CORROSION ON FRAME SPLICE AT AFT CARGO BAY BS787 RBL25 WL158. ; / [01] CORROSION ON SPLICE WAS FOUND TO BE OUT OF LIMITS DUE TO NO LIMITS ARE GIVEN IN THE SRM.; [02] VERIFIED CORRECTIVE ACTION STEP 1.; [03] REMOVED ACB FRAME SPLICE BS787; RBL25; WL158. PER SRM 51-40-02-0G-0; [04] LOCATED AND DRILLED NEW ACB FRAME SPLICE BS787; RBL25; WL158. PER DWG 146A1262 AND SRM 51-40-05-0G-0. OK TO INSTALL.; [05] VERIFIED LOCATED AND DRILLED NEW ACB FRAME SPLICE BS787; RBL25; WL158. PER DWG 146A1262 AND SRM 51-40-05-0G-0. OK TO INSTALL.; [06] INSTALLED NEW ACB FRAME SPLICE BS787; RBL25; WL158. PER DWG 146A1262 AND SRM 51-40-02-0G-0.; [07] VERIFIED INSTALLED NEW ACB FRAME SPLICE BS787; RBL25; WL158. PER DWG 146A1262 AND SRM 51-40-02-0G-0.