What it approves
ONE-ONLY STC, S/N 6660: Replace the Cameron Balloons US basket, burner, and fuel tanks with Balloon Works 4.9A1 basket; F-1 Mirage burner; and the 3229, 3035, 3258 and 3661 fuel tanks can be installed onto the Cameron Balloons Model Z-90 via the standard snaplinks (carabiners).
What the certificate says
From the PDF’s text layer, without the form’s printed wording. Layout and order may differ; the PDF is the record.
Part 31 of the Federal Aviation Regulations. (See Type Certificate Data Sheet No. B3GL for complete certification basis)
Replace the Cameron Balloons US basket, burner, and fuel tanks with Balloon Works 4.9A1 basket; F-1 Mirage burner; and the 3229, 3035, 3258 and 3661 fuel tanks can be installed onto the Cameron Balloons Model Z-90 via the standard snaplinks (carabiners).
1. FAA Approved Balloon Flight Manual Supplement, dated July 12, 2012, or later FAA approved revisions required.
2. You cannot use descriptive data about this design change to duplicate other products. This approval is limited to the installation made in Cameron Balloons Model Z-90, S/N 6660, only. This STC does not permit manufacturing of parts for multiple installations.
Cameron Balloons U.S.
7399 Newman Blvd.
Dexter, MI 48130 B3GL Make : Cameron Balloons US Model : Z-90, S/N 6660
Date of application, May 3, 2012
Date of issuance : July 23, 2012
Original Signed By:
Karol Mordasiewicz ( Signature) Karol Mordasiewicz Airframe & Administrative Branch Chicago Aircraft Certification Office
( Title)
FAA FORM 8110-2-1(10-69) PAGE 2 of 2 PAGES
Number
ADs that name this STC · 0
An AD can apply because an STC is installed, or mention one in its text.
Approved models · 1
| Make | Model | Data sheet |
|---|---|---|
| Cameron Balloons US | Z-90 | B3GL |