What was found
DURING D-CHECK, FOUND STATION 400 FLOOR BEAM APPROX RBL 60 HAS HOLE IN TOP CHORD TO CLOSE TO EDGE, BAD E/D. CUT OUT DAMAGE SECTION UPPER CHORD PER SRM 53-108. INSTALLED UPPER FLOOR BEAM REPAIR PER SRM 53-10-8 3 INCH BY 8 INCH.
As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.
DURING D-CHECK, FOUND STATION 400 FLOOR BEAM APPROX RBL 60 HAS HOLE IN TOP CHORD TO CLOSE TO EDGE, BAD E/D. CUT OUT DAMAGE SECTION UPPER CHORD PER SRM 53-108. INSTALLED UPPER FLOOR BEAM REPAIR PER SRM 53-10-8 3 INCH BY 8 INCH.