Service difficulty report · Probe · Boeing 737890

Difficulty date
August 5, 2017
Submitted
August 7, 2017
Operation
Air carrier
Aircraft
N530AS
Make and model
Boeing 737890
Aircraft serial
36578
Aircraft time
28,592 hours, 8,519 cycles
Engine
Cfmint CFM567B27
Part
Probe
Part number
TC29603
Condition
No Test
Location
Nr 2 Engine
Stage of operation
IN
How discovered
C
Nature of condition
L
Precautionary procedure
K

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

NR 2 ENGINE MAX POWER ASSURANCE EGT INDICATION IS HIGH AT 65% N1. INDICATION ERROR IS SUSPECTED: S1 = 535, S2 = 558, S3 = 697, S4 = 545. ACFT GROUNDED. INITIAL EVAL UPON RETURN TO HANGAR: T495 = 126.91, S1-113.05, S2-88.53, S3-195.05, S4-109.14. ACCOMPLISHED EGT CLEANING IAW AMM 77-21-00-140-801. VISUAL INSPECTION OK, POST CLEANING RESULTS: T495 = 37.96 , S1- 44.87, S2- 31.03, S3- 31.09, S4- 44.79, EEC TEST PASSED. ALSO ACCOMPLISHED T49.5 PROBE AND EGT SYSTEM INSPECTION IAW AMM 77-21-01-200-801, CJ9 CONNECTOR DP0911 S2 PINS 9 TO GROUND, 10 TO GROUND FAILED INSULATION RESISTANCE TEST IAW STEP (2) TABLE (2). FOUND PROBES S1-S4 AND CJ10 & CJ9 HARNESSES TO BE OUT OF LIMITS PER EGT SYSTEM INSPECTION AMM 77-21-01-200-801-F00. REPLACED ALL 4 PROBES PER AMM 77-21-01/401. OPS CHECK GOOD, REPLACED THE CJ9 & CJ10 HARNESS IAW AMM 73-21-06/401. ALL OPS CHECK OF THE CJ9 & CJ10 HARNESS COMPLETE. ACCOMPLISHED POWER ASSURANCE TEST 5 & ACTUATORS TEST 12 OF AMM 71-00-00-700, ALL INDICATIONS AND PARAMETERS WITHIN LIMITS.