# Bombardier Service Bulletin 700-28-6006

Copy: No revision named ("SB 700-28-6006 Basic Revision"), 15 pages: PDF https://openairdocs.org/files/sha256/9d/a9/9da9deb7e99a51b2b08c2a3a49cdf78bf044c72dbd5ec2063d2739e1cfb52ac6; text https://openairdocs.org/service-documents/bombardier/sb-700-28-6006/file/9da9deb7e99a.md. Rights: © Bombardier Inc. Filed by the FAA in regulations.gov docket FAA-2021-0030; AD 2021-10-22 incorporates this document by reference. Not covered by OpenAirDocs’ CC0 dedication.

## Details

- Manufacturer: [Bombardier](https://openairdocs.org/service-documents/bombardier.md)
- Type: Service bulletin (Service Bulletin)
- Number: 700-28-6006
- Page: https://openairdocs.org/service-documents/bombardier/sb-700-28-6006

## ADs that cite it (1) (OpenAirDocs)

Newest first, with the revision each names, as OpenAirDocs read it from the AD's text.

- [AD 2021-10-22](https://openairdocs.org/ad/2021-10-22.md), effective Jul 6, 2021: No revision named

Also cited in [1 proposed AD](https://openairdocs.org/service-documents/bombardier/sb-700-28-6006/proposed.md).

## Text (15 pages)

Rights: © Bombardier Inc. Filed by the FAA in regulations.gov docket FAA-2021-0030; AD 2021-10-22 incorporates this document by reference. Not covered by OpenAirDocs’ CC0 dedication. Each page's text from the PDF; open the PDF at a page with #page=N.

### Page 1

MODIFICATION – REFUEL / DEFUEL SYSTEM –
REFUEL/DEFUEL LINE BRACKET REPLACEMENT
The information below is provided for your reference. For full details, including labor and part
coverage, please see corresponding paragraph contained within this bulletin.
RECOMMENDED
SPECIFIED TIME COMPLIANCE
COMPLIANCE TIME
Within 30 months of Service
Bulletin release (Basic Issue)
EFFECTIVITY: A/C Serial No. 9657 to 9844
MANPOWER: 10 man−hours
CONTINUED AIRWORTHINESS (CAW)
FLEET CAMPAIGN NOYES
TLMC, CH 5 AFFECTED NOYES
KITS and/or PARTS YES NO
TOOLING/GSE YES NO
PLANNING INFORMATION NOYES
DEDICATED SCHEDULE NOYES
PREREQUISITE SERVICE BULLETINS: N/A
NOTE: This Service Bulletin will be subject to an Airworthiness Directive (AD) which will
make it necessary to implement this Service Bulletin.
To place an order for parts or kits, please call Bombardier Aviation Parts Services at:
514−855−2999 or 1−866−538−1247
SERVICE BULLETIN SUMMARY
my.businessaircraft.bombardier.com
MODEL BD−700−1A10 (BD−700)
ATA 28−23
FUEL
Basic Issue: Jun 01/2020 700−28−6006
Page 1 of 1
This Service Bulletin is available at:

### Page 2

MODIFICATION – REFUEL / DEFUEL SYSTEM –
REFUEL/DEFUEL LINE BRACKET REPLACEMENT
1. PLANNING INFORMATION
NOTE: Before you do this Service Bulletin, examine all STC, STA or equivalent
action changes to make sure that this Service Bulletin can be completed.
A. Effectivity
BD−700−1A10 aircraft, Serial No. 9657 to 9844.
NOTE: The instructions in this Service Bulletin are only applicable to the systems
and parts installed at the time of delivery of the aircraft or as changed by
Bombardier Aviation Service Bulletin(s).
B. Reason
Evidence:
A supplier reported to Bombardier that a bracket had been mislocated during
aircraft assembly on the intermediate rib in the center fuel tank during installation.
This condition may result in an undesirable offset and gap between the
refuel/defuel tube and the mating adjacent fuel fitting.
Objective/Benefit:
This Service Bulletin replaces the existing mislocated bracket with new modified
bracket to ensure proper alignment of fuel tube and fitting.
C. Description
This Service Bulletin gives instructions to:
− Remove and discard the hydraflow coupling and sleeve from the fuel lines,
SERVICE BULLETIN
my.businessaircraft.bombardier.com
MODEL BD−700−1A10 (BD−700)
ATA 28−23
FUEL
Refer to applicable governmental agency regulations and requirements and make sure that the work described in this
Service Bulletin is performed in compliance with manufacturer’s recommendations and/or acceptable industry standards.
This document is proprietary to Bombardier Inc. and/or its affiliates and may not be reproduced or copied in any form or
by any means without the prior written consent of Bombardier Inc. and/or its affiliates.
 2020 Bombardier Inc.  All rights reserved
Learjet, Challenger, Global, are registered trademarks of Bombardier Inc. or its subsidiaries.
Basic Issue: Jun 01/2020 700−28−6006
Page 1 of 12
This Service Bulletin is available at:

