What was found
AFTER FLOOR SUPPORT LBL 11 TO RBL 11 FS280 REMOVAL, CORROSION ON FLOOR STRUCTURE CROSSBEAM AT FS280.00. FLOOR STRUCTURE CROSSBEAM AT FS280.00 WAS REPLACED PER CRJ900 SRM 51-42-06-001-001-A01 AND CRJ900 SRM 51-42-21-001-001-A01
As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.
AFTER FLOOR SUPPORT LBL 11 TO RBL 11 FS280 REMOVAL, CORROSION ON FLOOR STRUCTURE CROSSBEAM AT FS280.00. FLOOR STRUCTURE CROSSBEAM AT FS280.00 WAS REPLACED PER CRJ900 SRM 51-42-06-001-001-A01 AND CRJ900 SRM 51-42-21-001-001-A01