure 52. Remove any outer chord repair that is found.
NOTE: The 747-100/200/300 SRM 53-10-04, Figure 93, or 747-SP SRM 53-19-02, Figure 52
outer chord repairs are not applicable to 747-400 airplanes.
3. Group 1-7:
Do a detailed inspection of the left Main Entry Door 1 main upper sill in accordance with Figure 1.
4. Group 1, 3, 5-6:
Do a detailed inspection of the right Main Entry Door 1 main upper sill in accordance with Figure
2.
5. Group 1-7:
If no crack(s) is found and a repair was removed, install the Drawing 691U0145 or 141U0062 outer
chord repair in accordance with PART 3.
6. Group 1-7:
If no crack(s) is found, and no repair was removed, install equipment that was removed for access
in accordance with PART 4. Put the airplane back to a serviceable condition. Get access in
accordance with PART 1 and do the inspection in PART 2 again at the time given in Table 1 of
Paragraph 1.E., Compliance.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
48 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 49

NOTE: As an alternative if no crack(s) is found, continue to PART 3 and install the Drawing
691U0145 or 141U0062 outer chord repair. After installation of this repair, start to do
inspections of the repair in accordance with PART 5 at the time given in Paragraph 1.E.,
Compliance.
7. Group 1-7:
If crack(s) is found, install a repair in accordance with PART 3.
PART 3 - REPAIR
1. Group 1-4:
If installed, remove any 747-100/200/300 SRM 53-10-04 Figure 93 or 747-SP SRM 53-19-02
Figure 52 repairs that are installed. Install a new repair in accordance with Drawing 691U0145 or
141U0062.
2. Group 1-7:
If outer chord crack(s) is found, repair by installing the repair in accordance with Drawing 691U0145
or 141U0062.
3. Group 1-7:
Remove and replace cracked frame attach angles or clips.
4. Group 1-7:
If main upper sill web crack(s) is found, contact Boeing for repair data and do the repair.
5. Group 1-7:
Install equipment that was removed for access in accordance with PART 4. Put the airplane back
to a serviceable condition.
a. If the Drawing 691U0145 or 141U0062 outer chord repair was installed, start to do the
inspections in PART 5 at the time given in Table 2 or Table 3 of Paragraph 1.E., Compliance.
If the Drawing 691U0145 or 141U0062 outer chord repair was not installed, do the inspection
in PART 1 again at the time given in Table 1 of Paragraph 1.E., Compliance.
PART 4 - RESTORATION
1. Group 1, Configuration 1, 3; Group 3, Configuration 1; Group 5; Group 6, Configuration 1:
Install equipment that was removed for access to the left and right Main Entry Door 1 main upper
sill as follows:
a. Install the sidewall and ceiling insulation above left and right Main Entry Door 1 that was moved
for access to the main upper sill. Refer to 747-100/200/300 AMM 25-21-04  or 747-400 AMM
25-21-04  as accepted procedures.
b. Install the ceiling panel above left and right Main Entry Door 1. Refer to 747-100/200/300
AMM 25-22-04 or 747-400 AMM 25-22-01 as accepted procedures.
c. If removed for access, install the escape rope retainer assembly and the emergency escape
rope above left and right Main Entry Door 1. Refer to 747-100/200/300 AMM 25-61-03 or
747-400 AMM 25-61-03 as accepted procedures.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
49 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 50

