Service difficulty report · Sidewall Support · Boeing 7377H4

Difficulty date
August 19, 2021
Submitted
September 27, 2021
Operation
Air carrier
Aircraft
N208WN
Make and model
Boeing 7377H4
Aircraft serial
29856
Aircraft time
52,294 hours, 30,932 cycles
Part
Sidewall Support
Condition
Corroded
Location
Bs 500-500a
Stage of operation
IN
How discovered
9
Nature of condition
O
Precautionary procedure
K

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

CORROSION ON FLOOR TO SIDEWALL SUPPORT AT FWD CARGO BAY BS500 - BS500A LBL23 WL156. ; / [01] L/H FLOOR TO SIDEWALL SUPPORT WAS REMOVED ON CUSTOMER CARD:TTG8Q004E8Y8; [02] BLENDED CORROSION ON LH FLOOR TO SIDEWALL SUPPORT FROM BS 500- BS 500A. REMOVED .011' (AT DEEPEST BLEND) MATERIAL IN A AREA MEASURING .6' X .6'. ORIGINAL THICKNESS IS .040' THEREFORE THE PART IS OUT OF LIMITS BECAUSE MATERIAL REMOVAL EXCEEDS 10% OF MATERIAL THICKNESS PER SRM 53-00-53-1A-2. STEP 4. A (2) FIGURE 103<BR><BR>PART REQUIRES REPLACEMENT<BR><BR>DEPTH GUAGE USED:<BR>ID:ATS401<BR>S/N: UNKNOWN<BR>DATE:07/2021<BR>DUE:07/2022; [03] VERIFIED FLOOR TO SIDEWALL SUPPORT AT BS500-500A BLEND OUT EXCEEDS ALLOWABLE LIMITS PER SRM 53-00-53-1A-2. STEP 4. A (2) FIGURE 103; [04] FABRICATED AND DRILLED NEW FLOOR TO SIDEWALL SUPPORT AT BS 500-500D LBL23 WL 156 PER SRM 51-40-05-0G-0 AND DWG 143A7501.-; [05] VERIFIED LOCATE AND DRILL OF THE BS500-500D FLOOR TO SIDEWALL SUPPORT PER SRM 51-40-05-0G-0 AND DWG 143A7501. OK TO APPLY CHEMICAL CONVERSION AND PRIME REPAIR PARTS.; [06] APPLIED CHEMICAL CONVERSION COATING AND PRIMER ON FLOOR TO SIDEWALL AT FCB BS 500-500D LBL23 WL 156.- IAW 737-700; AMM 51-21-72-370-804; AMM 51-21-41-370-802 OK TO APPLY FINAL PAINT AND INSALL; [07] VERIFIED CHEMICAL CONVERSION AND PRIMER PER AMM 51-21-72-370-804; AMM 51-21-41-370-802. OK TO PAINT ENAMEL AND INSTALL; [08] INSTALLED FCB FLOOR TO SIDEWALL SUPPORT BS500 - BS500A; LBL23; WL 156 PER SRM 51-40-02-0G-0 AND BOEING DWG 143A7500;