What was found
DURING 4800/9600 HOUR STRUCTURAL INSP, FOUND CORROSION ON FUSELAGE SKIN FOUND AT STA 146.2-FUEL TANK RT OF CENTERLINE. REMOVED CORROSION, TREATED AREA AND INSTALLED DOUBLER FABRICATED FROM 2024T3 .032 -10" X 6" IN SIZE AT STA 146.2 - (7) INCHES RT OF CENTERLINE IAW SRM 53-00-00. CORROSION DAMAGE FOUND AT STA 200.2 - FUEL TANK LT OF CENTERLINE. REMOVED CORROSION, TREATED AREA AND INSTALLED DOUBLER FABRICATED FROM 2024 T3 .032 - 9" X 6" IN SIZE AT STA 200.2 - 18 INCHES LT OF CENTERLINE IAW SRM 53-00-00.