### Page 3

− Remove and discard the clamp from the bracket,
− Visually inspect the refuel/defuel tube for damage,
− If damage is found, remove and replace the tube,
− Remove and re−locate the bracket with a new modified bracket assembly,
− Install a new clamp, o−rings and hydraflow coupling and close out the area, and
− Do the necessary test of the refuel/defuel system.
D. Compliance
Recommended within 30 months from this Service Bulletin release date
(Basic Issue).
NOTE: If it is not possible to complete all the instructions in this Service Bulletin
because of the aircraft configuration, submit an SRPSA for an analysis
and to get an approved disposition to complete this Service Bulletin.
E. Approval
The technical content of this Service Bulletin has been approved under the
authority of Transport Canada Civil Aviation (TCCA) Design Approval Organization
(DAO) No. DAO #93−Q−02.
NOTES: 1. The technical content of this Service Bulletin is accepted by the FAA
under the Canada/USA bilateral Aviation Safety Agreement.
2. The technical content of this Service Bulletin is accepted by EASA
under the Canada/EU bilateral Aviation Safety Agreement.
F. Manpower
NOTES: 1. The man−hours given are to help you schedule the tasks given in this
Service Bulletin. The man−hours are for direct labor performed by an
experienced crew and do not include the time for familiarization,
planning, aircraft preparation in hangar such as towing and
positioning of scaffolds, removal of interior furnishings, repainting,
supervision and inspection.
For more information related to the man−hours, refer to
SB 700−00−6002.
2. This Service Bulletin may require consumable materials that have
specific curing times (refer to Paragraph 3). The accumulated curing
time is not included in the man−hours and should be considered for
planning purposes before you schedule this Service Bulletin.
10 man−hours are necessary to do this modification.
The labor required to do this Service Bulletin is at no cost if:
− the work is done at Bombardier Business Aviation Services (BBAS) or
Authorized Service Facilities (ASF), and
MODEL BD−700−1A10 (BD−700)
Basic Issue: Jun 01/2020 700−28−6006
Page 2 of 12

### Page 4

− this Service Bulletin is scheduled in less than 30 months from its release date
(Basic Issue).
G. Material − Cost and Availability
Kit 700K28−6006 is necessary to do this modification.
KIT NO. PRICE
700K28−6006
Please contact Bombardier Aviation
Parts Services, in Montreal, for delivery
lead times and pricing.
Sufficient kits will be kept for the estimated amount of orders.
In addition to the kit shown above, the parts in Paragraph 3.B. and material in
Paragraph 3.C. are necessary to do this modification.
This kit is available at no cost if:
− a no−charge purchase order is sent to Bombardier Aviation in less than
30 months from this Service Bulletin release date (Basic Issue).
H. Tooling
The equipment and tools listed below are necessary to do this modification.
GSE REFERENCE NO. PART NO. DESCRIPTION
20X−10−01 − Tag, Circuit Breaker(Red Ring)
NOTES: 1. Refer to the Global 6000 BD−700 Illustrated Tool and Equipment
Manual (ITEM) to make sure that you use the correct equipment
configuration.
2. Refer to the Liability Statement in the ITEM for the G6000, for
acceptable GSE equivalents.
I. Weight and Balance
No Change.
J. Electrical Load Data
No Change.
K. References
− TCCA Airworthiness Directive (Pending).
− Bombardier Aviation, Modification Summary, R700T400724, Rev. A.
MODEL BD−700−1A10 (BD−700)
Basic Issue: Jun 01/2020 700−28−6006
Page 3 of 12

