TextPartly OCR
Some pages are OCR from a scan. OCR can misread letters and numbers.
Query with SQL
duckdb -csv -c "SELECT p.page, p.text_source, p.text, f.rights_holder, f.license FROM 'https://openairdocs.org/data/latest/service_document_file_page.parquet' p JOIN 'https://openairdocs.org/data/latest/service_document_file.parquet' f USING (file_sha256) WHERE p.file_sha256 = '3c2b9af4c2e6bcec26a62d059d027e01b8c53be96864bf9c98ce26190fc31fc0' ORDER BY p.page"
Prints the whole list as CSV. It reads the release’s Parquet files over HTTPS, so there’s nothing to download first. Install DuckDB to run it.
SELECT p.page, p.text_source, p.text, f.rights_holder, f.license FROM 'https://openairdocs.org/data/latest/service_document_file_page.parquet' p JOIN 'https://openairdocs.org/data/latest/service_document_file.parquet' f USING (file_sha256) WHERE p.file_sha256 = '3c2b9af4c2e6bcec26a62d059d027e01b8c53be96864bf9c98ce26190fc31fc0' ORDER BY p.page
Run it at the DuckDB prompt, or in any tool that reads Parquet over HTTPS. More ways to query the release are on Use the data.
GroupVariable Number 51PW531 - PW533 1PW534 51PW535 - PW537 49PW538 - PW550 1PW556 49PW557 55PW561 - PW564 1PW571 55PW572 - PW574 53PW575 - PW576 51PW591 1PW592 51PW593 - PW595 49PW596 51PW611 - PW612 1PW613 - PW615 51PW616 47PW617 - PW619 1PW620 47PW621 - PW622 51PW631 - PW632 49PW633 - PW636 1PW637 51PW661 - PW662 49PW681 - PW683 49PW701 - PW702 53PW711 - PW717 52PW741 49PW742 49PW761 49PW771 50PW831 50PW851 - PW856 Export Controlled ECCN: 9E991 - BOEING PROPRIETARY - Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 08, 2019 737-57A1321 37 of 289 BOEING SERVICE BULLETIN 737-57A1321
ALERTALERT
2. Spares Affected None.
B. Concurrent Requirements None.
C. Reason Accomplishment of this service bulletin will reduce the risk of ignition sources in the fuel tanks. If this service bulletin is not done, there is a higher risk of ignition sources in the fuel tanks which can cause a fire or an explosion.
Boeing has found that some fuel tank fasteners can be an ignition source if a fault current or hot short occurs. A detailed analysis of the fault current threats was done to find the configuration necessary to safely conduct the fault current threats without causing sparks in the fuel tanks. Application of sealant on the fasteners in the fuel tanks at the wing rear spars, front spars and upper wing rib shear ties decreases the risk of ignition sources at those fuel tank fastener locations. In addition, external to the fuel tanks at locations along the wing rear spars, front spars, the forward cargo compartment station 540 bulkhead and the main wheel well station 663 bulkhead, installation of cushion clamps over Teflon sleeves on wire bundles decreases metal-to-metal contact between the clamps and their support brackets and will help prevent hot shorts.
This service bulletin gives instructions to seal fuel tank fasteners in the fuel tanks at the wing rear spars, front spars and upper wing rib shear ties. This service bulletin also gives instructions to install cushion clamps over Teflon sleeves on wire bundles external to the fuel tanks at locations along the wing rear spars, front spars, the forward cargo compartment station 540 bulkhead and the main wheel well station 663 bulkhead.
This service bulletin is the result of the safety assessments conducted by Boeing under Special Federal Aviation Regulation (SFAR) 88, Fuel Tank System Fault Tolerance Evaluation Requirements.
For Continued Airworthiness, the Structural Repair Manual (SRM) has been revised to add a new Section 51-80-01, GENERAL - LIGHTNING, ELECTRICAL WIRING AND EQUIPMENT FAULT CURRENT REQUIREMENTS.
Airworthiness Limitations (AWL's) 28-AWL-31 and 28-AWL-32, listed in the 737-300/400/500 section of 737-100/200/300/400/500 AWL's and Certification Maintenance Requirements (CMR's) document, D6-38278-CMR, are related to this service bulletin.
