AD 2008-04-07

Airworthiness directive · Fuel tank system · Saab AB, Saab Aerosystems SAAB 340B and 340A (SAAB SF340A)

Effective
March 28, 2008
Published
February 22, 2008 · 73 FR 9659–9661
Issued
February 11, 2008
Models
SAAB 340B, 340A (SAAB SF340A)
Data sheet
TCDSA52EU
Registered aircraft
66 matched by model
Product
Aircraft · Large airplane
ATA chapter
28 · Fuel
Amendment
39-15379
Docket
FAA-2007-0333
Project
2007-NM-236-AD
Issued as
Final rule

Unofficial copy from the Federal Register XML, document E8-3068. Only the govinfo PDF is the legal edition. DRS record last changed May 30, 2024.

On this page

Summary

We are adopting a new airworthiness directive (AD) for the products listed above. This AD results from mandatory continuing airworthiness information (MCAI) originated by an aviation authority of another country to identify and correct an unsafe condition on an aviation product. The MCAI describes the unsafe condition as:

Subsequent to accidents involving Fuel Tank System explosions in flight * * * and on ground, the FAA has published Special Federal Aviation Regulation 88 (SFAR88) * * * [which] required * * * [conducting] a design review against explosion risks.

The airworthiness directive

2008-04-07 Saab Aircraft AB: Amendment 39-15379. Docket No. FAA-2007-0333; Directorate Identifier 2007-NM-236-AD.

(a) Effective Date

PDF page 2

(a) This airworthiness directive (AD) becomes effective March 28, 2008.

(b) Affected ADs

PDF page 2

(b) None.

(c) Applicability

PDF page 2

(c) This AD applies to Saab Model SAAB SF340A and SAAB 340B airplanes, all serial numbers, certificated in any category.

(d) Subject

PDF page 2

(d) Air Transport Association (ATA) of America Code 28: Fuel.

(e) Reason

PDF page 2

(e) The mandatory continuing airworthiness information (MCAI) states:

Subsequent to accidents involving Fuel Tank System explosions in flight * * * and on ground, the FAA has published Special Federal Aviation Regulation 88 (SFAR88) in June 2001.

In their Letters referenced 04/00/02/07/01-L296 dated March 4, 2002, and 04/00/02/07/03-L024, dated February 3, 2003, the JAA (Joint Aviation Authorities) recommended the application of a similar regulation to the National Aviation Authorities (NAA).

Under this regulation, all holders of type certificates for passenger transport aircraft with either a passenger capacity of 30 or more, or a payload capacity of 7,500 pounds (3402 kg) or more, which have received their certification since January 1, 1958, are required to conduct a design review against explosion risks.

This Airworthiness Directive, which renders mandatory the modification [3162] to separate wiring of Fuel Quantity Indication System, is a consequence of the design review.

The unsafe condition is the potential of ignition sources inside fuel tanks, which, in combination with flammable fuel vapors, could result in fuel tank explosions and consequent loss of the airplane. Modification 3162 includes parking (stowing) of the existing wiring to the FQIS, installing new wires with shields to the FQIS, and operational and functional tests of the FQIS.

(f) Actions and Compliance

PDF page 2

(f) Within 72 months after the effective date of this AD, unless already done, do modification 3162 in accordance with the Accomplishment Instructions of Saab Service Bulletin 340-28-024, Revision 01, dated May 21, 2007. Actions done before the effective date of this AD in accordance with Saab Service Bulletin 340-28-024, dated February 26, 2007, are considered acceptable for compliance with the requirements of this AD.

FAA AD Differences

PDF page 2

Note 1:

This AD differs from the MCAI and/or service information as follows: No differences.

