# M7 Aerospace Service Bulletin CC7-27-026: U.S. DOT/FAA - CC7 SB 27-026 R2 (10-23-13)

- Rights: © M7 Aerospace. Filed by the FAA in regulations.gov docket FAA-2014-0023; AD 2014-09-02 incorporates this document by reference. Not covered by OpenAirDocs’ CC0 dedication.
- Document: [M7 Aerospace Service Bulletin CC7-27-026](https://openairdocs.org/service-documents/m7-aerospace/cc7-27-026.md)
- Title as filed: U.S. DOT/FAA - CC7 SB 27-026 R2 (10-23-13)
- Pages: 16
- PDF: https://openairdocs.org/files/sha256/59/c0/59c08dee7cc9f77dd9f5c4e619ecaa8cca0814758f2d230f77dbb5716ad447a1
- Page: https://openairdocs.org/service-documents/m7-aerospace/cc7-27-026/file/59c08dee7cc9

## Text

Each page's text from the PDF; open the PDF at a page with #page=N.

### Page 1

P.O. Box 790490 • San Antonio, Texas 78279–0490 • (210) 824–9421
TO: HOLDERS OF SA227 COMMUTER CATEGORY SERVICE INFORMATION
MANUALS
Attached is Revision 2 of SA227 Commuter Category Service Bulletin CC7-27-026,
Inspection and Lubrication of the Aileron Control Cable Chain in the Pilot's and
Copilot's Control Columns , Issued: June 06, 2013, Revised: October 23, 2013..
Revision 2 revises step 1.D. Compliance, steps 1.D.(1)(a) and (b),  1.D.(2), 1.D.(2)(a).
It also revisessteps 1.D.(3) and 1.D.(3)(a). Step 1.D.(3)(d)1) is revised to include "not
to exceed 24 calendar months from the date of this bulletin" statement.  It also revises
step 1.D.(4) and adds 1.D.(4)(a). It revises step 1.D.(5)(a). It adds step 1.D.(6). It
revises Notes 1 and 2 and adds Note 3 in step 1.D.  It revises steps 2.A.(4), 2.A.(5),
and 2.A.(6)(b). Corrects issue date to June 6, 2013.
Please insert the attached revised Chapter 27 Index pages.

### Page 2

P.O. Box 790490 • San Antonio, Texas 78279–0490 • (210) 824–9421

### Page 3

CHAPTER 27–FLIGHT CONTROLS
Issued: May 19, 1994 CHAPTER 27 INDEX
Page 3 of 4
NUMBER DATE TITLE AIRCRAFT EFFECTIVITY
SA227 SERIES
COMMUTER CATEGORY
27-021 Not Issued
27-022 Not Issued
27-023 09-19-08 Gravel Guard Installation All SA227 Commuter
Category Airplanes
27-024 06-10-11 Inspection and Repair / All SA227 Commuter
(R) 09-06-11 Replacement of Pitch Trim Category Airplanes
(R) 10-14-11 Actuator Fuselage Fittings
27-025 05-17-11 SAS Power Advance Indicator All SA227 Commuter
Lights Modification Category Airplanes
27-026 06-06-13 Inspection and Lubrication of All SA227 Commuter
(R) 09-30-13 Aileron Control Cable Chain in Category Airplanes
(R) 10-23-13 the Pilot's and Copilot's Control
Columns
Revised:  October 23, 2013

### Page 4

CHAPTER 27 INDEX
Page 4 of 4
Issued: May 19, 1994
CHAPTER 27 – FLIGHT CONTROLS
NUMBER DATE TITLE AIRCRAFT EFFECTIVITY
SA227 SERIES
COMMUTER CATEGORY
INTENTIONALLY LEFT BLANK
Revised:  June 10, 2011

