SDR MALA050260

Service difficulty report · Pump · Bac AVRO146RJ85A

Difficulty date
March 11, 2005
Submitted
March 17, 2005
Operation
Air carrier
Aircraft
N503XJ
Make and model
Bac AVRO146RJ85A
Aircraft serial
E2310
Aircraft time
15,696 hours, 15,435 cycles
Part
Pump
Condition
Malfunctioned
Location
Hyd System
Stage of operation
CR
How discovered
O
Nature of condition
M, J
Precautionary procedure
O

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

CREW REPORTED, RECEIVED GREEN HYDRAULIC HI TEMP. CREW FOLLWED QRH, THEN 45 MINUTES LATER CREW REPORTED YELLOW HYDRAULIC HI TEMP CAME ON. FOLLOWED QRH, AFTER FOLLOWING QRH FOR BOTH FAULT LIGHTS, THE LIGHTS WENT OUT. REPLACED NR 3 ENGINE DRIVEN PUMP FOR GREEN HYDRAULIC, YELLOW HYDRAULIC, GROUND RAN FOR 40 MINUTES AT HIGH POWER SETTINGS AND OPERATING ALL YELLOW SYSTEM HYD COMPONENTS. UNABLE TO DUPLICATE.