Service difficulty report · Shutoff Valve · Emb ERJ190100IGW

Difficulty date
June 18, 2011
Submitted
September 9, 2011
Operation
Air carrier
Make and model
Emb ERJ190100IGW
Aircraft time
8,643 hours
Engine
Ge CF3410E5A1
Part
Shutoff Valve
Part number
10012463
Condition
Failed
Location
Bleed Sys
Stage of operation
NR
How discovered
O
Nature of condition
O
Precautionary procedure
B

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

THE FLIGHT DISPATCHED UNDER MEL WITH NR1 BLEED INOP, AS THE FLIGHT CLIMBED THRU FL200. THE NR 2 BLEED FAILED. DID THE QRH PROCEDURE MSG EXTINGUISHED. THE FLIGHT DESCENDED TO 14000 FT AND MAINTAINED PRESSURE WITH THE APU BLEED AND CONTINUED NORMALLY TO DESTINATION. NR 2 ENG NAPRSOV INSTALLED IAW AMM 36-11-03-400-801-A LEAK CHECK C/OUT, NIL LEAK FOUND. OPS TEST OF BLEED SYS C/OUT IAW AMM 36-00-00-710-801-A, OPS CHECKED NORMAL.