### Page 5

Issued: June  6, 2013
Revised: October 23, 2013
CC7-27-026 R2
Page 1 of 9
SERVICE BULLETIN
SA227 SERIES
COMMUTER CATEGORY
Flight Controls
Lubrication of the Aileron Control Cable Chain in the Pilot's and Copilot's Control
Columns
1. PLANNING INFORMATION
A. Effectivity:
All SA227-CC/-DC Airplanes
B. Reason:
An operator has reported an incident where the ailerons became jammed in flight due
to the aileron control cable chain climbing back on itself and jamming within the control
column housing. There was no report of stiffness or difficulty in the controls by the pilot
prior to this incident. The chains had never been replaced by the operator since
manufacture.
Revision 2 revises step 1.D. Compliance, steps 1.D.(1)(a) and (b),  1.D.(2), 1.D.(2)(a).
It also revisessteps 1.D.(3) and 1.D.(3)(a). Step 1.D.(3)(d)1) is revised to include "not
to exceed 24 calendar months from the date of this bulletin" statement.  It also revises
step 1.D.(4) and adds 1.D.(4)(a). It revises step 1.D.(5)(a). It adds step 1.D.(6). It
revises Notes 1 and 2 and adds Note 3 in step 1.D.  It revises steps 2.A.(4), 2.A.(5),
and 2.A.(6)(b). Corrects issue date to June 6, 2013.
C. Description:
Inspect the pilot's and copilot's aileron control cable chains in the control columns for
defective condition or wear. Replace the bearings and chain sprocket inside each
control column. Ensure the instructions for chain/sprocket lubrication during replace-
ment is performed to prevent jamming.
D. Compliance:
Mandatory
Comply with this service bulletin within the compliance times specified unless already
done.
(1) For aircraft that have records showing replacement of the control column chains and
lubrication(using the correct lubricant per Table 1) at installation, perform the follow-
ing:
(a) Replace and lubricate the chain, sprocket, and bearings by 10,000 hours or 13
years, from the date of the last chain replacement, or within the next 24 months
from the date of of this service bulletin, whichever occurs later.

### Page 6

Issued: June  6, 2013
Revised: October 23, 2013
CC7-27-026 R2
Page 2 of 9
SERVICE BULLETIN
SA227 SERIES
COMMUTER CATEGORY
NOTE: The 27-71026-001 aileron control chain is usually sold as part of the aileron
control cable assembly. Replacement of this control cable assembly (includ
ing the chain) complies with the chain replacement requirement of this
service bulletin.
(b) Check aileron control cable tension at the same time as step 1.D.(1)(a).
(2) For aircraft that have records showing the chains were replaced within the last 10,000
hours, but does NOT indicate if they were lubricated, perform the following:
(a) Comply with step 1.D.(3)(a), (b), and (c) by 10,000 hours aircraft time since last
chain replacement or within the next 1,000 hours, whichever occurs later, but not
to exceed 24 calendar months from the date of this bulletin.
(3) For aircraft that have no records showing replacement of the control column chains
within the last 10,000 hours, perform the following:
(a) Replace and lubricate the control chain during installation in each  control
column. This can be coordinated with aileron control cable replacement if
desired.
(b) Replace the sprocket and two bearings (see Table 1) in each control column.
(c) Check aileron control cable tension.
(d) Comply with (a) and (b) within the following schedule:
1) For aircraft with less than 10,000 hours Total Aircraft Time (TAT), perform
by 10,000 hours or within the next 1,000 hours, whichever occurs later, not
to exceed 24 calendar months from the date of this bulletin.
2) For aircraft with 10,000  - 20,000 hours TAT, perform within the next 1,000
hours or 12 calendar months, whichever occurs first, from the date of this
service bulletin.
3) For aircraft with 20,001  - 30,000 hours TAT, perform within the next 750
hours  or 6 calendar months, whichever occurs first, from the date of this
service bulletin.
4) For aircraft with 30,001  hours TAT or more, perform within the next 400
hours  or 3 calendar months, whichever occurs first, from the date of this
service bulletin.
(4) Repetitive Replacement:
On a repetitive basis, perform replacement per step 1.D.(4)(a). Ensure the chain is
lubricated during installation. The 27-71026-001 aileron control chain is usually sold
as part of the aileron control cable assembly. Replacement of this control cable
assembly (including the chain) complies with the chain replacement requirement of
this service bulletin. See step 2.
(a) Replace and lubricate the chain, sprocket, and bearings by 10,000 hours or 13
years from the date of the last chain replacement, whichever occurs first. Check
aileron control cable tension.
(5) For aircraft that are choosing to follow the inspection option of the ST-UN-M003
Airframe Airworthiness Limitations Manual (see ATA 27-00, item 10-1), which has an