Boeing Service Related Problems (SRP) 737-SRP-57-0236 and 737-SRP-57-0296 are related to this service bulletin.
Boeing Fleet Team Digest (FTD) 737 FTD 57-10001 is related to this service bulletin.
D. Description Get access to the left main, right main and center fuel tanks. Seal fasteners on the rear spar, front spar and upper wing rib shear ties in the left main and right main fuel tanks. Seal fasteners on the rear spar and front spar in the center fuel tank.
Export Controlled ECCN: 9E991 - BOEING PROPRIETARY - Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 08, 2019 737-57A1321 38 of 289 BOEING SERVICE BULLETIN 737-57A1321
ALERTALERT
External to the fuel tanks, get access to the wire bundle installation along the left and right wing rear spars and front spars, the forward cargo compartment station 540 bulkhead and the main wheel well station 663 bulkhead. Replace wire bundle clamps and install Teflon sleeve under the clamps.
The work in this service bulletin is done in the maintenance zone(s) given below.
Group 1:
Affected Maintenance Zones ZoneModel 221, 305, 405737-300, 737-400, 737-500 Group 2-9, 16-35, 56-59:
Affected Maintenance Zones ZoneModel 221, 305, 405737-300 Group 10-15, 36:
Affected Maintenance Zones ZoneModel 221, 305, 405737-500 Group 37-55:
Affected Maintenance Zones ZoneModel 221, 305, 405737-400 E. Compliance The Federal Aviation Administration (FAA) will possibly release an Airworthiness Directive related to this service bulletin. The Airworthiness Directive will make the compliance tasks and times given in this service bulletin mandatory.
Group 2-59:
Boeing recommends that the modification given in this service bulletin be done within 5 years after the original issue date of this service bulletin.
Group 1:
Contact The Boeing Company for modification instructions and do the modification within 5 years after the original issue date of this service bulletin.
Export Controlled ECCN: 9E991 - BOEING PROPRIETARY - Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 08, 2019 737-57A1321 39 of 289 BOEING SERVICE BULLETIN 737-57A1321
ALERTALERT
F. Approval This service bulletin was examined by the Federal Aviation Administration (FAA). The changes specified in this service bulletin comply with the applicable regulations and are FAA approved, as well as European Aviation Safety Agency (EASA)/Joint Aviation Authorities (JAA) approved for all EASA/JAA approved airplanes listed in the service bulletin effectivity. This service bulletin and its approval were based on the airplane in its original Boeing delivery configuration or as modified by other approved Boeing changes.
If an airplane has a non-Boeing modification or repair that affects a component or system also affected by this service bulletin, the operator is responsible for obtaining appropriate regulatory agency approval before incorporating this service bulletin.
G. Manpower The table below shows an estimate of the task hours necessary to do this change for each airplane.
This estimate is for direct labor only, done by an experienced crew. Adjust the estimate with operator task hour data if necessary. The estimate does not include lost time. These are some examples of lost time:
• Time to adjust to the workplace
• Time to schedule the work
• Time to inspect the work
• Time to cure the materials
• Time to make the parts
• Time to find the tools.
Group 1:
Contact Boeing.
Group 2-59:
WORK PACKAGE 1 : FUEL TANKS - FASTENER SEALING Elapsed HoursTask HoursNumber of PersonsTask
7.2529.004Open Access
3.406.802FIGURE 1
0.500.501FIGURE 2
2.252.251FIGURE 3
4.509.002FIGURE 4
0.500.501FIGURE 5
2.254.502FIGURE 6
2.002.001FIGURE 7
2.002.001FIGURE 8
9.2036.804FIGURE 9
9.7539.004FIGURE 10
2.002.001FIGURE 11 Export Controlled ECCN: 9E991 - BOEING PROPRIETARY - Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 08, 2019 737-57A1321 40 of 289 BOEING SERVICE BULLETIN 737-57A1321
ALERTALERT
Group 2-59:
WORK PACKAGE 1 : FUEL TANKS - FASTENER SEALING Elapsed HoursTask HoursNumber of PersonsTask
2.002.001FIGURE 12
9.7539.004FIGURE 13
10.7543.004FIGURE 14
2.502.501FIGURE 15
3.503.501FIGURE 16
25.25101.004FIGURE 17
25.25101.004FIGURE 18
4.804.801FIGURE 19
3.903.901FIGURE 20
4.804.801FIGURE 21
3.903.901FIGURE 22
14.5529.102FIGURE 23
5.0020.004Close Access
(a)(a)TOTAL FOR EACH AIRPLANE
(a) Refer to Paragraph 3.B., Work Instructions to find the applicability of each figure. The total hours for an airplane can then be calculated.