d. Install the left and right Main Entry Door 1 Attendant's Service Unit. Refer to 747-100/200/300
AMM 25-23-04 or 747-400 AMM 25-23-04 as accepted procedures.
e. Install the left and right Main Entry Door 1 Sidewall Lining Doorway Panel. Refer to
747-100/200/300 AMM 25-21-03 or 747-400 AMM 25-21-03 as accepted procedures.
f. Remove the safety barrier and close left and right Main Entry Door 1. Refer to 747-100/200/300
AMM 52-11-00 or 747-400 AMM 52-11-00 as accepted procedures.
2. Group 1, Configuration 2, 4; Group 3, 6, Configuration 2:
Install equipment that was removed for access to the left and right Main Entry Door 1 main upper
sill as follows:
a. Install the sidewall and ceiling insulation above left and right Main Entry Door 1 that was moved
for access to the main upper sill. Refer to 747-100/200/300 AMM 25-59-05 or 747-400 AMM
25-59-05 as accepted procedures.
b. Install the ceiling lining above left and right Main Entry Door 1. Refer to 747-100/200/300 AMM
25-59-01 or 747-400 AMM 25-59-01 as accepted procedures.
c. If removed for access, install the escape rope retainer assembly and the emergency escape
rope above left and right Main Entry Door 1. Refer to 747-100/200/300 AMM 25-61-03 or
747-400 AMM 25-61-03 as accepted procedures.
d. Install the sidewall lining above left and right Main Entry Door 1. Refer to 747-100/200/300
AMM 25-59-01 or 747-400 AMM 25-59-01 as accepted procedures.
e. Remove the safety barrier and close left and right Main Entry Door 1. Refer to 747-100/200/300
AMM 52-11-00 or 747-400 AMM 52-11-00 as accepted procedures.
3. Group 2, 4, 7:
Install equipment that was removed for access to the left Main Entry Door 1 main upper sill as
follows:
a. Install the sidewall and ceiling insulation above Main Entry Door 1 that was moved for access
to the main upper sill. Refer to 747-100/200/300 AMM 25-59-05 or 747-400 AMM 25-59-05
as accepted procedures.
b. Install the ceiling lining above Main Entry Door 1. Refer to 747-100/200/300 AMM 25-59-01
or 747-400 AMM 25-59-01 as accepted procedures.
c. If removed for access, install the escape rope retainer assembly and the emergency escape
rope above Main Entry Door 1. Refer to 747-100/200/300 AMM 25-61-03 or 747-400 AMM
25-61-03 as accepted procedures.
d. Install the sidewall lining above Main Entry Door 1. Refer to 747-100/200/300 AMM 25-59-01
or 747-400 AMM 25-59-01 as accepted procedures.
e. Remove the safety barrier and close Main Entry Door 1. Refer to 747-100/200/300 AMM
52-11-00 or 747-400 AMM 52-11-00 as accepted procedures.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
50 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 51

PART 5 - AFTER-REPAIR INSPECTION
1. Group 1-7:
At the time given in Table 2 or Table 3 of Paragraph 1.E., Compliance, get access in accordance
with PART 1.
2. Group 1-7:
Do inspections of left Main Entry Door 1 main upper sills with the Drawing 691U0145 or 141U0062
outer chord repair installed in accordance with Figure 3.
3. Group 1, 3, 5-6:
Do inspections of right Main Entry Door 1 main upper sills with the Drawing 691U0145 or 141U0062
outer chord repair installed in accordance with Figure 4.
4. Group 1-7:
If no crack is found, install equipment that was removed for access in accordance with PART 4.
Put the airplane back to a serviceable condition. Do the PART 5 inspection again at the time given
in Table 2 or Table 3 of Paragraph 1.E., Compliance.
5. Group 1-7:
If any crack is found, contact Boeing for repair data and do the repair.
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1: July 15, 2010
51 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 52 (OCR)

BOEING SERVICE BULLETIN 747-53A2785
ALERT  ALERT
UPPER DECK
FLOOR BEAMS
0000000000000  MAIN SILL  UPPER
/ S-13
• S-14
S-15
3—S-16
S-17
• S-18
• S-19
- S-20
• S-22
S-23
→ S-24
• S-26
- S-27
ASSEMBLY  REVEAL  5-28
/ S-30
STA
400
LOWER
STA  MAIN SILL
420
STA
LOWER AUXILLIARY SILL  440
STA
460
STA
480
STA  STA  500  1664247
520  MAIN ENTRY DOOR NO. 1
FIGURE 1: LEFT MAIN ENTRY DOOR 1 MAIN UPPER SILL INSPECTION
(SHEET 1 OF 4)
Original Issue: February 12, 2009
Revision 1 July 15, 2010  BOEING PROPRIETARY -  747-53A2785
Copyright © Unpublished Work - See page 1 for details.  52 of 63