### Page 7

Issued: June  6, 2013
Revised: October 23, 2013
CC7-27-026 R2
Page 3 of 9
SERVICE BULLETIN
SA227 SERIES
COMMUTER CATEGORY
initial inspection of 10,000 hours and a repeat inspection of 400 hours, the action with
regards to the control column chain is hereby clarified:
(a) The control column chain, sprocket, and bearings shall be  replaced following the
repeat requirements of step 1.D.(4)(a). See step 1.D.(3) for compliance of initial
replacement. The chain/sprocket must be lubricated and the aileron control
cable tension should be checked.
(b) The ST-UN-M003 item remains in effect, with the owner/operator choosing to
continue to inspect, or replace the cables (NOT including the control column
chains).
(6) See step 2 for accomplishment instructions
NOTE:
1. It is permissible to perform the repeat replacement prior to the 10,000 hours (13
calendar years) to align the repeat action with other maintenance schedules of the
operators.
2. The repeat replacement of the chains is currently implied as a requirement of the
ST-UN-M003 Airframe Airworthiness Limitations Manual. However, the require-
ment is placed against the aileron control cable assembly. This service bulletin
clarifies that this aileron control cable assembly INCLUDES the aileron control
column chain. This bulletin states that the chain, sprocket, and bearings must be
replaced every 10,000 hours with additional calendar time requirements as
defined by step 1.D.(4).
3. Aircraft that have already complied with this bulletin at an earlier revision do not
have to repeat the initial action outlined in steps 1.D.(1) thru 1.D.(3). They may
proceed with repeat replacement per step 1.D.(4).
E. Approval:
FAA Approved for Engineering Design.
F. Manpower:
M7 Aerospace estimates 20 manhours to perform the actions of this service bulletin.
This estimate includes time to gain access, perform the inspection, replacement and
lubrication, and re-assembly of both control columns. This estimate is for direct labor
only accomplished by an experienced crew. Adjust the estimate with operator task hour
data if necessary.
G. Material - Cost and Availability
Contact M7 Aerospace Spares/Sales Department for Cost and Availability. See
Table 1.

### Page 8

Issued: June  6, 2013
Revised: October 23, 2013
CC7-27-026 R2
Page 4 of 9
SERVICE BULLETIN
SA227 SERIES
COMMUTER CATEGORY
H. Tooling-Price and Availability:
No special tooling is required.
I . Weight and Balance:
None
NOTE: It is recommended the aircraft operating weight be re-established after incorpo-
rating 20 service bulletins classified as having negligible impact on aircraft weight
and balance. This recommendation is derived from data provided in FAA
Advisory Circular 120-27.
J. Reference:
SA227 Commuter Category Maintenance Manual.
ST-UN-M003 Airframe Airworthiness Limitations Manual.
M-5585 - M7 Aerospace Memorandum Aileron Control Chain Service Difficulty Report
(SDR).
NOTE: References are for manufacturers’ use only.
K. Other Publications Affected:
SA227 Commuter Category Maintenance Manual, Chapters 05-10-00, 12-20-10, and
 27-10-10.
SA227 Commuter Category Illustrated Parts Catalog, Chapter 27-10-40.
SA227 Commuter Category Phase Inspection Manual, Form 603.
SA227 Commuter Category Letter Check Inspection Manual, Letter Check B, Flight
 Compartment Items 23.
ST-UN-M003 Airframe Airworthiness Limitations Manual, Figure Item 10-1.
2. ACCOMPLISHMENT INSTRUCTIONS
A. For replacement of any or all chain, sprocket, and bearings; perform the following:
Gain access to pilot's and copilot's control columns in the cockpit by removing any floor
panels, kick panels, and control column boots as required. Refer to SA227 Commuter
Category Illustrated Parts Catalog (IPC), Chapter 25-10-20, Figure 1 for cockpit
upholstery details, and Chapter 53-30-30, Figure 1 for floorboard details. Retain all
hardware for reinstallation of same.
(1) Remove access panels on each control column vertical post to access the chain (27-
71026-001) if required. Retain hardware for reinstallation.
(2) Remove the lower access panel on the pilot's side control column only (which gives
access to the cable turnbuckle). Refer to SA227 Commuter Category Illustrated Parts
Catalog (IPC), Chapter 27-10-40, Figure 2 for details. Retain all hardware.
(3) Follow the guidelines per SA227 Commuter Category Maintenance Manual, Chapter
27-10-10, for control wheel disassembly (ref SA227 Illustrated Parts Catalog for

