What was found
CORROSION ON BONDING JUMPER ANGLE SUPPORT OF AFT BOOST PUMP TANK 2 I/B TRAILING EDGE AT RT WING (2EA) 2024-600553<[01] REPLACED INBOARD TRAILING EDGE BONDING JUMPER SUPPORT ANGLE OF AFT BOOST PUMP TANK 2 AT RT WING (2 EA) IAW B737-800 AMM 28-22-41-400-801. STEP 3.H.(18);(20);(21);(22). AND PERFORMED RESISTANCE TEST IS OK. TOOL USED: BONDING METER PN:M1 MILLIOHM METER; S/N:DC007483; DUE DATE:29 JUL 25.;[02] REPLACED INBOARD TRAILING EDGE BONDING JUMPER SUPPORT ANGLE OF AFT BOOST PUMP TANK 2 AT RT WING (2 EA) IAW B737-800 AMM 28-22-41-400-801. STEP 3.H.(18);(20);(21);(22). AND PERFORMED RESISTANCE TEST IS OK. TOOL USED: BONDING METER PN:M1 MILLIOHM METER; S/N:DC007483; DUE DATE:29 JUL 25.