What was found
TUL - FOUND 3 GROUND LUGS CORRODED, 3RD STIFFENER INBOARD OF TANK 2 FUEL DUMP VALVE. BLENDED AREA TO REMOVE CORROSION. INSTALLED L-ANGLE 13 INCHES LONG, INSIDE OF FORWARD FLANGE ON Z-ANGLE STIFFENER PER AARD 51-40-00-1. (M)
As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.
TUL - FOUND 3 GROUND LUGS CORRODED, 3RD STIFFENER INBOARD OF TANK 2 FUEL DUMP VALVE. BLENDED AREA TO REMOVE CORROSION. INSTALLED L-ANGLE 13 INCHES LONG, INSIDE OF FORWARD FLANGE ON Z-ANGLE STIFFENER PER AARD 51-40-00-1. (M)