Service difficulty report · Trim System · Cessna 750

Difficulty date
August 15, 2008
Submitted
May 14, 2009
Operation
Air carrier
Aircraft
N950QS
Make and model
Cessna 750
Aircraft serial
7500050
Aircraft time
8,767 hours, 5,557 cycles
Part
Trim System
Condition
Malfunctioned
Stage of operation
CL
How discovered
O
Nature of condition
F
Precautionary procedure
O

As reported to the FAA. Reports are unverified, and codes are left as the FAA publishes them.

What was found

CLIMBING THROUGH FL230 AT 270 KNOTS INDICATED, "RETRIM L WING DOWN" AP DISENGAGED & ACFT REQUIRED 50 PERCENT LT AILERON TRIM. TRIM STAYED 50 % LT UNTIL DESCENT WHEN WE HAD A "RETRIM R WING DOWN" AT FL200, 340 KIAS. FUEL BALANCED WITH ZERO CTR FUEL AT ALL TIMES TRIM REPOSITIONED TO NORMAL/CENTERED. ALL GROUND OPS & TRAVEL CHECKS GOOD. UPON INSP OF DAMAGE, FOUND FWD BAR DRAIN LINE BENT. REMOVED FOR INSP & CHECK DRAIN HEATERS FOR PROPER OPERATIONS. FOUND TOP HOSE CLAMP LOOSE & DRAIN HOSE ROUTED WRONG. RE-ROUTED DRAIN HOSE & TIGHTENED HOSE CLAMP, OPS CHECKED DRAIN & HEATERS FOR PROP OPS. IAW MM 38-30-02, PERFORMED TRAVEL LIMIT CHECKS, WITHIN LIMITS IAW MM 27-10-00 REV 31. PERFORMED VISUAL INSP OF FLAPS FOR DAMAGE, LOCKS IN NORMAL CONDITION NOTE ALL 3 FLAPS ARE TRIMMED FOR LT HEAVY COND. PERFORMED TENSION CHECKS IAW MM 27-10-00. JACKED ACFT. CHECKED CABLE TENSIONS IAW MM 27-10-00 REV 31 PERFORMED AILERON NEUTRAL ADJUSTMENT CHECKS, AILERO NEUTRAL IN LIMITS. PERFORMED AILERON TRAVEL CHECKS, IN LIMITS. PERFORMED CABLE TENSION CHECKS TO DOUBLE CHECK BEFORE PANELS ARE REINSTALLED. REINSTALLED ALL PANELS REMOVED, CHECKS IAW MM 27-10-00. PERFORMED OPS CHECK OF ALL FLT CONTROLS AND SERVICED HYD SYS. DOWNJACKED ACFT.