Service difficulty report · Proximity Switch · Emb EMB145LR

Difficulty date
January 6, 2025
Submitted
January 13, 2025
Operation
Air carrier
Aircraft
N914JX
Make and model
Emb EMB145LR
Aircraft serial
145595
Aircraft time
44,137 hours, 33,862 cycles
Part
Proximity Switch
Part number
8005701
Part serial
42055
Condition
Failed
Stage of operation
CL
How discovered
O
Nature of condition
N
Precautionary procedure
A

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

CREW REPORTED- AIR RETURN TO BCT DUE TO LG AIR/GRND FAIL. CORR ACTION MX REMOVED NOSE WOW HARNESS W019 (PN:145-21495-403), SN:NA AND INSTALLED A CUSTOMER SUPPLIED “REPAIRED” HARNESS W019 (PN:145-21495-403), SN:NA REMOVED NOSE WOW SWITCH (PN:80-057-01), SN:42055 AND ISTALLED A CUSTOMER SUPPLIED “TESTED” SWITCH (PN:80-057-01), SN:24868. GAINED ACCESS TO LEFT AND RIGHT MLG WOW WIRING HARNESS. REMOVED L/H W510 PROXIMITY SWITCH P/N80-057-01 S/N 1711 AND INSTALLED CUSTOMER SUPPLIED 'TESTED" PROXIMITY SWITCH P/N80-057-01 S/N 1329 . REMOVED R/H W510 PROXIMITY SWITCH P/N80-057-01 S/N NA AND INSTALLED CUSTOMER SUPPLIED 'NEW" PROXIMITY SWITCH P/N80-057-01 S/N 1714 REMOVED RH W510 (PN:145-21586-406 SN:N/A) AND INSTALLED A CUSTOMER SUPPLIED "NEW" HARNESS (PN:145-21586-405 SN:JSX24-109). REMOVED RH W509 (PN:145-21585-405 SN:N/A) AND INSTALLED A CUSTOMER SUPPLIED "NEW" HARNESS (PN:145-21585-405 SN:N/A). REMOVED LH W510 (PN:145-21586-405 SN:N/A) AND INSTALLED A CUSTOMER SUPPLIED "REPAIRED" HARNESS (PN:145-21586-405 SN:N/A). REMOVED LH W509 (PN:145-21585-405 SN:N/A) AND INSTALLED A CUSTOMER SUPPLIED "REPAIRED" HARNESS (PN:145-21585-405 SN:N/A). PERFORMED VARIOUS SATISFACTORY OPS CHECKS.RESTORED AIRCRAFT TO ORIGINAL CONFIGURATION. NOSE PROXIMITY SWITCH P/N80-057-01, OFF S/N 42055 ; ON: 24868 NOSE HARNESS PN:145-21495-403#1 W510 PN:145-21586-405, NSN#1 W509 PN:145-21585-405, NSN#1 PROX SENSOR PN:80-057-01, OFF SN:1711; ON SN:1329#2 W510 PN:145-21586-405, NSN#2 W509 PN:145-21585-405, NSN#2 PROX SENSOR PN:80-057-01, OFF SN: NA; ON SN:1714. CHECKED CONTINUITY FOR RELATED RELAYS. VISUALLY INSPECTED HARNESS FOR WOW PROX SWITCHES ON BOTH MAINS AND NOSE. TESTED ALL WOW PROX SWITCHES. #1 ON THE RIGHT MAIN AND #2 ON THE LEFT MAIN FAILED REMOVED AND REPLACED WITH NEW WOW PROX SWITCHES P/N 80-527-01. PERFORMED AIR/GROUND SYSTEM OPS CHECK. CHECKED GOOD. NO DEFECTS AT THIS TIME.