(g) Other FAA AD Provisions

PDF page 2

(g) The following provisions also apply to this AD:

(1) Alternative Methods of Compliance (AMOCs): The Manager, International Branch, ANM-116, Transport Airplane Directorate, FAA, has the authority to approve AMOCs for this AD, if requested using the procedures found in 14 CFR 39.19. Send information to ATTN: Shahram Daneshmandi, Aerospace Engineer, International Branch, ANM-116, Transport Airplane Directorate, FAA, 1601 Lind Avenue, SW., Renton, Washington 98057-3356; telephone (425) 227-1112; fax (425) 227-1149. Before using any approved AMOC on any airplane to which the AMOC applies, notify your appropriate principal inspector (PI) in the FAA Flight Standards District Office (FSDO), or lacking a PI, your local FSDO.

(2) Airworthy Product: For any requirement in this AD to obtain corrective actions from a manufacturer or other source, use these actions if they are FAA-approved. Corrective actions are considered FAA-approved if they are approved by the State of Design Authority (or their delegated agent). You are required to assure the product is airworthy before it is returned to service.

(3) Reporting Requirements: For any reporting requirement in this AD, under the provisions of the Paperwork Reduction Act, the Office of Management and Budget (OMB) has approved the information collection requirements and has assigned OMB Control Number 2120-0056.

(h) Related Information

PDF page 3

(h) Refer to MCAI EASA Airworthiness Directive 2007-0170, dated June 15, 2007; and Saab Service Bulletin 340-28-024, Revision 01, dated May 21, 2007; for related information.

(i) Material Incorporated by Reference

PDF page 3

(i) You must use Saab Service Bulletin 340-28-024, Revision 01, dated May 21, 2007, to do the actions required by this AD, unless the AD specifies otherwise.

(1) The Director of the Federal Register approved the incorporation by reference of this service information under 5 U.S.C. 552(a) and 1 CFR part 51.

(2) For service information identified in this AD, contact Saab Aircraft AB, SAAB Aircraft Product Support, S-581.88, Linköping, Sweden.

(3) You may review copies at the FAA, Transport Airplane Directorate, 1601 Lind Avenue SW., Renton, Washington; or at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call (202) 741-6030, or go to: http://www.archives.gov/federal-register/cfr/ibr-locations.html.

Rule preamble

The FAA’s background, reasoning and cost estimate, published with the AD.

DatesPage 1

This AD becomes effective March 28, 2008.

The Director of the Federal Register approved the incorporation by reference of a certain publication listed in this AD as of March 28, 2008.

AddressesPage 1

You may examine the AD docket on the Internet at http://www.regulations.gov or in person at the U.S. Department of Transportation, Docket Operations, M-30, West Building Ground Floor, Room W12-140, 1200 New Jersey Avenue, SE., Washington, DC.

For further information contactPage 1

Shahram Daneshmandi, Aerospace Engineer, International Branch, ANM-116, Transport Airplane Directorate, FAA, 1601 Lind Avenue, SW., Renton, Washington 98057-3356; telephone (425) 227-1112; fax (425) 227-1149.

DiscussionPage 1

We issued a notice of proposed rulemaking (NPRM) to amend 14 CFR part 39 to include an AD that would apply to the specified products. That NPRM was published in the Federal Register on December 17, 2007 (72 FR 71271). That NPRM proposed to correct an unsafe condition for the specified products. The MCAI states:

Subsequent to accidents involving Fuel Tank System explosions in flight * * * and on ground, the FAA has published Special Federal Aviation Regulation 88 (SFAR88) in June 2001.

In their Letters referenced 04/00/02/07/01-L296 dated March 4, 2002 and 04/00/02/07/03-L024, dated February 3, 2003, the JAA (Joint Aviation Authorities) recommended the application of a similar regulation to the National Aviation Authorities (NAA).

Under this regulation, all holders of type certificates for passenger transport aircraft with either a passenger capacity of 30 or more, or a payload capacity of 7,500 pounds (3402 kg) or more, which have received their certification since January 1, 1958, are required to conduct a design review against explosion risks.

This Airworthiness Directive, which renders mandatory the modification [3162] to separate wiring of Fuel Quantity Indication System [FQIS], is a consequence of the design review.

The unsafe condition is the potential of ignition sources inside fuel tanks, which, in combination with flammable fuel vapors, could result in fuel tank explosions and consequent loss of the airplane. Modification 3162 includes parking (stowing) of the existing wiring to the FQIS, installing new wires with shields to the FQIS, and operational and functional tests of the FQIS. You may obtain further information by examining the MCAI in the AD docket.

