Service difficulty report · Hose · Emb EMB145LR

Difficulty date
March 6, 2019
Submitted
March 8, 2019
Operation
Air carrier
Aircraft
N922AE
Make and model
Emb EMB145LR
Aircraft serial
14500906
Aircraft time
34,772 hours, 30,014 cycles
Part
Hose
Condition
Damaged
Location
Ac Bay
Stage of operation
CL
How discovered
O
Nature of condition
J
Precautionary procedure
B

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

SUPPLEMENTAL CABIN ALT WAS 9000' AND CLIMBING AS WE STARTED DESCENT THROUGH FL240. WE BEGAN RAPID DESCENT TO 10,000'. CABIN ALT WAS MAXED AT 11,300' THE BEGAN DESCENDING. C/A-DEFERRED ELECTROPNUEMATIC AND PNEUMATIC OUTFLOW VLVS. M PROCEDURES C/W MEL 21-22 AUTH 030207DMC. PERFORMED FIM T/S 21-31-00-810-808A THRU STEP 9. FOUND AIR LEAKAGE FROM MAIN DOOR UPPER FLAP, NR 1 DUAL TEMP VALVE COUPLING AND CARGO DOOR SEAL. ALL ITEMS HAVE BEEN REPAIRED AS PER AMM 52-18-04, AMM 21-60-01, AND AMM 52-00-04. PERFORMED CABIN LEAKAGE TEST I/A/W AMM 21-31-00-700-808 A/500. LEAKS CHECK OK. MEL RESTORED. RESECURED MAIN DOOR UPPER FLAP SEAL WITH RTV 157 IAW AMM 52-18-04. APPLIED RTV AT 2PM. REMOVED AND REAPPLIED SEALANT BETWEEN BAGGAGE DOOR PROTECTOR STRIP AND ALUMINUM SKIN AS PER AMM 53-31-09. SEALANT APPLIED AT 9:45 PM. REMOVED AND REPLACED RUBBER HOSE FOR PACK 1 DUAL TEMP CONTROL VALVE AND Y-DUCT AS PER AMM 21-60-01. OPC AND LEAK CHECK GOOD.

More about the Emb EMB-145LR