Copy · RR SB-RB211-72J803_Rev2 · 26 pages

© Rolls-Royce plc. Filed by the FAA in regulations.gov docket FAA-2019-0425; AD 2020-25-04 incorporates this document by reference. Not covered by OpenAirDocs’ CC0 dedication.

TextPartly OCR

Some pages are OCR from a scan. OCR can misread letters and numbers.

Query with SQL
duckdb -csv -c "SELECT p.page, p.text_source, p.text, f.rights_holder, f.license
  FROM 'https://openairdocs.org/data/latest/service_document_file_page.parquet' p JOIN 'https://openairdocs.org/data/latest/service_document_file.parquet' f USING (file_sha256)
  WHERE p.file_sha256 = 'dba9f35d80e1a6014e7cb5f82ee91eae54a16e636bc4e4f0b64d2ac4c3a80b19'
  ORDER BY p.page"

Prints the whole list as CSV. It reads the release’s Parquet files over HTTPS, so there’s nothing to download first. Install DuckDB to run it.

This document transmits Revision 2 to Service Bulletin RB211-72-J803 and Revision 2 to the Supplement Document History Service Bulletin Revision Status Supplement Revision Status Initial Issue Dec.7/17 Initial Issue Dec.7/17 Revision 1 Jul.13/18 Revision 1 Jul.13/18 Bulletin Revision 2 Remove Incorporate Reason for change Pages 1 to 16 of the Service Bulletin Pages 1 to 23 of the Service Bulletin Updated to introduce On-wing applicability.

Supplement Revision 2 Remove Incorporate Reason for change All pages Page 1 Updated to introduce On-wing applicability.

Printed in Great Britain Apr. 1/19 RB211 TRENT 800 SERIES PROPULSION SYSTEMS SERVICE BULLETIN RB.211−72−J803 Transmittal - Page 1 of 2 Date

LIST OF EFFECTIVE PAGES The effective pages to this Service Bulletin following incorporation of Revision 2 to the Bulletin and Revision 2 to the Supplement are as follows:

Page Revision Number Revision Date Bulletin R 1 2 Apr.1/19 R 2 2 Apr.1/19 R 3 2 Apr.1/19 R 4 2 Apr.1/19 R 5 2 Apr.1/19 R 6 2 Apr.1/19 R 7 2 Apr.1/19 R 8 2 Apr.1/19 R 9 2 Apr.1/19 R 10 2 Apr.1/19 R 11 2 Apr.1/19 R 12 2 Apr.1/19 R 13 2 Apr.1/19 R 14 2 Apr.1/19 R 15 2 Apr.1/19 R 16 2 Apr.1/19 R 17 2 Apr.1/19 R 18 2 Apr.1/19 R 19 2 Apr.1/19 R 20 2 Apr.1/19 R 21 2 Apr.1/19 R 22 2 Apr.1/19 R 23 2 Apr.1/19 Supplement R 1 2 Apr.1/19 Printed in Great Britain RB.211−72−J803 Transmittal - Page 2

1. Planning Information A. Effectivity Boeing 777 RB211-TRENT875-17 Engines prior to Serial No. 51542 RB211-TRENT877-17 Engines prior to Serial No. 51542 RB211-TRENT884-17 Engines prior to Serial No. 51542 RB211-TRENT884B-17 Engines prior to Serial No. 51542 RB211-TRENT892-17 Engines prior to Serial No. 51542 RB211-TRENT892B-17 Engines prior to Serial No. 51542 RB211-TRENT895-17 Engines prior to Serial No. 51542 B. Concurrent Requirements None.

C. Reason

(1) Problem The current standard of upper bifurcation nose fairing assembly is susceptible to cracking at the right hand seal land, which may result in material loss.

The problem is believed to be attributed to several factors including higher than expected loads on the seal and a reduced damping of high cycle fatigue loads.

(2) Evidence The problem has been identified on a number of in-service engines.

(3) Substantiation The changes introduced by this Service Bulletin have been the subject of satisfactory engineering evaluation, supported by stress assessment and successful manufacturing trial by the manufacturer.

ENGINE - GAS GENERATOR FAIRINGS-ENGINE/POWER PLANT INTERSERVICES - INTRODUCTION OF A

REVISED UPPER BIFURCATION NOSE FAIRING ASSEMBLY FEATURING AN ADDITIONAL SUPPORT BRACKET ASSEMBLY - MOD.72-J803 Printed in Great Britain RB.211−72−J803 Page 1 of 23 Dec. 7/17 Apr. 1/19R

(4) Objective Incorporation of this Service Bulletin (Modification) is designed to maintain reliability.

