Service difficulty report · Tie Down · Boeing 7377H4

Difficulty date
August 18, 2022
Submitted
September 27, 2022
Operation
Air carrier
Aircraft
N489WN
Make and model
Boeing 7377H4
Aircraft serial
33855
Aircraft time
57,460 hours, 34,246 cycles
Part
Tie Down
Condition
Corroded
Location
Aft Cargo
Stage of operation
IN
How discovered
9
Nature of condition
O
Precautionary procedure
K

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

CORROSION ON AFT CARGO BAY TIE DOWN AT LBL 17 BS 727D; BS 787. / [01] SRM 53-00-53-1A-2 IS FOUND TO BE APPLICABLE;[02] REMOVED CORROSION ON ACB TIE DOWN LBL 17 BS 727D L=1.4'XW=.5'XD=.055' FOUND TO BE OUT OF LIMITS WITH REMAINING THICKNESS OF .090' OF ORIGINAL THICKNESS .140'.<BR>BS 787 L=1.4'XW=.5'XD=.20' IS FOUND TO BE IN LIMITS WITH REMAINING THICKNESS OF .120' OF ORIGINAL THICKNESS 140' IAW SRM 53-60-53-0I-2; SRM 53-00-53-1A-2; BAC1520-1397 AND BOEING DWG 146A7501 <BR>DEPTH GAUGE USED ID:E9655 S/N:UNKNOWN DUE:03/2023;[03] VERIFIED CORRECTIVE ACTION ITEM 1-2.;[04] REMOVED ACB TIE DOWN FROM BS 727+4 TO BS 867; LBL 17; IAW SRM 51-40-02-0G-0.;[05] LOCATED AND DRILLED NEW ACB TIE DOWN FROM BS 727+4 TO BS 867; LBL 17 IAW BOEING DWG 146A7500 AND SRM 51-40-02;[06] OK TO INSTALL TIE DOWN TRACK AT LBL 17; BS 727+4 TO BS 867.;[07] VERIFIED CORRECTIVE ACTIONS 5; 6 AND MEASUREMENT FIELD;[08] INSTALLED TRACK IAW SRM 51-40-02-0G-0 AND DWG 146A7500 REV A.;[09] VERIFIED CORRECTIVE ACTION #8

More about the Boeing 737-7H4