### Page 5

− Bombardier Aviation, Kit Drawing KGC991−1612, Rev. A.
− Global 6000 BD−700 Aircraft Maintenance Manual (AMM), Chapters 6, 24, 28
and 53.
− Global 6000 BD−700 Aircraft Illustrated Parts Catalog (AIPC), Chapter 28.
− Bombardier Aviation, Standard Practices Manual (SPM), Chapter 20.
− Bombardier Aviation, Structural Repair Manual (SRM), Chapter 51.
L. Other Publications Affected
− Global 6000 BD−700 Aircraft Illustrated Parts Catalog (AIPC), Chapter 28.
M. Equivalent Service Bulletins
None.
2. ACCOMPLISHMENT INSTRUCTIONS
NOTES: 1. All TASKs given in the procedures that follow are from the Global 6000
BD−700−1A10, Aircraft Maintenance Manual (AMM) unless otherwise
specified.
2. All references made to zones, access panels and/or doors, are from the
Global 6000 BD−700−1A10, Aircraft Maintenance Manual (AMM),
Chapter 6.
A. Aircraft Setup
NOTE: The steps in the Aircraft Setup section of this Service Bulletin are
recommended steps. The steps give a recommendation to get access to
the work area. This recommendation is to give a safe work area and to
minimize possible damage to surrounding aircraft parts. Alternative steps
can be used at the operator’s discretion.
(1) Obey all electrical/electronic safety precautions. Refer to
AMM 24−00−00−910−801.
(2) Obey the fuel−system safety precautions. Refer to AMM 28−00−00−910−801.
(3) Prepare the fuel tank for access. Refer to AMM 28−10−00−840−801.
(4) Remove the belly fairing access−panel 183BB. Refer to
AMM 53−61−19−000−801.
(5) Remove the wing−tank access panels 183AZ and 183BZ. Refer to
AMM 28−11−01−000−801.
NOTE: The second panel needs to be opened to allow fuel tank venting.
MODEL BD−700−1A10 (BD−700)
Basic Issue: Jun 01/2020 700−28−6006
Page 4 of 12

### Page 6

B. Modification
NOTE: If it is not possible to complete all the instructions in this Service Bulletin
because of the configuration of the aircraft, submit a SRPSA for an
analysis and to get an approved disposition to complete this Service
Bulletin.
(1) On the intermediate rib assy, Part No. GM229−1302−7 at FS 698.75 and
LBL 27.00, locate the refuel tube assy, Part No. GM428−7227−1, the clamp,
Part No. MS21919WDF16 and bracket, Part No. GM427−7317−11. Refer to
Figure 1.
(2) Remove and discard the screw, Part No. MS35207−263, washer, Part No.
AN960JD10L, clamp, Part No. MS21919WDF16 and bracket, Part No.
GM427−7317−11.
(3) Remove and discard the o−rings, Part No. M25988/1−214 and coupling sleeve
assy, Part No. 14J02−16A.
(4) Perform the visual inspection. Refer to Figure 1 (Sheet 2).
(a) Inspect refuel tube assy, Part No. GM428−7227−1 to ensure there are no
indications of damage such as permanent deformation, corrosion, cracks,
gouges, dents, or deep scratches.
(b) Perform a detail visual inspection of 10X magnification of the elbow
sections of refuel tube assy, Part No. GM428−7227−1 to ensure there are
no indication of cracks or any other damage such as damaged paint,
permanent deformation, corrosion, gouges, dents, or deep scratches.
(c) If any damage is found outside of allowable damage limits, refer to
SPM−MM 20−22−00−910−805.
(i) Remove and replace the refuel tube assy, Part No. GM428−7227−1.
NOTE: Ensure there is no preload condition when reinstalling refuel
tube assy, Part No. GM428−7227−1.
(ii) Install 2 new o−rings and coupling assy at the other extremity of the
fuel tube. Refer to SPM−MM 20−30−00−910−808.
(d) If no damage is found outside of allowable damage limits, it is permissible
to retain existing fuel tube assy, Part No. GM428−7227−1.
(5) Install nutplate, Part No. MS21061L3 on bracket, Part No. GC427−0031−1,
using rivets, Part No. MS20426AD3−4, as shown on Figure 1, Detail E. Refer
to SRM 51−42−08.
NOTE: If required, it is permissible to adjust the grip length of rivets, Part No.
MS20426AD3−4.
(6) Temporarily install the clamp, Part No. MS21919WDF16 on bracket assy, Part
No. GC427−0031−1 and locate bracket assy as per Figure 1, Detail C and D.
Do not drill at this time.
NOTE: Make sure offset between refuel tube assy and fitting assy is less than
0.063 in. (1.60 mm), gap between fittings is 0.150 in. ± 0.050 in.
(3.81 mm ± 1.27 mm) and maximum misalignment of the tube axes
does not exceed 2 degrees. Refer to Figure 1, Detail F.
MODEL BD−700−1A10 (BD−700)
Basic Issue: Jun 01/2020 700−28−6006
Page 5 of 12