(5) Effect of Bulletin on:

(a) Operation Not affected.

(b) Maintenance Affected (see 1.L. Other Publications Affected).R

(c) Overhaul Not affected.

(d) Repair Schemes Affected (affected Repair Schemes will be revised to include the part(s) introduced by this Service Bulletin).

(e) Interchangeability Affected (see 1.M. Interchangeability of Parts).

D. Description

(1) The changes are:

(a) A revised upper bifurcation nose fairing assembly is introduced similar to the existing item except for an additional bracket assembly at the right hand seal land and the associated attaching rivets.

(b) The forward array of rivet holes is moved upwards by 8,00 mm (0.315 in.).

(c) Two revised bolts are introduced to attach the seal block to the upper bifurcation nose fairing assembly similar to the existing items except for an increase in length.

(2) Existing upper bifurcation nose fairing assemblies may be reworked.

(3) This Service Bulletin is in two parts as follows:

(a) Part 1 New production and in-service applications.

Printed in Great Britain RB.211−72−J803 Page 2 Dec. 7/17 Apr. 1/19R

(b) Part 2 Reserved for possible future use.

E. Compliance

(1) ON-WING

OPTIONALR This Service Bulletin is optional and incorporation is subject to customer choice.

R R

(2) IN-SHOP

RECOMMENDED It is recommended that this Service Bulletin be accomplished on engines/powerplants at Non-modular rework level of Engine Refurbishment and Engine Check and Repair.

F. Approval The technical content of Modification 72-J803 was approved by a representative of the European Aviation Safety Agency (EASA) on Dec. 5/17 and was re-approved Aug.29/18, R R EASA certificate No. EASA.C.10063976.

G. Manpower

(1) On-wing

(a) To gain access:R 15 minutes (1 person) - EstimatedR

(b) Time to inspectR 3 hours (1 person) - EstimatedR Personnel with NDT level 2 training are required to carry out FPI inspection.

R R

(c) Time to rework:R 8 hours (2 persons) - EstimatedR

(d) Time to return to a serviceable condition:R 30 hours (2 persons) - EstimatedR Printed in Great Britain RB.211−72−J803 Page 3 Dec. 7/17 Apr. 1/19R

(2) In-shop Time to rework:

8R hours (2 persons) - Estimated NOTE: The parts affected by this Service Bulletin are accessible on-wing andR in-shop.

H. Material Price and Availability Modification kit not required; parts supplied as single line items.

For prices and availability of future spares see supplement to this Service Bulletin.

I. Tooling Price and Availability Special tools are not required.

J. Weight and Balance

(1) Weight change Plus 0,32 kg (0.7 lb).

(2) Moment arm 551 mm (21.7 in.) rearwards.

(3) Datum Power Plant Station (PPS) 100.

K. References

(1) Aircraft Maintenance Manual:R 72-03-14, Removal and InstallationR

(2) Engine Manual:R

(a) 72-03-00, Removal/InstallationR

(b) 72-03-14, ExaminationR

(3) Standard Practices Manual (SPM):R 70-42-28-300-005R Printed in Great Britain RB.211−72−J803 Page 4 Dec. 7/17 Apr. 1/19R

L. Other Publications Affected

(1) For effect on Illustrated Parts Catalogue (IPC) see 2. Material Information.

R R

(2) Aircraft Maintenance Manual:R 72-03-14, Removal and InstallationR M. Interchangeability of Parts It is essential that items within Part 1 are fitted as a set.

Printed in Great Britain RB.211−72−J803 Page 5 Dec. 7/17 Apr. 1/19R

2. Material Information A. Parts required to accomplish this Service Bulletin:

All Engines Part 1 of SB 72-03-14 FIG ITEM NO.

NEW PART NO.

QTY PART TITLE MAT OLD PART NO.

INSTR DISP 07811 AS48513 2 Bolt, bihex hd

(0.250 in. dia x 0.812 in.)

QZK AS48511 (1)(2) B. Parts to be reworked:

All Engines Part 1 of SB 72-03-14 FIG ITEM NO.

NEW PART NO.

QTY PART TITLE MAT OLD PART NO.

INSTR DISP 07250 KH75280 1 Fairing, nose upper bifurcation fairing assy

- FK25470 (1) C. New production parts:

The following parts will be made available as future spares in addition to those listed under A and B:

All Engines Part 1 of SB 72-03-14 FIG ITEM NO.

NEW PART NO.

QTY PART TITLE MAT OLD PART NO.

INSTR DISP 07397 KH75281 1 Bracket, assy - - (3)(4)(5) Printed in Great Britain RB.211−72−J803 Page 6 Dec. 7/17 Apr. 1/19R

FIG ITEM NO.

