Appendix 7 installed after December 20, 2010, that have not previously had DTE performed and DTI implemented, develop and implement DT Data as follows:

(a) If the time on the component (in flight cycles or flight hours) is known, or can be conservatively assigned, perform the following:

1 Survey the component,

2 Disposition the repairs and alterations,

3 Implement any DTI in accordance with the schedule in Chapter 2 or 3 of this AC, using the component’s age, and

4 Accomplish the initial inspection using the actual age of the repairs or alterations, or total number of flight cycles or flight hours, if known. If the age of the repairs or alterations is not known, use the component age.

Repeat the inspection at the intervals given for the repairs or alterations against the component.

(b) If the time on the component (in flight cycles or flight hours) is unknown and cannot be conservatively assigned, perform the initial repair or alteration assessment of the affected component prior to installation, and take the following actions:

1 Develop the DT Data per the process given in Chapter 2 or 3 of this AC, as applicable.

2 Incorporate any DTI into the maintenance program.

3 Accomplish the first inspection on the affected component at the next C-check (or equivalent interval) following the repair or alteration assessment.

4 Repeat the inspection at the intervals given for the repair or alteration against the component.

(3) New Repairs and Alterations. New repairs and alterations to affected removable structural components installed after December 20, 2010, must have a DTE performed and DTIs implemented according to an approved process. For repairs, that process is described in Appendix 5 of this AC. Perform the initial and repetitive inspections at the intervals given for the repair or alteration against the component.

d. Implementation Options to Help Reduce Tracking Burden. The following implementation techniques may be used to alleviate some of the burdens associated with tracking repairs to affected removable structural components. These techniques, if used, would need to be included in the OIP and may require additional FAA approval and TC or STC Holder input for DTIs.

A7-3

Appendix 7

(1) Upgrading Existing Repairs.

(a) As an option, existing repairs may be removed and replaced to zero time the DTI requirements of the repair and establish an initial tracking point for the repair.

Normally, this would be done at or before the survey for maximum benefit. The initial and repetitive inspections for the upgraded repair would then be accomplished at the intervals given for the repair against the component.

(b) A repair could also be upgraded to one whose inspection requirements and methods are already fulfilled by a part 121 or part 129 operator’s maintenance or inspection program (see paragraph 406 of this AC). That repair would then be repetitively inspected at each routine inspection interval applicable to the repair.

Specific tracking would not be required because that area of the airplane would already be normally inspected on each airplane in the fleet as part of the existing approved maintenance program. If the operator’s program intervals were changed, the effect on requirements for specific tracking would have to be re-evaluated.

(2) Special Initial and/or Routine Inspections.

(a) As an option, existing repairs may have special initial inspections accomplished during the component survey. This initial inspection establishes an initial tracking point for the repair. Following this initial inspection, the DTI requirements (e.g., repetitive inspections) of the repair would be implemented.

(b) In addition, special routine inspections could be defined for typical repairs that could be applied at a normal interval. In this case, an operator could check the affected components on each airplane for this type of a repair at the defined interval. If the repair was found, the special inspection would be applied to ensure its airworthiness until the next scheduled check. This alleviates the need to specifically track affected components for every repair, especially typical ones.

(c) The development of inspection processes, methods, applicability and intervals would most likely require the assistance of the TC or STC Holder for the FCS in question. In all circumstances, the data must be approved by the FAA Oversight Office.

A7-4

Appendix 8 APPENDIX 8. PROGRAM IMPLEMENTATION EXAMPLES

The following are provided to assist the operator in understanding the timeline for when the program should be implemented. Two examples are given, one covers airplanes below 75 percent of the design service goal (DSG) on December 18, 2009, and the other is for airplanes beyond the DSG on December 18, 2009.

a. Airplane Below 75 Percent of the DSG on December 18, 2009. Operators should complete a survey at the first heavy maintenance check (time limit equivalent to a “D-check”) after the airplanes reach 75 percent of the DSG, and not to exceed the DSG.

