U/D STA 390 WL 380 RBL14 EMER LTS POWER PACK M5168 CAPACITY LOW FOUND DURING DEEP CYCLE TEST. EMER LTS PWR PACK M5168 BATT ASSY REPLACED & TESTED NORMAL AS PER AMM 33-51-04 REV 110 15 MAR 2024. OPS CHECK GOOD.
As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.
U/D STA 390 WL 380 RBL14 EMER LTS POWER PACK M5168 CAPACITY LOW FOUND DURING DEEP CYCLE TEST. EMER LTS PWR PACK M5168 BATT ASSY REPLACED & TESTED NORMAL AS PER AMM 33-51-04 REV 110 15 MAR 2024. OPS CHECK GOOD.