### Page 53 (OCR)

BOEING SERVICE BULLETIN 747-53A2785
ALERT  ALERT
TYPICAL CRACK
STA  460  STILL WEB  WEB (4  TYPICAL CRACK
STA  460
TYPICAL CRACK
CHORD  OUTER CHORD
FIGURE 1: LEFT MAIN ENTRY DOOR 1 MAIN UPPER SILL INSPECTION
(SHEET 2 OF 4)
Original Issue: February 12, 2009
Revision 1 July 15, 2010  BOEING PROPRIETARY -  747-53A2785
Copyright © Unpublished Work - See page 1 for details.  53 of 63

### Page 54 (OCR)

BOEING SERVICE BULLETIN 747-53A2785
ALERT  ALERT
STA
440
2) CLIP
STA
460
FRAME
@ ANGLE
TYPICAL CRACK
EXAMPLE
STA
480
CLIP 2
EXAMPLE
D
EXAMPLE
1664643
The step numbers shown below agree with the numbers shown in the circle symbols in the figure.
FIGURE 1: LEFT MAIN ENTRY DOOR 1 MAIN UPPER SILL INSPECTION
(SHEET 3 OF 4)
Original Issue: February 12, 2009
Revision 1 July 15, 2010  BOEING PROPRIETARY -  747-53A2785
Copyright © Unpublished Work - See page 1 for details.  54 of 63

### Page 55

MORE DATAQTYIDENTIFICATIONNAMETASKSTEP
Do a detailed inspec-
tion from above of
the visible outer
chord from STA 440
to STA 480, for
cracks.
--Outer ChordInspect1
Do a detailed inspec-
tion from above of
the frame attach an-
gles or clips from
STA 440 to STA
480, for cracks.
--Attach Angles or ClipsInspect2
Do a detailed inspec-
tion from above of
the visible upper sill
web from STA 440
to STA 480, for
cracks.
--Sill WebInspect3
Do a detailed inspec-
tion from below of
the visible upper sill
web from STA 440
to STA 480, for
cracks.
--Sill WebInspect4
Do a detailed inspec-
tion from below of
the visible outer
chord from STA 440
to STA 480, for
cracks.
--Outer ChordInspect5
FIGURE 1: LEFT MAIN ENTRY DOOR 1 MAIN UPPER SILL INSPECTION
(SHEET 4 OF 4)
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1 July 15, 2010
55 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 56 (OCR)

BOEING SERVICE BULLETIN 747-53A2785
ALERT  ALERT
UPPER DECK
FLOOR BEAMS
UPPER  MAIN SILL  •000000000000
S-13
S-14
S-15.
S-16~
S-17~  >
S-18
S-19
S-20
S-22
S-23.
S-24.
S-26
S-27
REVEAL
S-28  ASSEMBLY
S-30_
STA
400
LOWER
MAIN SILL
STA
420
STA  440  LOWER AUXILLIARY SILL
STA
460
STA
480
STA  500  STA  1664704
MAIN ENTRY DOOR NO. 1  520
FIGURE 2: RIGHT MAIN ENTRY DOOR 1 MAIN UPPER SILL INSPECTION
(SHEET 1 OF 4)
Original Issue: February 12, 2009
Revision 1 July 15, 2010  747-53A2785
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.  56 of 63