Consider the following:

(1) Airplane Total Flight Cycles on December 18, 2009, – 55,000

(2) DSG = 75,000 Cycles, 75percent DSG – 56,250 Flight Cycles

(3) Time of last “D”-Check Equivalent – 53,000 Flight Cycles

(4) 8-Year “D”-Check Equivalent – 365 Days/Year, 4 cycles/day = 11,680 Flight Cycles

The survey would be performed after the airplane has reached 56,250 total flight cycles (75% DSG) and would be due before the airplane has accumulated 11,680 flight cycles (D- check equivalent) beyond the time of the last D-check (53,000 flight cycles). Therefore, the survey would be due before the airplane has reached 64,680 total flight cycles, but in any case would be required before the airplane has reached 75,000 total flight cycles (DSG).

b. Airplane Beyond the DSG on December 18, 2009. Operators complete a survey of these airplanes at or before the next heavy maintenance check (equivalent to a D-check) after December 20, 2010, not to exceed 6 years.

Consider the following:

(1) Airplane Total Flight Cycles on December 18, 2009, – 80,000

(2) DSG = 75,000 Cycles, 75percent DSG – 56,250 Flight Cycles

(3) Time of last “D”-Check Equivalent – 78,540 Flight Cycles, conducted in Jan 2009

(4) 8-Year “D”-Check Equivalent – 365 Days/Year, 4 cycles/day = 11,680 Flight Cycles

(5) Assume maximum total flight cycles accumulated by December 20, 2010, to be 81,460 (80,000 flight cycles on 12/18/2009 + 1,460 flight cycles/year).

Consider an airplane that has 80,000 total flight cycles as of December 18, 2009, and a DSG of 75,000 total flight cycles. The airplane is currently on an 8-year D-check equivalent and the last D-check was performed in January 2009 at 78,540 total flight cycles. The survey would need to be performed prior to the airplane accumulating 11,680 flight cycles (D-check equivalent) beyond the time of the last D-check (78,540 flight cycles) or 6 years,

whichever occurs first. Therefore, the survey would be due before the airplane has reached 90,220 total flight cycles or 6 years, whichever occurs first, based on the airplane utilization

A8-1

Appendix 8 of 4 cycles/day, a 365-day year, and a maximum total of 81,460 flight cycles as of December 20, 2010.

A8-2

Appendix 9

APPENDIX 9. LIST OF SIGNIFICANT ALTERATIONS THAT MAY

ADVERSELY AFFECT FATIGUE CRITICAL STRUCTURE

1. Passenger-to-freighter conversions (including addition of main deck cargo doors).

2. Gross weight increases (increased operating weights, increased zero fuel weights, increased landing weights, and increased maximum takeoff weights).

3. Installation of fuselage cutouts (passenger entry doors, emergency exit doors or crew escape hatches, fuselage access doors, and cabin window relocations).

4. Complete re-engine or pylon alterations.

5. Engine hush-kits.

6. Wing alterations such as installing winglets or changes in flight control settings (flap droop), and alteration of wing trailing edge structure.

7. Modified skin splices.

8. Antenna Installations.

9. Any alteration that affects several stringer or frame bays.

10. An alteration that covers structure requiring periodic inspection by the operator’s maintenance program.

11. An alteration that results in operational mission change that significantly changes the manufacturer’s load or stress spectrum (e.g., passenger-to-freighter conversion). Examples of this type of alteration may be an alteration that adds new structural splices, or increases the operational loads causing existing structure to become fatigue critical.

12. An alteration that changes areas of the fuselage which prevents external visual inspections (for example, the installation of a large external fuselage doubler that results in hiding details beneath it).

13. In general, attachment of interior monuments to fatigue critical structure. Interior monuments include large items of mass such as galleys, closets, and lavatories.

A9-1