What was found
SUPPLEMENTAL INFORMATION: FLOOR SUPPORT ANGLE CORRODED STA 706+8; WL-208; RBL-60 ; / [01] CORRECTION TO FAULT SHOULD BE RBL-63; [02] REMOVED 1EA FASTENER AT BS 706+8 RBL 65 OF CREASE BEAM IAW SRM 51-40-02; [03] VERIFIED APPLICABILITY OF SRM 53-40-13-0I-1 AND SRM 53-40-13-1A-1. REMOVED DAMAGE ON FLOOR SUPPORT ANGLE AT BS 706+8; WL 208; RBL 65 IAW SRM 51-10-02. AREA OF DAMAGE REMOVED IS 2.2'X1.1'. ORIGINAL THICKNESS FOUND TO BE 0.071' IAW SRM 53040-13-0I-1. WILL REQUEST NDI TO VERIFY REMAINING THICKNESS.; [04] CORRECTION OF RBL. SHOULD BE RBL 63; [05] CORRECTION OF RBL. SHOULD BE RBL 63; [06] VERIFIED; [07] VERIFIED CORRECTIVE ACTION 2-5; [08] UT INSPECTED BLENDED AREA IAW 737 NDTM PART 4 51-00-00 PROCEDURE 2; REMAINING THICKNESS IS 0.068' ADJACENT TO 0.071'. <BR>EQUIP ID#: ATS2031 S/N: 170515011; [09] AREA OF DAMAGE REMOVAL FOUND TO BE IN LIMITS IAW SRM 53-40-13-1A-1 STEP 4.A.(2) FIG. 103 F WITH ONLY 0.003' MATERIAL LOSS 0F 0.071' ORIGINAL THICKNESS.; [10] VERIFIED DAMAGE REMOVAL ON INNER CHORD FOUND IN LIMITS PER SRM 53-40-13-1A-1; WHILE VERIFYING DEPTH OF DAMAGE REMOVAL; FOUND ADDITIONAL CORROSION ON LOWER WEB (REF. FAULT TTG8Q009K39K); [11] APPLIED CHEMICAL CONVERSION COATING TO DAMAGE REMOVAL AREAS IAW SRM 51-20-01. OK TO PRIME.; [12] VERIFIED CORRECTIVE ACTION STEP 11 COMPLETE; [13] APPLIED PRIMER TO DAMAGE REMOVAL AREAS IAW SOPM 20-41-02; [14] INSTALLED 1EA FASTENER AT BS 706+8 RBL 65 OF CREASE BEAM IAW SRM 51-40-02;