What was found
UNABLE TO GET THE APU TO START. CREW TRIED TWO TIMES, NO JOY, CYCLED CB'S L-41 AND L42. THIRD ATTEMPT WAS NO GOOD. OK TO DEFER THE APU INOP PER MEL 4910B. OK TO DEFER APU INOP PER MEL 4910B. RPL- T-S PER TSM49-00-00-810- 899, RPLD ECB (59KD) PER MM49-61-34, APU OPS CHKS NORMAL NO FAULTS NOTED.