### Page 7

(7) Backdrill holes from structure to the bracket and secure temporarily.
(8) Install the new bracket, Part No. GC427−0031−1 with rivets, Part No.
MS20470AD4−6 on the intermediate rib assy, Part No. GM229−1302−7 at
FS 698.75 and LBL 27.00. Refer to SRM 51−42−08 and Figure 1.
NOTE: If required, it is permissible to adjust the grip length of rivets, Part No.
MS20426AD3−4.
(9) Install the new o−rings, Part No. M25988/1−214 and new coupling assy, Part
No.14J02−16A on the fitting assy, Part No. GM427−7211−1 and refuel tube
assy, Part No. GM428−7227−1. Refer to SPM−MM 20−30−00−910−808.
NOTES: 1. Ensure there is no preload condition when reinstalling coupling
assy.
2. Make sure offset between refuel tube assy, Part No.
GM428−7227−1 and fitting assy, Part No. GM427−7211−1 is less
than 0.063 in. (1.60 mm), gap is 0.150 in. ± 0.050 in.
(3.81 mm ± 1.27 mm) and maximum misalignment of the tube
axes does not exceed 2 degrees. Refer to Figure 1, Detail F.
(10) Visually inspect that the bonding spring has correct contact with the ferrule
during the installation of coupling, Part No. 14J02−16A.
(11) Install the new clamp, Part No. MS21919WDF16 with screw, Part No.
MS35207−263, washer, Part No. NAS1149D0332J on the bracket, Part
No. GC427−0031−1 and refuel tube assy, Part No. GM428−7227−1. Refer to
SRM 51−41−04
(12) Touch up the reworked areas as per the finish code A022. Refer to
SRM 51−01−04.
C. Testing
(1) Close the fuel tank after maintenance. Refer to AMM 28−10−00−840−803.
(2) Install the belly fairing access−panel 183BB. Refer to
AMM 53−61−19−400−801.
(3) Install the wing−tank access panels 183AZ and 183BZ. Refer to
AMM 28−11−01−400−801.
(4) Do the Operational test of the refuel/defuel system. Refer to
AMM 28−23−00−710−801.
D. Close−out
NOTE: The steps in the Close−out section of this Service Bulletin, except for the
return−to−service tests, are recommended steps. The steps give a
recommendation to install components removed during the Aircraft Setup.
This recommendation is to make sure that the aircraft is safe and ready to
return to service. Alternative steps can be used at the operator’s
discretion.
Remove all tools, equipment and unwanted materials from the aircraft.
MODEL BD−700−1A10 (BD−700)
Basic Issue: Jun 01/2020 700−28−6006
Page 6 of 12

### Page 8

E. Recording
When this Service Bulletin is completed, make an entry in the aircraft log and send
the attached Incorporation Notice to Bombardier Business Aircraft Customer
Services (BBACS).
For information, correction(s), comment(s) and/or feedback regarding Service
Bulletins released on the Customer Portal, please contact the Service Bulletin
Group at the following email address:
bbad_SBgroup@aero.bombardier.com
3. MATERIAL INFORMATION
A. Kit
Kit 700K28−6006 is necessary to do this Service Bulletin and contains the parts
that follow:
NEW PART NO. QTY ITEM USED PARTNO. INSTRUCTIONS-DISPOSITION
GC427−0031−1 1 Bracket − −
M25988/1−214 2 O−Ring − −
MS20426AD3−4 2 Rivet, CSK − −
MS20470AD4−6 3 Rivet, UNIHead − −
MS21061L3 1 Nutplate − −
MS21919WDF16 1 Clamp − −
MS35207−263 1 Screw − −
NAS1149D0332J 1 Washer − −
14J02−16A 1 Coupling − −
B. Parts
The parts that follow are necessary to do this Service Bulletin and are available
from Bombardier Aviation Parts Services, Montreal:
MODEL BD−700−1A10 (BD−700)
Basic Issue: Jun 01/2020 700−28−6006
Page 7 of 12

