Service difficulty report · Switch · Bombdr DHC8400

Difficulty date
September 14, 2011
Submitted
September 14, 2015
Operation
General aviation
Make and model
Bombdr DHC8400
Engine
Pwc PW150A
Part
Switch
Condition
Shorted
Location
Coffeemaker
Part time
853 hours
Stage of operation
CR
How discovered
9
Nature of condition
O
Precautionary procedure
O

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

(CAN) THE F/A RECEIVED AN ELECTRICAL SHOCK FROM THE RT COFFEEMAKER. THE COFFEEMAKER WAS REPLACED. PN 400-1794-02, SN 11-07-48811, ACFT TSN 853, CSN 580.