AC 90-114B

Change 1Historical

Advisory circular · Automatic Dependent Surveillance-Broadcast Operations

A newer version is currentThis is a historical version. AC 90-114C is the version in force, approved January 14, 2025.
Approved
December 15, 2022
Last reviewed
July 29, 2024
This change
Change 1 of AC 90-114B.
Cancels
AC90-114B
Family
AC 90-114 · 7 versions
Revision
B, change 1
14 CFR parts
91
14 CFR sections
§ 91.225§ 91.227

Guidance, not mandatory unless a rule or AD requires it. DRS record last changed November 21, 2025.

Show pages 60–71

Appendix F F.8.1 IM Outside the U.S. NAS. In the future, ANSPs outside the United St ates may conduct IM. Before conducting IM operations outside the U.S. NAS, determine whether the destination ANSP provides IM services that are compliant with existing ICAO guidance.

F.8.2 Flight Plan Codes. Cur rently there are no specific flight plan equipment capability codes for IM, only codes that indicate installed ADS-B Out and ADS-B In equipment.

However, in the future there will be codes published in ICAO and FAA guidance that indicate a number of ADS-B In capabilities and flightcrew authorizations. Refer to the Aeronautical Information Manual (AIM), Chapter 5, Air Traffic Procedures, for instructions on filing ADS-B equipment codes.

F.9 Authorization to Conduct IM. FAA authorization is required for all U.S. aircraft operators to conduct IM operations using ADS-B In (14 CFR part 119, § 119.49(a)(5)).

For FAA authorization, refer to FAA Order 8900.1, Volume 3, Chapter 18, Section 3, Operations Specification (OpSpec)/Management Specification (MSpec)/Letter of Authorization (LOA) A355, Automatic Dependent Surveillance-Broadcast (ADS-B) In Operations.

F.9.1 Initial Request for Authorization. U. S. aircraft operators seeking to conduct IM should first contact their assigned FAA office to indicate their intent. At the time of the operator’s initial request, the FAA will provide the operator with an IM Application Checklist, which should be completed with attached supporting documents.

F.9.2 Documentation to Submit With Formal Request. T his section describes the documentation to be submitted with a formal IM proposal.

F.9.2.1 Req uest Letter. The operator’s assigned principal inspector (PI) may ask for additional information based on any unique aspects of their specific operation.

The operator should submit a letter of request for issuance of authorization to the assigned PI. The letter may be in a form acceptable to the Administrator

(e.g., as an electronic document entered into the Operations Approval Portal System (OAPS)). The letter of request should include the following information:

• Type of aircraft (make, model, and series (M/M/S)).

• List of aircraft registration numbers (N-number) associated with the request for authorization.

• ADS-B equipment complies with TSO-C195c or later, or as approved for IM by the Administrator.

• Installation was completed following guidance contained in AC 20-165, Airworthiness Approval of Automatic Dependent Surveillance - Broadcast OUT Systems, and AC 20-172, Airworthiness Approval for ADS-B In Systems and Applications, or other acceptable means.

F-12

Appendix F

• Name of the ADS-B In (IM) software manufacturer and applicable software version(s).

• Intended areas of IM operations, listed by ANSP.

F.9.2.2 Airplane Flight Manual (AFM) Compliance Documentation. Operators will submit documentation that demonstrates applicable aircraft have an ADS-B In system that meets the performance standards of TSO-C195c or later, or as otherwise approved by the Administrator, for IM operations.

F.9.2.3 Operation Manuals and Checklists. The certificate holder (CH)/operator/program manager (as applicable) should submit information

(e.g., Airplane Operations Manual (AOM) bulletin or equivalent) to the flightcrews describing ADS-B to include:

• IM system description;

• Normal procedures; and

• Non-normal or contingency procedures.

F.9.2.4 Maintenance Documentation. See Appendix C, ADS-B In Operations— Aircraft Qualification and Maintenance, for applicable maintenance guidance.

F.9.2.5 Re vision of Minimum Equipment List (MEL). See Appendix C for guidance on the necessary MEL documents to be submitted for authorization of IM.

F.9.2.6 Pilot Training. Submit applicable portions of proposed IM-specific pilot training material and include a description of the methods used to conduct, evaluate, and manage the training. The IM pilot training should include:

1. ADS-B Out/In system overview (if not previously addressed with another ADS-B application).

2. ADS-B IM system operations.

3. IM normal procedures:

• Understanding IM clearance types and clearance elements.

• Compliance with IM speed.

• Response to IM alerts.

• Lead aircraft FLT ID verification.

• Crew coordination during IM.

4. IM MEL procedures (as applicable).

5. IM equipment limitations.

F- 13

Appendix F

6. CDTI interface.

7. Contingency procedures.

F.9.2.7 Dispatch/Flight Follower Training. Submit applicable portions of proposed IM-specific dispatch/flight planning training material to include any appropriate updates to the dispatch operations manual, or equivalent, as well as a description of the methods used to conduct, evaluate, and manage training. The training material should include:

1. General understanding of ADS-B In operations.

2. Correct flight planning codes for IM operations, including the aircraft identification. A correct aircraft identification in the flight plan is essential to the IM operation. Before ATC can commence an IM operation, the transmitted FLT ID from the lead aircraft must exactly match that from the flight plan. While filing aircraft identification refers directly to the ADS-B Out aircraft, it can adversely impact an IM operation.

3. Dispatch of aircraft with the FIM system unserviceable.

4. How flight planning codes are affected with ADS-B or FIM avionics unserviceable.

5. Equipment needed to conduct IM.

6. A NSPs and airspace where IM operations are approved.

F-14