### Page 9

NEW PART NO. QTY ITEM USEDPART NO. INSTRUCTIONS-DISPOSITION
GM428−7227−1
(See Note 2) 1 Refuel Tube Assy − −
M25988/1−214
(See Note 2) 2 O−Ring − −
NOTES: 1. The part number for the item listed above is subject to change without
revision to this Service Bulletin. In case of discrepancy between this
list and any other list, the Illustrated Parts Catalog prevails and shall
be used to determine the latest part number.
2. The refuel tube assy and o−rings are required to replace only if found
damaged during inspection.
C. Material
The material that follows is necessary to do this Service Bulletin. It can be
purchased from a local supplier. Bombardier Aviation does not pay for this
consumable.
DESCRIPTION PART NO./NAME SPECIFICATION QUANTITY
SUPPLIER
(SEE
NOTE)
Coating
Chemical
Conversion
Alodine 1200S MIL−DTL−81706Class 1A AsRequired Code: A
NOTES: 1. Refer to the table that follows for supplier address listed by code.
2. At time of release of this Service Bulletin, the information on the
supplier was valid and accurate. In the event that this information has
changed, the operator is encouraged to use the World Wide Web to
find a local supplier.
SUPPLIERS ADDRESSES BY CODES
Code: A
Henkel Loctite Corp.
1001 Trout Brook Crossing,
Rocky Hill, CT, 06067−3910
U.S.A.
Tel.: 1−860−571−5100
Fax.: 1−860−571−5465
www.loctite.com
MODEL BD−700−1A10 (BD−700)
Basic Issue: Jun 01/2020 700−28−6006
Page 8 of 12

### Page 10

D. Publications
No publications required.
MODEL BD−700−1A10 (BD−700)
Basic Issue: Jun 01/2020 700−28−6006
Page 9 of 12

### Page 11

SB700−28−6006_001
LBL27.00
FS701.69
FS701.69
MODEL BD−700−1A10 (BD−700)
Centre Wing, Refuel/Defuel Line Bracket Replacement
Figure 1 (Sheet 1 of 3)
Basic Issue: Jun 01/2020 700−28−6006
Page 10 of 12

### Page 12

M25988/1−214
(O−RING)
M25988/1−214
(O−RING)
GM427−7317−11
(BRACKET)
MS21919WDF16
(CLAMP)
AN960JD10L
(WASHER)
MS35207−263
(SCREW)
NAS1149D0332J
(WASHER)
MS35207−263
(SCREW)
MS21919WDF16
(CLAMP)
GC427−0031−1
(BRACKET)
GM428−7227−1
(TUBE ASSEMBLY)
14J02−16A
(COUPLING) 14J02−16A
(COUPLING)
M25988/1−214
(O−RING)
M25988/1−214
(O−RING)
PRE MOD
POST MOD
SYMBOL WORK
PART DISCARDED IN
REMOVAL TASK
GM427−7211−1
(FITTING ASSEMBLY)
(REF)
GM427−7211−1
(FITTING ASSEMBLY)
(REF)
LBL27.00LBL27.00
GM428−7227−1
(TUBE ASSEMBLY)
NO 3 STGR
DATUM PLANENO 3 STGR
DATUM PLANE
MS21061L3
(NUTPLATE)
MS20470AD4−6
(RIVET)
(3 PLACES)
MS20426AD3−4
(RIVET)
(2 PLACES)
GM229−1302−7
(REF)
GM229−1302−7
(REF)
SB700−28−6006_002
MODEL BD−700−1A10 (BD−700)
Centre Wing, Refuel/Defuel Line Bracket Replacement
Figure 1 (Sheet 2 of 3)
Basic Issue: Jun 01/2020 700−28−6006
Page 11 of 12