### Page 57 (OCR)

BOEING SERVICE BULLETIN 747-53A2785
ALERT  ALERT
OUTER  CHORD  OUTER CHORD
TYPICAL CRACK
STA  460  STILL WEB  WEB  • TYPICAL CRACK  STA  460
TYPICAL CRACK
1664696
FIGURE 2: RIGHT MAIN ENTRY DOOR 1 MAIN UPPER SILL INSPECTION
(SHEET 2 OF 4)
Original Issue: February 12, 2009
Revision 1 July 15, 2010  BOEING PROPRIETARY -  747-53A2785
Copyright © Unpublished Work - See page 1 for details.  57 of 63

### Page 58 (OCR)

BOEING SERVICE BULLETIN 747-53A2785
ALERT  ALERT
STA
440
STA
460
CLIP (2)  FRAME
ANGLE 2
TYPICAL
CRACK
EXAMPLE
C
STA
480
2) CLIP  EXAMPLE
D
EXAMPLE
1664703
The step numbers shown below agree with the numbers shown in the circle symbols in the figure.
FIGURE 2: RIGHT MAIN ENTRY DOOR 1 MAIN UPPER SILL INSPECTION
(SHEET 3 OF 4)
Original Issue: February 12, 2009
Revision 1 July 15, 2010  BOEING PROPRIETARY -  747-53A2785
Copyright © Unpublished Work - See page 1 for details.  58 of 63

### Page 59

MORE DATAQTYIDENTIFICATIONNAMETASKSTEP
Do a detailed inspec-
tion from above of
the visible outer
chord from STA 440
to STA 480, for
cracks.
--Outer ChordInspect1
Do a detailed inspec-
tion from above of
the frame attach an-
gles or clips from
STA 440 to STA
480, for cracks.
--Attach Angles or ClipsInspect2
Do a detailed inspec-
tion from above of
the visible upper sill
web from STA 440
to STA 480, for
cracks.
--Sill WebInspect3
Do a detailed inspec-
tion from below of
the visible upper sill
web from STA 440
to STA 480, for
cracks.
--Sill WebInspect4
Do a detailed inspec-
tion from below of
the visible outer
chord from STA 440
to STA 480, for
cracks.
--Outer ChordInspect5
FIGURE 2: RIGHT MAIN ENTRY DOOR 1 MAIN UPPER SILL INSPECTION
(SHEET 4 OF 4)
BOEING PROPRIETARY -
Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 12, 2009
747-53A2785Revision 1 July 15, 2010
59 of 63
BOEING SERVICE BULLETIN 747-53A2785
ALERTALERT

### Page 60 (OCR)

BOEING SERVICE BULLETIN 747-53A2785
ALERT  ALERT
UPPER DECK
FLOOR BEAMS
000000000000  MAIN SILL  UPPER
/ S-13
• S-14
S-15
3—S-16
S-17
• S-18
• S-19
- S-20
• S-22
S-23
• S-24
• S-26
REVEAL  - S-27
ASSEMBLY
5-28
/ S-30
STA
400
LOWER
STA  MAIN SILL
420
LOWER AUXILLIARY SILL  STA
440
STA
460
STA
480
STA  1664707
STA  500
520  MAIN ENTRY DOOR NO. 1
The step numbers shown below agree with the numbers shown in the circle symbols in the figure.
FIGURE 3: REPAIRED LEFT MAIN ENTRY DOOR UPPER SILL AFTER-REPAIR INSPECTION
(SHEET 1 OF 2)
Original Issue: February 12, 2009
Revision 1 July 15, 2010  BOEING PROPRIETARY -  747-53A2785
Copyright © Unpublished Work - See page 1 for details.  60 of 63

The text continues at https://openairdocs.org/service-documents/boeing/747-53a2785/file/c9b46b7ab966.md?from=61

---
OpenAirDocs.org is an independent research project of [Contrail Labs](https://contraillabs.com/). It is not affiliated with the FAA or the NTSB. Source documents are U.S. government works in the public domain, except the copies of manufacturers’ service documents, which belong to their rights holders.