### Page 9

Issued: June  6, 2013
Revised: October 23, 2013
CC7-27-026 R2
Page 5 of 9
SERVICE BULLETIN
SA227 SERIES
COMMUTER CATEGORY
details of control wheel). This gives access to the chain (27-71026-001), sprocket ,
and bearings on the control wheel.
(a) The February 1987 FACTS article contained some helpful advice for removal
of the control wheel assembly which is reprinted here.
The process of removing the control wheel assembly is complicated because
removal is hampered by interference of electrical wiring. A modified tool for
breaking loose the control wheel nut is made by making a cutout on a special
1-1/4 inch socket as shown in Figure 1 below. This tool will clear all wiring at the
control wheel nut and save precious time while, at the same time, protecting the
wiring from damage.
(4) Replace the sprocket and bearings with those contained in Kit 26K71004-001 per
Table 1 in the Materials Listing (step 3.). The bearings are located in the front and rear
supports (26-71009-003) in the control wheel assembly. Visually inspect the removed
sprocket and the existing chain with 10X magnification and good light for chips,
gouges, damaged rollers, missing teeth, peeling metal, and signs of abnormal wear.
(5) Replace the chain.
(6) Lubricate control wheel chain with Table 1 lubricant (by hand) per SA227 Commuter
Category Maintenance Manual, Chapter 12-20-10. Note the following points (a) thru
(c).
(a) The current Maintenance Manual instructions apply a Corrosion Preventative
(CP) as well as a lubricant. This reference to the CP will be removed from
Chapter 27-00-00 at a later date. Until the Maintenance Manual is revised, the
instructions for lubrication shall follow this bulletin and NOT apply the CP to the
chain.
NOTE: The CP IS applicable to the cable.
(b) When the aircraft was delivered from the factory, or new chains are supplied
from the factory, the CP was/is installed. The chain must be cleaned to remove
the CP prior to the application of the lubricant. Clean the chain with a degreasing
solvent per MIL-PRF-680 or equivalent.
CAUTION:   SEVERAL OF THE TYPE OF SOLVENTS PER THIS SPECIFICATION
  ARE FLAMMABLE (E.G. MINERAL SPIRITS) AND CAUTIONS SHALL
  BE TAKEN AS APPLICABLE.
(c) Once the chain has been cleaned and dried, the lubricant can be added. Ensure
the lubricant is added adequately to cover the length of the chain. Work the
lubricant into the chain by exercising the chain by hand.
(7) Ensure all other parts of the control wheel assembly are fit for service. (See Figure 2
for parts)
(8) Restore the control wheel assembly to operating condition per SA227 Commuter
Category Maintenance Manual, Chapter 27-10-10.
(9) Reinstall all access panels on the control column removed in steps 2.A.(1) and 2.A.(2).

### Page 10

Issued: June  6, 2013
Revised: October 23, 2013
CC7-27-026 R2
Page 6 of 9
SERVICE BULLETIN
SA227 SERIES
COMMUTER CATEGORY
(10) Perform aileron control cable tension and rigging checks per SA227 Commuter
Category Maintenance Manual, Chapter 27-00-00.
(11) Reinstall all components, structure, and hardware per applicable sections of the
SA227 Commuter Category Maintenance Manual.
(12) Complete aircraft records in accordance with 14 CFR 43.9.
(13) Complete and mail service bulletin Compliance Form to M7 Aerospace Technical
Publications Department. Email: MetroTech@M7Aerospace.com. Fax: 210-820-
8626.
3. MATERIAL LISTING
TABLE 1
Notes:
*   Chain is usually sold as part of the aileron control cable assembly. However, this bulletin
     requests this specific chain be replaced.
**  The bearing contained in the kit is the replacement for KP16B bearing. KP16B bearing still
valid to use as replacement.
(Continued next page)
n o i t p i r c s eDr e b m u N t r aPy t i t n a u Q
* n i a hC1 0 0 - 6 2 0 1 7 - 721
* * t i K g n i r a e B d n a t e k c o r pS1 0 0 - 4 0 0 1 7 K 621
t n a c i r b uL* * * 2 2 3 1 8 - F R P - L IMR / A
t n e v l o S g n i s a e r g eD* * * * 0 8 6 - F R P - L IMR / A
: l a n o i t p o e r a s t r a p g n i w o l l o f e h T
r a e R d n a t n o r F , t r o p p uS3 0 0 - 9 0 0 1 7 - 622
‡ r e c a p S l l a mS5 9 0 - 4 0 0 1 7 - 62R / A

