Service difficulty report · Pump · Airbus A319132

Difficulty date
March 12, 2019
Submitted
April 8, 2019
Operation
Air carrier
Aircraft
N730AV
Make and model
Airbus A319132
Aircraft serial
6132
Part
Pump
Part number
974540
Part serial
G1440061
Condition
Abnormal
Location
3075gx
Part time
16,880 hours
Stage of operation
CR
How discovered
O
Nature of condition
J
Precautionary procedure
O

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

OVERHEAT HYD YELLOW - DURING APP AT SKPE, HOLDING PEI VOR WITH FLAPS 2,HYD Y RESERVOIR OVHT,PROCEEDED TO SKCL AS ALT. IN ACCORDANCE WITH AMM 29-23-41-000-001-A/400-001-A THE GREEN/YELLOW POWER TRANSFER UNIT WAS REPLACED. IN ACCORDANCE WITH AMM 29-24-21-000-001-A/400-001-A THE YELLOW E PUMP CHECK V/V WAS REPLACED, IAW TSM 29-13-00-810-819-A YELLOW HYDRAULIC SYSTEM LOW PRESSURE/OVERHEAT CAUSED BY USER SYSTEM FAULT WAS PERFORMED, NO FOUND FAULT. IN ACCORDANCE WITH SUBTASK 29-23-41-870-051-C BLEEDING PROCEDURE OF THE PTU WITH THE LEFT ENG PUM AND THE ELECTRICAL PUMP OF YELLOW HYD SYSTEM WAS PERFORMED SATISFACTORY AND AMM SUBTASK 29-24-21-710-050-A TEST OF THE YELLOW E-PUMP CHECK VALVE WAS PERFORMED SATISFACTORY. IN ACCORDANCE WITH AMM 29-00-00-280-003-A, THE CHECK OF THE INTERNAL LEAKAGE OF THE YELLOW HYD SYST WERE PERFORMED. IN ACCORDANCE WITH TSM 29-13-00-810-802-A, THE OVERHEAT INDICATION OF THE YELLOW HYDRAULIC SYSTEM WERE PERFORMED SATISFACTORY. IN ACCORDANCE WITH AMM 29-24-51 PB 401 CONF.00, PUMP ELECTRIC Y WAS REPLACED, PENDING TEST. IAW AMM 29-13-44 PB401 FILTER LP WAS REMOVED AND INSPECTED AND NO FOUND DEBRIS AND INSTALLED NEW ONE. IAW AMM 29-13-45-610-001-A STEP4.A. FILTER HP WAS REMOVED AND NO FOUND DEBRIS. IN ACCORDANCE WITH AMM 29-13--44-610-001-A SERVICING OF THE LP FILTER WAS ACCOMPLISHED AND AMM 29-13-45-610-001-A SERVICING OF THE HP FILTER WAS ACCOMPLISHED. AND AMM 29-14-00-614-002 HYDRAULIC RESERVOIR YELLOW AND BLUE. GREEN WERE ACCOMPLISHED. AND AMM 29-10-00-864-002-A SERVICING THE YELLOW AND BLUE HYDRAULIC SYSTEM WERE ACCOMPLISHED. BY W/O 2181822 REPLACE PUMP ELEC YELLOW- PERFORM HYD SYS UPSTREAM BLEEDING PROCEDURE. IN ACCORDANCE WITH AMM 29-00-00-870-006A THE BLEEDING PROCEDURE OF THE YELLOW HYD SYSTEM UPSTREAMOF THE YELLOW EPUMP WA PERFORMED SATISFACTORY. YELLOW HP FILTER CHECK SATISFACTORY. IN ACCORDANCE WITH AMM 29-24-21-000-001-A/400-001-A THE YELLOW E PUMP CHECK V/V WAS REPLACED, IN ACCORANCE WITH AMM 71-00-00-710-042-A NORMAL ENGINE AUTOMATIC START PROCEDURE WERE PERFORMED. IN AACORDANCE WITH AMM27-54-60-710-002-A AND AMM 27-14-00-710-001-A/AMM 27-24-00-710-001-A. F/CTL SURFACES MOVES BY 30 MIN. NO FAULT HYD Y RES. OVHT. IN ACCORANCE WITH AMM 71-00-00-710-042-A NORMAL ENGINE AUTOMATIC START PROCEDURE WERE PERFORMED. IN ACCORDANCE WITH AMM 27-54-60-710-002-A AND AMM 27-14-00-710-001-A. AMM 27-24-00-710-001-A. F/CTL SURFACES MOVES BY 30 MIN. NO FAULT HYD Y RES. OVHT.

More about the Airbus A319-132