Group 2-59:
WORK PACKAGE 2: EXTERNAL TO THE FUEL TANKS AT THE LEFT AND RIGHT WING
REAR SPAR - WIRE BUNDLE CLAMP REPLACEMENT AND TEFLON SLEEVE INSTALLATION Elapsed HoursTask HoursNumber of PersonsTask
1.001.001Open Access
5.5011.002FIGURE 24
5.5011.002FIGURE 25
5.5011.002FIGURE 26
5.5011.002FIGURE 27
5.5011.002FIGURE 28
5.5011.002FIGURE 29
1.001.001Close Access
(a)(a)TOTAL FOR EACH AIRPLANE
(a) Refer to Paragraph 3.B., Work Instructions to find the applicability of each figure. The total hours for an airplane can then be calculated.
Export Controlled ECCN: 9E991 - BOEING PROPRIETARY - Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 08, 2019 737-57A1321 41 of 289 BOEING SERVICE BULLETIN 737-57A1321
ALERTALERT
Group 2-59:
WORK PACKAGE 3: EXTERNAL TO THE FUEL TANKS AT THE LEFT AND RIGHT WING
FRONT SPAR - WIRE BUNDLE CLAMP REPLACEMENT AND TEFLON SLEEVE INSTALLA- TION Elapsed HoursTask HoursNumber of PersonsTask
0.500.501Open Access
4.4517.804FIGURE 30
4.4517.804FIGURE 31
4.4517.804FIGURE 32
0.500.501Close Access
(a)(a)TOTAL FOR EACH AIRPLANE
(a) Refer to Paragraph 3.B., Work Instructions to find the applicability of each figure. The total hours for an airplane can then be calculated.
Group 2-59:
WORK PACKAGE 4 - EXTERNAL TO THE FUEL TANKS AT THE FORWARD CARGO COM- PARTMENT STATION 540 BULKHEAD - WIRE BUNDLE CLAMP REPLACEMENT AND
TEFLON SLEEVE INSTALLATION Elapsed HoursTask HoursNumber of PersonsTask
0.650.651Open Access
2.752.751FIGURE 33
2.752.751FIGURE 34
2.752.751FIGURE 35
2.752.751FIGURE 36
2.752.751FIGURE 37
0.650.651Close Access
(a)(a)TOTAL FOR EACH AIRPLANE
(a) Refer to Paragraph 3.B., Work Instructions to find the applicability of each figure. The total hours for an airplane can then be calculated.
Group 2-59:
WORK PACKAGE 5 - EXTERNAL TO THE FUEL TANKS AT THE MAIN WHEEL WELL STA- TION 663 BULKHEAD - WIRE BUNDLE CLAMP REPLACEMENT AND TEFLON SLEEVE IN-
STALLATION Elapsed HoursTask HoursNumber of PersonsTask
0.600.601Open Access
3.3013.204FIGURE 38
3.3013.204FIGURE 39 Export Controlled ECCN: 9E991 - BOEING PROPRIETARY - Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 08, 2019 737-57A1321 42 of 289 BOEING SERVICE BULLETIN 737-57A1321
ALERTALERT
Group 2-59:
WORK PACKAGE 5 - EXTERNAL TO THE FUEL TANKS AT THE MAIN WHEEL WELL STA- TION 663 BULKHEAD - WIRE BUNDLE CLAMP REPLACEMENT AND TEFLON SLEEVE IN-
STALLATION Elapsed HoursTask HoursNumber of PersonsTask
3.3013.204FIGURE 40
3.3013.204FIGURE 41
3.3013.204FIGURE 42
3.3013.204FIGURE 43
3.3013.204FIGURE 44
1.151.151Close Access
(a)(a)TOTAL FOR EACH AIRPLANE
(a) Refer to Paragraph 3.B., Work Instructions to find the applicability of each figure. The total hours for an airplane can then be calculated.
