Service difficulty report · Lever · Airbus A300*

Difficulty date
January 2, 2022
Submitted
January 4, 2022
Operation
Air carrier
Aircraft
N919US
Make and model
Airbus A300*
Aircraft serial
6479
Aircraft time
21,583 hours, 8,518 cycles
Part
Lever
Part number
210TS07Y01
Part serial
2059
Condition
Defective
Location
Zone 200 - Fuse
Part time
76,646 hours, 28,961 cycles
Stage of operation
AP
How discovered
V
Nature of condition
J
Precautionary procedure
O

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

AIRCRAFT WAS GROUNDED: DURING APPROACH LGCIU (LAND GEAR CONTROL AND INTERFACE UNIT) #1 AND #2 FAILURE FAULTS LGCIU 1 & 2 FAULT. CREW LOWERED THE GEAR MANUALLY AND LANDED SAFELY WITHOUT FURTHER INCIDENT. **SUPPLEMENTAL REPORT FOR AALA202201039762: REPLACED LANDING GEAR CONTROL LEVER ASSEMBLY AND ACCOMPLISHED A SATISFACTORY OPERATIONAL CHECK PER AMM 32-31-11-000-001-A.** (CLOSED)