Service difficulty report · Reservoir · Cndair CL6002B19

Difficulty date
August 18, 2009
Submitted
August 20, 2009
Operation
Air carrier
Aircraft
N8577D
Make and model
Cndair CL6002B19
Aircraft serial
7577
Aircraft time
18,246 hours, 15,379 cycles
Part
Reservoir
Part number
601R751203
Part serial
673
Condition
Bypassing
Location
Hydraulic Sys
Part time
18,246 hours, 15,379 cycles
Stage of operation
CL
How discovered
O
Nature of condition
J
Precautionary procedure
A

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

DEPARTED CAE EN ROUTE TO DTW. CLEARED TO FL 300, PASSING FL 240 EICAS CAUTION MESSAGE HYD 2 HI TEMP CHECKED SYSTEMS PAGE AND CONFIRMED HYD 2 HI TEMP IN EXCESS OF 135C. CONDITION CONFIRMED, QRH INITIATED. CONTACTED ATC, ADVISED OF SYSTEM PROBLEM AND COORDINATED STOP CLIMB AT F250. COMPLIED WITH QUICK REFERENCE HANDBOOK, CONFIRMED TEMPERATURE IN EXCESS OF 135 AND FOLLOWED PROCEDURES FOR ENGINE SHUTDOWN, AND SINGLE ENGINE LANDING. EMERGENCY DECLARED, NEAREST SUITABLE LANDING GREENSBORO, NC, ADVISED ATC AND DISPATCH AND WAS REDISPATCHED TO GSO. REQUESTED CRASH, FIRE, RESCUE MEET US ON LANDING. UNEVENTFUL LANDING GSO, TAXIED TO GATE WHERE PASSENGERS WERE DEPLANED NORMALLY AND ACCOMMODATED ON OTHER FLIGHTS TO DESTINATION. COORDINATED WITH DISPATCH, MOC, SOC AND LOCAL MAINTENANCE UNTIL RELEASE AT 1945Z. ASSISTANT CHIEF PILOT AND DTW OPS MANAGER ALSO ADVISED OF ACTIONS. MTX RAI NR 2 HYD RESERVOIR IAW CRJ AMM 29-11-32-400-802 OPS AND LEAK CHECK GOOD.