Service difficulty report · Fcu · Boeing 767209

Difficulty date
October 4, 1999
Submitted
March 26, 2000
Operation
Air carrier
Make and model
Boeing 767209
Engine
Pwa JT9D7R4D
Part
Fcu
Condition
Fluctuated
Location
Engine
Stage of operation
CR
Nature of condition
R, J
Precautionary procedure
O

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

(CAN) ENGINE EXPERIENCED EPR FLUCTUATIONS UP TO 21 EPR. N2 REMAINED STEADY, N1 FLUCTUATED UP TO 5 DEGREES. EEC'S REPLACED INDESCRIMINENTLY, SUBMITTER STATED FAILURE WAS DUE TO FCU TRIM CONTROL MAIN OVERRIDE PX.