H. Weight and Balance Changes The below weight and balance changes are after all work packages in Paragraph 3.B., Work Instructions have been done.
Change in Moment (Pound-Inches) Change in Weight (Pounds)Airplane
(a)(a)Group 1 6822.311.3Group 2 5531.09.2Group 3-7, 20-21, 23-24, 30, 56-59 7468.012.4Group 8-9 5337.38.9Group 10-11, 17-19, 36-39, 46, 49-50 5251.28.7Group 12, 54 6176.710.3Group 13, 15, 22, 25-27, 31-33, 35, 40-43, 45, 47, 51-53 6198.210.3Group 14, 29, 34, 44, 48 4691.77.8Group 16 5939.99.9Group 28 7123.611.8Group 55
(a) Contact Boeing.
I. Electrical Load Data Not changed.
Export Controlled ECCN: 9E991 - BOEING PROPRIETARY - Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 08, 2019 737-57A1321 43 of 289 BOEING SERVICE BULLETIN 737-57A1321
ALERTALERT
J. References
1. Existing Data:
a. Boeing Service Related Problem (SRP) 737-SRP-57-0236, 737-SRP -57-0296
b. Service Bulletin Index D6-19567
c. Standard Overhaul Practices Manual (SOPM) 20-30-93, 20-50-01
d. Standard Wiring Practices Manual (SWPM) 20-00-11, 20-10-11, 2 0-10-12, 20-10-19
e. 737 Fleet Team Digest (FTD) 57-10001
f. 737-300/400/500 Aircraft Maintenance Manual (AMM) 12-31-61, 25-52-81, 27-61-00, 27-81-00, 28-10-00, 28-11-00, 28-11-11, 28-11-31, 28-23-00, 32-00-01, 52-31-00
2. Data Supplied with this Service Bulletin:
None.
3. Installation Drawings Used in the Preparation of this Service Bulletin:
TitleDrawing Number FRONT SPAR INSTALLATION - WING65-45320 REAR SPAR INSTALLATION - WING65-45321 FRONT SPAR INSTALLATION - WING CENTER SECTION65-45401 REAR SPAR INSTALLATION - WING CENTER SECTION65-45402 RIB INSTL-WBL 135.565-45445 RIB INSTL-WBL 157.0065-45446 RIB INSTALLATION-INSPAR, WBL 183.4065-45447 RIB INSTL-INSPAR, WBL 198.6065-45449 WIRE BUNDLE INSTALLATION - L. H. LEADING EDGE & FRONT SPAR SECTION 20 WBL 71.24 TO FSS 626.93 65-48301 WIRE BUNDLE INSTALLATION - R. H. LEADING EDGE & FRONT SPAR SECTION 20 WBL 71.24 TO FSS 626.93 65-48302 WIRE BUNDLE INSTALLATION - L. H. REAR SPAR RSS 259.38 TO RSS 652.9 SECTION 20 65-48307 WIRE BUNDLE INSTALLATION - R. H. REAR SPAR RSS 259.38 TO RSS 637.96 SECTION 20 65-48308 WIRE BUNDLE INSTALLATION - L. H. FILLET AREA & REAR SPAR SECTION 20 WBL 71.24 TO RSS 259.38 65-48309 WIRE BUNDLE INSTALLATION - R. H. FILLET AREA & REAR SPAR SECTION 20 WBL 71.24 TO RSS 259.38 65-48310 Export Controlled ECCN: 9E991 - BOEING PROPRIETARY - Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 08, 2019 737-57A1321 44 of 289 BOEING SERVICE BULLETIN 737-57A1321
ALERTALERT
TitleDrawing Number
WIRE BUNDLE INSTALLATION - FORWARD CARGO COMPART- MENT STATION 380 - 540 & FLOOR BEAMS STATION 380 - 727 65-48331
WIRE BUNDLE INSTALLATION - MAIN WHEEL WELL STATION
663.75 - 727 65-48339 The table above lists applicable drawings used to prepare this service bulletin. The drawings are not necessary to make the specified changes, and are not supplied with this service bulletin. The drawings may not be applicable to all airplane configurations or operators.