CommentsPage 1

We gave the public the opportunity to participate in developing this AD. We received no comments on the NPRM or on the determination of the cost to the public.

ConclusionPage 1

We reviewed the available data and determined that air safety and the public interest require adopting the AD as proposed.

Differences Between This AD and the MCAI or Service InformationPage 1

We have reviewed the MCAI and related service information and, in general, agree with their substance. But we might have found it necessary to use different words from those in the MCAI to ensure the AD is clear for U.S. operators and is enforceable. In making these changes, we do not intend to differ substantively from the information provided in the MCAI and related service information.

We might also have required different actions in this AD from those in the MCAI in order to follow our FAA policies. Any such differences are highlighted in a NOTE within the AD.

Costs of CompliancePage 2

We estimate that this AD will affect about 218 products of U.S. registry. We also estimate that it will take about 80 work-hours per product to comply with the basic requirements of this AD. The average labor rate is $80 per work-hour. Required parts will cost about $12,900 per product. Where the service information lists required parts costs that are covered under warranty, we have assumed that there will be no charge for these parts. As we do not control warranty coverage for affected parties, some parties may incur costs higher than estimated here. Based on these figures, we estimate the cost of this AD to the U.S. operators to be $4,207,400, or $19,300 per product.

Authority for This RulemakingPage 2

Title 49 of the United States Code specifies the FAA's authority to issue rules on aviation safety. Subtitle I, section 106, describes the authority of the FAA Administrator. “Subtitle VII: Aviation Programs,” describes in more detail the scope of the Agency's authority.

We are issuing this rulemaking under the authority described in “Subtitle VII, Part A, Subpart III, Section 44701: General requirements.” Under that section, Congress charges the FAA with promoting safe flight of civil aircraft in air commerce by prescribing regulations for practices, methods, and procedures the Administrator finds necessary for safety in air commerce. This regulation is within the scope of that authority because it addresses an unsafe condition that is likely to exist or develop on products identified in this rulemaking action.

Regulatory findingsPage 2

We determined that this AD will not have federalism implications under Executive Order 13132. This AD will not have a substantial direct effect on the States, on the relationship between the national government and the States, or on the distribution of power and responsibilities among the various levels of government.

For the reasons discussed above, I certify this AD:

1. Is not a “significant regulatory action” under Executive Order 12866;

2. Is not a “significant rule” under the DOT Regulatory Policies and Procedures (44 FR 11034, February 26, 1979); and

3. Will not have a significant economic impact, positive or negative, on a substantial number of small entities under the criteria of the Regulatory Flexibility Act.

We prepared a regulatory evaluation of the estimated costs to comply with this AD and placed it in the AD docket.

Examining the AD DocketPage 2

You may examine the AD docket on the Internet at http://www.regulations.gov; or in person at the Docket Operations office between 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays. The AD docket contains the NPRM, the regulatory evaluation, any comments received, and other information. The street address for the Docket Operations office (telephone (800) 647-5527) is in the ADDRESSES section. Comments will be available in the AD docket shortly after receipt.

Adoption of the amendmentPage 2

Accordingly, under the authority delegated to me by the Administrator, the FAA amends 14 CFR part 39 as follows:

1. The authority citation for part 39 continues to read as follows:

2. The FAA amends § 39.13 by adding the following new AD:

Affected TCDS · 1

The type certificate data sheets for the models this AD names, matched by model and maker.

Registered aircraft · 66

Registered aircraft whose airframe or engine model this AD names. Matched by model only, so check each against the AD’s applicability.

By aircraft maker
  • Saab-Scania42 aircraft
  • Saab15 aircraft
  • Saab-Fairchild8 aircraft
  • Saabscania1 aircraft
By year built
19851999
Registered aircraft by year built: 37 aircraft
19852
19871
19891
19908
19913
19923
19934
19941
19961
19975
19987
19991

29 with no year recorded