Service difficulty report · Diverter · Emb ERJ190100IGW

Difficulty date
December 3, 2018
Submitted
January 15, 2019
Operation
Air carrier
Aircraft
N267JB
Make and model
Emb ERJ190100IGW
Aircraft serial
19000065
Aircraft time
33,383 hours, 21,195 cycles
Part
Diverter
Condition
Broken
Location
Apu
Stage of operation
IN
How discovered
V
Nature of condition
O
Precautionary procedure
K

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

DURING HEAVY MAINTENANCE AT YRQ FOUND WITH A SECTION OF APU OIL COOLER AIR INLET DIVERTER (P/N: 170-50258-005) FOUND BROKEN AND MISSING. ALSO, WHILE INVESTIGATION OF AFFECTED AREA, YRQ FOUND APU COMPARTMENT RT UPPER PANEL CRACKED AT 6 PLACES. DVI AND HFEC INSPECTIONS CARRIED OUT TO DETERMINE FULL EXTEND OF THE CRACKS. SEE REF/2/ DEFINITION SHEET, FIGURE 1 FOR MORE DETAILS. THE DAMAGE AREA WAS EVALUATED PER THE REF/3/ SRM REPAIR AND IT WAS DETERMINED THAT IT IS NOT ALLOWED IN THIS AREA. CONTACTED AND PROVIDED THE REF/1/ ETD REQUIRING THE REF/2/ REPAIR INSTRUCTIONS TO BE ACCOMPLISHED. THE REPAIR CONSIST OF ACCOMPLISH A DOUBLER REPAIR PER THE RED/3/ SRM WITH DEVIATION OF DOUBLER CROSSING FASTENER ROW AND ALLOWS FOR THE INSTALLATION OF (1) ROW OF FASTENERS AS SHOWN IN FIGURE 2 OF THE REF/2/ REPAIR. IT ALSO REQUIRES THE INSTALLATION OF FLOW DIVERTER (P/N 170-50400-001) USING THE INSTRUCTIONS WITHIN THE REF/4/ SB190-49-0005. REF/4/ SB HAS BEEN PARTIALLY COMPLETED. NOTE: THIS IS THE ONLY AIRCRAFT IN THE FLEET THAT HAS THE REF/4/ SB MOD DIVERTER (P/N 170-50400-001) INSTALLED. THIS WAS REQUIRED ON THIS REPAIR FOR 2 REASONS (1. THE PRE-MOD PN 170-50258-005 WAS NOT PROCURABLE AND 2. DUE TO THE SHAPE OF THE PRE-MOD DIVERTER IT WOULD INTERFERE WITH THE REPAIR DOUBLER). FOR THESE REASONS THE POST MOD DIVERTER WAS INSTALLED. THE REF/1/ ETD REPAIR HAS A 5000FH LIFE LIMITATION AND A 600 FH RE-INSPECTION REQUIREMENT. EC E18-1003-01 ACCOMPLISHES THE REF/1/ ETD REPAIR WITHOUT DEVIATION. EC E18-1003-02 ACCOMPLISHES THE POST REPAIR INSPECTIONS (EXTERNAL DVI) EVERY 600 FH PER THE REF/1/ ETD REPAIR WITHOUT DEVIATION. EC E18-1003-03 TRACKS THE REPAIR LIMITATION OF 5000FH PER THE REF/1/ ETD WITHOUT DEVIATION; THIS REPAIR IS APPROVED PER REF /1/ ETD AND IS CLASSIFIED AS TEMPORARY WITH POST REPAIR INSPECTIONS AND MAJOR.