SHIP 652 ERA 571971-14 SECTION I WAS ACCOMPLISHED IN MSP 23OCT18. FOLLOW ON ACTION IS REQUIRED FOR SECTION II. CORRECTIVE ACTION: REF ERA 571971-14 REV A. COMPLETE DTE RESULTS, SECTION II DT INSPECTIONS IS ADDED.
As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.
SHIP 652 ERA 571971-14 SECTION I WAS ACCOMPLISHED IN MSP 23OCT18. FOLLOW ON ACTION IS REQUIRED FOR SECTION II. CORRECTIVE ACTION: REF ERA 571971-14 REV A. COMPLETE DTE RESULTS, SECTION II DT INSPECTIONS IS ADDED.