What was found
FLIGHT CREW REPORTED A COMPLETE LOSS OF NR 2 SYSTEM HYDRAULIC QUANTITY AND PRESSURE. ACCOMPLISHED QRH 10-11 PROCEDURE. R & R THE NR 2 PUMP IAW AMM 29-11-01. PERFORMED OPS & LEAK CHECK. OPS & LEAK CHECKED PASSED.
As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.
FLIGHT CREW REPORTED A COMPLETE LOSS OF NR 2 SYSTEM HYDRAULIC QUANTITY AND PRESSURE. ACCOMPLISHED QRH 10-11 PROCEDURE. R & R THE NR 2 PUMP IAW AMM 29-11-01. PERFORMED OPS & LEAK CHECK. OPS & LEAK CHECKED PASSED.