What was found
DURING ACCOMPLISHMENT OF CPCP WORK CARD C53-224-01 REVEALED TWO MAIN AREAS OF CORROSION ON UPPER CHORD OF FS 1110 FLOORBEAM. REMOVED DAMAGED AREAS. FABRICATED AND INSTALLED REPAIRS PER SRM 53-10-8 FIGURE 3 AND 51-30-2. (M)
As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.
DURING ACCOMPLISHMENT OF CPCP WORK CARD C53-224-01 REVEALED TWO MAIN AREAS OF CORROSION ON UPPER CHORD OF FS 1110 FLOORBEAM. REMOVED DAMAGED AREAS. FABRICATED AND INSTALLED REPAIRS PER SRM 53-10-8 FIGURE 3 AND 51-30-2. (M)