Service difficulty report · None · Boeing 737

Difficulty date
November 5, 2021
Submitted
April 29, 2022
Operation
Air carrier
Aircraft
N206WN
Make and model
Boeing 737
Aircraft serial
34011
Aircraft time
52,876 hours, 31,083 cycles
Part
None
Condition
Cracked
Location
R/H Horiz. Stab.
Stage of operation
IN
How discovered
9
Nature of condition
O
Precautionary procedure
K

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

SUPPLEMENTAL INFORMATION: RIGHT HAND HORIZONTAL STABILIZER INSPAR RIB; AT STABILIZER STATION 129.50; 3RD VERTICAL STIFFENER IS CRACKED. ; / [01] CUT AND REMOVED THE DAMAGE FROM THE VERTICAL STIFFENER AND WEB OF THE RIB PER SRM 55-10-09-2R-4.; [02] VERIFIED SRM 55-10-09-2R-4 IS APPLICABLE AND DAMAGE IS REMOVED; [03] HFEC INSPECTED OPEN HOLES IAW 737 NDTM PART 6 51-00-00 PROCEDURE 16; NO CRACKS NOTED. <BR>EQUIP ID#: IS000450 S/N: N500D000M120071 EQUIP ID#: ATS2407 S/N: MM1591DD064104; [04] HFEC INSPECTED CUT OUT IAW 737 NDTM PART 6 51-00-00 PROCEDURE 23; NO CRACKS NOTED. <BR>EQUIP ID#: IS000450 S/N: N500D000M120071; [05] FABRICATED REPAIR PARTS -1 T SECTION FROM 60-5872#7075T76511 0.063' LOT#1463116-1;-2 ANGLE FROM BAC1490-2793#7075T62 0.063' LOT#1464923-1;-3 SHIM FROM 7075T6 0.016' LOT#1351319-2. APPLY A CHEMICAL CONVERSION COATING TO THE REPAIR PARTS. PER SRM55-10-09-2R-4.; [06] ACCOMPLISHED GVI; NO ADDITIONAL FAULTS NOTED; PER SRM 55-10-09-2R-4 REPAIR 4 STEP 4.E. <BR><BR>VERIFIED CORRECTIVE ACTION 5 (FAB OF PARTS); [07] APPLIED A CHEMICAL CONVERSION COATING AND PRIMER TO THE REPAIR PARTS AND THE BARE SURFACES AND CUT EDGES OF THE RIB. PER SRM 55-10-09-2R-4. O.K TO INSTALL [09] INSTALLED REPAIR PARTS PER SRM 55-10-09-2R-4 STEPS 4 M-P.; [10] RII INSPECTED REPAIR PARTS INSTALLED PER SRM 55-10-09-2R-4.; [11] APPLIED FILLET SEAL AND FINISH TO REPAIR PARTS AND RIB ASSY. IAW SRM 55-10=09=2R-4 PARA. 4