K. Publications Affected
1. Publications:
Chapter-SectionPublication Section C.1 Fuel Systems Ignition Prevention, 737- 300/400/500 Maintenance Planning Data 28-AWL-31 and 28-AWL-32 D6-38278-CMR, 737-12345 Airworthiness Limitations/Certification Maintenance Requirements
2. Damage Tolerance Based Structural Inspections:
Boeing has evaluated the repairs and/or changes in this service bulletin for effects on Fatigue Critical Structure (FCS) and for changes to Damage Tolerance Inspections (DTI) required in the Maintenance Program. This service bulletin affects FCS but no new DTIs are necessary.
L. Interchangeability and Intermixability of Parts Accomplishment of this service bulletin does not affect interchangeability or intermixability of parts.
M. Software Accomplishment Summary Not affected.
Export Controlled ECCN: 9E991 - BOEING PROPRIETARY - Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 08, 2019 737-57A1321 45 of 289 BOEING SERVICE BULLETIN 737-57A1321
ALERTALERT
Export Controlled ECCN: 9E991 - BOEING PROPRIETARY - Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 08, 2019 737-57A1321 46 of 289 BOEING SERVICE BULLETIN 737-57A1321
ALERTALERT
BLANK PAGE
2. MATERIAL INFORMATION A. Material - Price and Availability The operator can supply the parts and materials shown in Paragraph 2.C., Parts Necessary for Each Airplane . As an alternative, operators can purchase the parts from Boeing Spares. This service bulletin does not show the Boeing price and supply data.
B. Industry Support Information Boeing warranty remedies are not available for the configuration changes given in this service bulletin.
C. Parts Necessary for Each Airplane
1. Kits/Parts None.
2. Parts and Materials Supplied by the Operator The following parts or materials are necessary to do the change in this service bulletin. Parts and materials in the manuals given in Paragraph 1.J., References, can also be necessary. Examine operator part and material supply to make sure all necessary parts and materials are available.
NotesNameQTYPart Number / Specification
(a)CUSHION CLAMP294BACC10JU(103 thru 109); or BACC10GU(101 thru 109)
(b)TEFLON SLEEVE120 FEETTFE-2X, STANDARD WALL
(c)TEFLON TAPE20 FEETPTFE, GRADE D, CLASS 2
(d)LACING TAPE1200 FEETBMS13-54, TYPE III, CLASS 1, FINISH C, WHITE; or BMS13-54, TYPE III, CLASS 1, FINISH C, BLACK SEALANT10 OUNCES BMS 5-45, CLASS A-2, GRADE 1; or BMS 5-45, CLASS A-2, GRADE 2 SEALANT10 OUNCES BMS 5-45, CLASS B-2 WIPER5BMS 15-5, CLASS A, PROCESS CLEANING AB-
SORBENT WIPER
(a) The quantity and size of the clamp required can vary and depends on clamp location, wire bundle installation and airplane configuration. Refer to wire bundle FIGURES 24 thru 44, as applicable, for more information. Cushion clamps are available from Boeing.
(b) Use Teflon sleeve material that is twice the diameter of the wire bundle and will provide a minimum of a 50% circumferential overlap when cut and wound around the wire bundle. Refer to wire bundle FIGURES 24 thru 44, as applicable, for more information. Refer to SWPM 20-10-11 for supplier information.
(c) Refer to SWPM 20-00-11 for materials and supplier information. Teflon tape is used in APPENDIX A.
Export Controlled ECCN: 9E991 - BOEING PROPRIETARY - Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 08, 2019 737-57A1321 47 of 289 BOEING SERVICE BULLETIN 737-57A1321
ALERTALERT
NotesNameQTYPart Number / Specification
(d) See the Qualified Products List at the end of the Boeing Material Specification (BMS) for supplier data.
3. Parts Modified and Reidentified None.
4. Parts Removed and Not Replaced None.
D. Parts Necessary to Change Spares None.
E. Special Tooling - Price and Availability None.
F. Special Tooling Necessary to do this Service Bulletin No special tools or equipment are necessary to do the change in this service bulletin. But, maintenance and overhaul tools in the manuals given in Paragraph 1.J., References, can be necessary. Examine operator tool supply to make sure all necessary tools are available.
Export Controlled ECCN: 9E991 - BOEING PROPRIETARY - Copyright © Unpublished Work - See page 1 for details.
Original Issue: February 08, 2019 737-57A1321 48 of 289 BOEING SERVICE BULLETIN 737-57A1321