### Page 13

GC427−0031−1
(BRACKET)
MS21919WDF16
(CLAMP) UP
NO 2 STGR
DATUM PLANE
NO 3 STGR
DATUM PLANE
LBL27.00
MS21061L3
(NUTPLATE)
GC427−0031−1
(BRACKET)
0.92 in. (REF)
(23.37 mm)
0.26 in. (REF)
(6.60 mm)
0.063 in.
(1.60 mm)
GM229−1302−7
(REF)
FS701.69
VIEW LOOKING OUTBOARD
FUEL LINES NOT SHOWN FOR CLARITY
SB700−28−6006_003
0.150 ± 0.050 in.
(3.81 ± 1.27 mm)
GM229−1302−7
(REF)
0.50 in.
(12.70 mm)
1.00 in. (REF)
(25.40 mm)
0.50 in.
(12.70 mm)
0.25 in.
(6.35 mm)
DIAMETER HOLE
GC427−0031−1
(BRACKET)
(REF)
MS21061L3
(NUTPLATE)
MS20426AD3−4
(RIVET)
VIEW ROTATED 90° CCW
SOME ELEMETS OMITTED FOR CLARITY
NOTE
Maximum misalignment of the tube axes does not exceed 2 degrees.1
1
0.063 in.
(1.60 mm)
MAXIMUM
MODEL BD−700−1A10 (BD−700)
Centre Wing, Refuel/Defuel Line Bracket Replacement
Figure 1 (Sheet 3 of 3)
Basic Issue: Jun 01/2020 700−28−6006
Page 12 of 12

### Page 14

700−28−6006 Basic Jun 01/2020
MODIFICATION – REFUEL / DEFUEL SYSTEM –
REFUEL/DEFUEL LINE BRACKET REPLACEMENT
bbad_SBgroup@aero.bombardier.com
NOTE: Please use Salesforce only for troubleshooting issues or when Engineering
deviation is necessary to accomplish the Service Bulletin modification.
SERVICE BULLETIN EVALUATION FORM
(Your ideas will help us provide better bulletins)
SERVICE BULLETIN: ISSUE: DATED:
TITLE:
For any information, correction(s), comment(s) and/or feedback regarding Service
Bulletins released on the Customer Portal, please contact the Service Bulletin Group
at the following email address:

### Page 15

SERVICE BULLETIN INCORPORATION SHEET − "700−28−6006"
Upon completion of the Service Bulletin, please fill−in, fax to
(514) 855−8798 or e−mail to Fracas at fracas.montreal@aero.bombardier.com
If you’re reporting Service Bulletin (SB) Incorporations to CAMP, sending
this Incorporation Sheet to Bombardier is not mandatory. If your aircraft is
on another tracking system, please contact Bombardier to make arrangements
for automated data submission.
700−28−6006 Basic
COMPLIED WITH
YES    NO    N/A
Actual hours to accomplish Service Bulletin:
* NOTES:
Aircraft Serial No. Aircraft Reg. No.
Airframe Hours: Airframe Landings
S.B. Incorporation Date Service Order No.
Facility incorporating S.B.
Name Signature Date
BOMBARDIER
SUBMISSION
Service Bulletin
Number
Rev. * Parts
Completed
Remarks/Reason
(Mandatory if N/A)
1. Where the Service Bulletin is divided into a number of parts (e.g., PARTS A,
B, C, D, etc.) which can be carried out separately, indicate only those parts
completed at this time.
2. For repetitive checks (usually PART A) only the initial check should be
reported unless otherwise stated in the Service Bulletin.
3. When more than one part is carried out at the same time, each part should
be reported.
4. Fill in ’Remark/Reason’ to explain compliance method when N/A is selected.(E.g. Part
not installed, N/A by effectivity, N/A by Part Serial Number, etc.
5. PCW means ’Previously Complied With’.
(dd/mm/yy)
Signature not required if sent by E−Mail (dd/mm/yy)

---
OpenAirDocs.org is an independent research project of [Contrail Labs](https://contraillabs.com/). It is not affiliated with the FAA or the NTSB. Source documents are U.S. government works in the public domain, except the copies of manufacturers’ service documents, which belong to their rights holders.