What was found
INITIAL INSPECTION: CORROSION ON FRAME FS613 BTW STGR 26L-26R AT FWD BAGGAGE BAY COMPARTMENT. (C1)(TCI: 53-20-306). CORROSION ON FRAME FS613 BTW STGR 26L-26R AT FWD BAGGAGE BAY COMPARTMENT WAS REMOVED PER CRJ-900 SRM 51-21-06-001-001-A01 AND BLENDED AREAS WERE MEASURED AND FOUND WHIT THE FOLLOWING DIMENTIONS: ORIGINAL THICKNESS: 0.063"", REMAINING THICKNESS IS 0.061"" THEREFORE IS WITHIN LIMITS PER CRJ-900 SRM 53-31-06-101-003-A04, LEVEL CORROSION 1.