NEW PART NO.

QTY PART TITLE MAT OLD PART NO.

INSTR DISP 07399 NAS1398C4 A4 2 Rivet, blind universal hd (V80205)

- - (3)(4)(5)R 07403 NAS1398C4 A3 4 Rivet, blind, universal head (V80205)

- - (3)(4)(5)R 07405 AS16489 6 Rivet EEG - (3)(4)(5)(6)R 07405 AS16490 6 Rivet EEG - (3)(4)(5)(6)R 07405 AS16492 6 Rivet EEG - (3)(4)(5)(6)R D. Redundant Parts:

All Engines Part 1 of SB 72-03-14 FIG ITEM NO.

NEW PART NO.

QTY PART TITLE MAT OLD PART NO.

INSTR DISP 07265 - 6 Rivet, solid csk head EEG AS16488 (3)(7) 07401 - 2 Rivet, solid universal hd EEG AS16087 (3)(8) E. Instruction disposition codes:

(1) Not Interchangeable. The new part must not be replaced by the old part in isolation, and the old part must not be replaced by the new part in isolation.

(2) Old part may be used up on other applications.

(3) Part of fairing assembly at ATA chapter reference 72-03-14, Fig./Item

07-250.

(4) New part will not be made available as a spare for replenishment purposes.

(5) Item will not be listed in the Engine Illustrated Parts Catalogue (EIPC).

(6) Alternatives.

(7) Quantity required decreased from 24 to 18.

Printed in Great Britain RB.211−72−J803 Page 7 Dec. 7/17 Apr. 1/19R

(8) Quantity required decreased from 26 to 24.

Printed in Great Britain RB.211−72−J803 Page 8 Dec. 7/17 Apr. 1/19R

3. Accomplishment Instructions A. The revised upper bifurcation nose fairing assembly introduced by this Service Bulletin is interchangeable with the existing items only when installed as a full Service Bulletin set (see 1.M. Interchangeability of Parts).R Remove existing and install reworked upper bifurcation nose fairing assembly in accordance with current overhaul procedures (Engine Manual, 72-03-00, Removal/Installation), in-shop.

R R R Rework existing upper bifurcation nose fairing assemblies in accordance with Part C. of these Accomplishment Instructions, in-shop R R Remove, rework and install the upper bifurcation nose fairing assembly in accordance with Part D. of these Accomplishment Instructions, on-wing.

R R B. Rework the existing Upper Bifurcation Fairing Assembly (part number FK25470) (IPC ATA number 72-03-14, Fig/Item 07-250).

R R

GENERAL DATAR This task gives the procedure to modify the Upper Bifurcation Fairing Assembly by fitting a bracket to the lower Right Hand Seal Land.

R R Source demonstration is not necessary for this rework instruction.R TASKS identified by OP TASK are in the Engine Overhaul Processes Manual, TSD594-J.

R R TASKS identified by SPM TASK are in the Standard Practices Manual.R DescriptionR RR SymbolR MaterialR Upper Bifurcation Fairing Assembly R R TAKR Titanium AlloyR

EQUIPMENT AND MATERIALR clamping equipmentR degreasing equipmentR hand toolsR inspection equipmentR penetrant crack test equipmentR portable drill equipmentR rivet clampsR vibration peen equipmentR Consumable MaterialsR OMat 632R fluorescent penetrant high sensitivity - water washableR OMat 650R fluorescent penetrant medium sensitivity - post emulsifiedR Printed in Great Britain RB.211−72−J803 Page 9 Dec. 7/17 Apr. 1/19R

Consumable MaterialsR OMat 653R fluorescent penetrant medium sensitivity - water washableR NOTE: (1) To identify consumable materials, refer to Overhaul Materials Manual, OMat.

R R

(2) Additional consumable materials are included in Overhaul Processes referenced within this rework R R Special ToolsR None.R Expendable Parts:R

FIG/ITEMR PART NOR PART IDENTR QTYR 07-397R KH75281R Stiffening bracket (Item 1)R 1 offR Repair Parts:R

FIG/ITEMR PART NOR PART IDENTR QTYR 07-399R NAS1398C4A4R blind rivet (Item 2)R 2 offR 07-403R NAS1398C4A3R blind rivet (Item 3)R 4 offR 07-405R AN16489R solid rivet (Item 4)R 6 offR 07-405R AN16490R solid rivet (Item 4)R 6 offR 07-405R AN16492R solid rivet (Item 4)R 6 offR Printed in Great Britain RB.211−72−J803 Page 10 Dec. 7/17 Apr. 1/19R

Pages 13–24 of 26