### Page 11

Issued: June  6, 2013
Revised: October 23, 2013
CC7-27-026 R2
Page 7 of 9
SERVICE BULLETIN
SA227 SERIES
COMMUTER CATEGORY
*** MIL-PRF-81322 supercedes MIL-G-81322 however, MIL-G-81322 is still a valid grease to
use in this application. This is a specification. Multiple products meet this specifica-
tion.
****A degreasing solvent meeting the requirements of MIL-PRF-680 is suggested to be used
to remove the Corrosion Preventative compound from the chain. Equivalent alternatives
are permitted to remove this compound. Follow the solvents MSDS sheet for usage.
‡ Spacer, P/N 26-71004-025 ia a 0.090 inch thick spacer installed in earlier control column
assemblies. This spacer was replaced by a 0.016 inch thick spacer, P/N 26-71004-095.
This change was incorporated to provide improved adjustment of the control wheel
assembly. The 26-71004-095 is sold in quantities of ten to ensure sufficient quantities are
available at reassembly of the control wheel assembly. Each control wheel assembly (left
hand or right hand) may require up to ten P/N 26-71004-095 spacers. Refer to step 2.A.(8)
for instructions.
TABLE 1 NOTES (Continued)

### Page 12

Issued: June  6, 2013
Revised: October 23, 2013
CC7-27-026 R2
Page 8 of 9
SERVICE BULLETIN
SA227 SERIES
COMMUTER CATEGORY
FIGURE 1
REMOVE
MATERIAL1.10
1.00
MODIFIED
1 1/4” 12-POINT SOCKET

### Page 13

Issued: June  6, 2013
Revised: October 23, 2013
CC7-27-026 R2
Page 9 of 9
SERVICE BULLETIN
SA227 SERIES
COMMUTER CATEGORY
6M271001201
FWD
A
A
BEARING
REAR SUPPORT
SPACER (P/N 26-71007-003)
SHAFT
WOODRUFF
KEY
RETAINING
NUT
CONTROL WHEEL
BEARING FRONT
SUPPORT
SPACER (P/N 26-71007-001)
SPACERS A/R (P/N 26-71004-095);
   UP TO 10 REQUIRED
CHAIN AND
SPROCKET WOODRUFF
KEY SLOT
CONTROL COLUMN
KEEPER
CABLE
MASTER
LINK
FIGURE 2
CONTROL WHEEL ASSEMBLY

### Page 14

P.O. Box 790490 • San Antonio, Texas 78279–0490 • (210) 824–9421

### Page 15

SERVICE BULLETIN COMPLIANCE FORM
CC7-27-026 R2
TO: OPERATOR OR SERVICE FACILITY ACCOMPLISHING BULLETIN
Please complete this compliance form, and  mail according to the instructions on the
reverse side.
Thank you for returning this form.
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Aircraft Model Aircraft Serial Number
Bulletin Issue Date Revision Date
Aircraft Registration Number
Operator/Owner
Time on Aircraft
Date Accomplished
Comments

### Page 16

M7 AEROSPACE  LP
P. O. BOX 790490
SAN ANTONIO, TEXAS 78279–0490
(Staple)
ATTN: Technical Publications Department
Fold  Here to Mail
Fold  Here to Mail
Place
Stamp
Here

---
OpenAirDocs.org is an independent research project of [Contrail Labs](https://contraillabs.com/). It is not affiliated with the FAA or the NTSB. Source documents are U.S. government works in the public domain, except the copies of manufacturers’ service documents, which belong to their rights holders.