Service difficulty report · Channel · Cndair CL6002B19

Difficulty date
January 21, 2020
Submitted
March 10, 2020
Operation
Air carrier
Aircraft
N905EV
Make and model
Cndair CL6002B19
Aircraft serial
7632
Aircraft time
39,265 hours, 36,176 cycles
Part
Channel
Condition
Corroded
Location
Fuselage
Stage of operation
IN
How discovered
V
Nature of condition
O
Precautionary procedure
K

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

*PRESSURE FLOOR BEAM CHANNEL CORROSION FS409.00+128 €“ 559.00 LBL 9(R) (MARKED) (C CHECK) RO 3/7/2020 REMOVED CORROSION ON PRESSURE FLOOR BEAM CHANNEL FS409.00+128 THRU FS559.00 LBL 9(R). REF. CRJ200 SRM. ORIGINAL MATERIAL THICKNESS IN AREA IS .050" REF. DWG, REMAINING MATERIAL THICKNESS IN AREA IS .028" REF. NDT REPORT, MATERIAL LOSS IN AREA IS .022". AREA AT FLOOR BEAM FS 409.00+128 - 559.00 LBL 9(R) IS OUT OF LIMITS OF ALLOWABLE DAMAGE LIMITS OF 10 PERCENT REF. CRJ-200 SRM. COMPLETED PRESSURE FLOOR BEAM CHANNEL REPAIR REF BOMBARDIER REO. SEE CONTINUATION CARD FOR DETAILS.