What was found
R/H MAIN WHEEL FWD VAPOR BARRIER HAS CRACK RBL 25 + 7 TO RBL 25 + 9.5 DOWNWARD APPROX. 3.5' LONG LOWER END TERMINATES AT RIVET UNABLE TO SEE UPPER END TERMINATION POINT DUE TO STRUCTURE / R/H MAIN WHEEL WELL FWD VAPOR BARRIER HAS CRACK RBL 25+7 TO RBL 25+9.5 DOWNWARD APPROX 3.5' LONG LOWER END TERMINATES AT RIVET UNABLE TO SEE UPPER END TERMINATION POINT DUE TO STUCTURE.REPAIRED PER SRM 57-10-10-2R-2 REPAIR 2 PARAGRAPH 6. THIS IS AN INTERIM REPAIR AND REQUIRES A DETAILED VISUAL INSPECTION EVERY 3000 FLIGHT CYCLES. REF 57-10-10-2R-2 REPAIR 2 SECTIONS 1.C 2.C AND PARAGRAPH 6REPETITIVE ACTION REQUIRED:PERFORM A DETAILED VISUAL INSPECTION OF FWD VAPOR BARRIER REPAIR AT RBL 25+7 TO RBL 25+9.5. REF SRM 57-10-10-2R-2