What was found
PIT - DURING Q-3/C-5 CHECK INSPECTION, FOUND LEVEL 1 CORROSION STATION 227 LONGERON 29R AT RIVET HEADS PREVIOUSLY RE WORKED CORROSION TASK NR C51-53300. SPLICED IN NEW SECTION OF LONGERON PER SRM 53-02 FIG 2. (M)
As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.
PIT - DURING Q-3/C-5 CHECK INSPECTION, FOUND LEVEL 1 CORROSION STATION 227 LONGERON 29R AT RIVET HEADS PREVIOUSLY RE WORKED CORROSION TASK NR C51-53300. SPLICED IN NEW SECTION OF LONGERON PER SRM 53-02 FIG 2. (M)