What was found
GROUND POWER PANEL CUTOUT CRACKED AT THE SIX O CLOCK POSITION.<[01] REMOVED DAMAGE PER SRM 53-10-15-2R-4;[02] PERFORMED .040 INSURANCE CUT AFTER NDT PER SRM 53-10-15-2R-4;[03] PREFORMED SURFACE HFEC INSPECTION PART 6 ; 51-00-00 PROCEDURE 23;[04] INSPECTED WORK ABOVE;[05] FABRICATED REPAIR PARTS PER SRM 53-10-15-2R-4;[06] INSPECTED WORK ABOVE;[07] OK TO INSTALL REPAIR PARTS;[08] REPAIRED GROUND POWER PANEL REF SRM 53-10-15-2R-4.;[09] REPAIRED GROUND POWER PANEL REF SRM 53-10-15-2R-4. C/W INSPECTION